1723 - NON-METALLIC OFFSET BLOCKS FOR GUARDRAIL 1700-34
1723.1 Description
This specification governs non-metallic offset blocks for guardrail that are not covered under the wood post specification in DIVISION 2300 . Substitution for the wood offset blocks is permitted for line and bullnose guardrail sections as shown on the Contract Documents. Substitution within the end terminal sections is only permitted when specified by the manufacturer of the end terminal.
1723.2 Requirements
a. General.
1723.3 Test Methods
Test the ultraviolet (UV) protection of the block using ASTM G 155, “Practice for Operating Xenon Arc Light Apparatus for Exposure of Non-metallic Materials. ” Utilize Cycle #1 for 500 hours following Table X3. Use a sample size of 1 inch by 4 inch by 4 inch. Perform KTMR-31, “Solvent Resistance of Non-metallic Materials.” Obtain a copy of this test by contacting KDOT’s Quality Assurance Section in the Materials and Research Center. Determine the strength of 1 complete block in this manner: Apply the compressive force along the entire length and in the direction that is perpendicular to both the guardrail and post. Support the post track so no force is applied to edges. Blocks are required to have a minimum compressive stress of 450 psi. Calculate the pressure by using the average longitudinal cross section area. Use a properly calib rated compression machine as defined in ASTM E 4. Determine the water absorption of the block using ASTM D 2842, Procedure B, with the following exceptions: Use the actual width and thickness of the specime n instead of the specified 6 inch by 6 inch dimensions. Under 9. Conditioning, delete 9.2 and 9.3. Add 9.2 Cool to room temperature and weigh to the nearest 0.1 g. Change 9.4 to 9.3. Under 10. 2 Procedure B, maintain a water bath temperature of 77 + 2ºF. 1723 - NON-METALLIC OFFSET BLOCKS FOR GUARDRAIL 1700-35 When calculating the absorption, use this equation: %absorption = [((W2i – W3i) – (W2f – W3f))/(W2i – W3i)]X100
1723.4 Prequalification
To become prequalified, provide the Bureau of Cons truction and Materials with a copy of the FHWA letter showing the product has been accepted under the Natio nal Cooperative Highway Re search Program (NCHRP) Report 350. Blocks m ust be able t o c om ply with subsection 1723.3. Submit 4 offset blocks to the Engineer of Tests. The Bureau of Construction and Materials will mainta in a prequalified list of all complying manufacturers.
1723.5 Basis of Acceptance
The plant must be currently prequalified as specified in subsection 1723.4. Receipt and approval of a Type C certification as specified in DIVISION 2600. Visual inspection for voids as outlined in subsection 1723.2.b.