728 - BRIDGE CURB REPAIR 700-108

728.1 Description

Repair the bridge curb according to the Contract Documents. Use e ither the conventional method or the concrete surface repair-shotcrete method for placing the concrete. B I D I T E M U N I T S Bridge Curb Repair Linear Foot

728.2 Materials

Provide materials that comply with the applicable requirements. Concrete (Conventional Method) .......................................................................... SECTIONS 401 & 402 Concrete Surface Repair-Shotcrete ........................................................................ SECTION 826 Aggregate for Concrete Not On Grade .................................................................. SECTION 1102 Concrete Curing Materials .................................................................................... DIVISION 1400 Expansion Joint Materials ..................................................................................... DIVISION 1500 Reinforcement Materials ....................................................................................... DIVISION 1600 Epoxy Resin Base Bonding Systems ..................................................................... DIVISION 1700

728.3 Construction Requirements

Remove and dispose of the unsound concrete to the limits shown in the Contract Documents. Do not damage sound concrete that is to remain in-place. Repair any damage to the existing structure caused during removal. Prior to placing any new concrete, clean all reinforcing steel exposed during the removal of the unsound concrete. Apply an epoxy resin base bonding system to th e adjacent concrete surfaces before placing any new concrete. If epoxy resin dries, reapply another coating. If the new concrete is placed using conventional met hods, construct and cure the bridge curb according to

Division 700

If the new concrete is placed by the concrete surface repair-shotcrete method, apply the concrete according to SECTION 826.

728.4 Measurement and Payment

The Engineer will measure repaired bridge curb al ong the base of the curb by the linear foot. Payment for "Bridge Curb Repair" at the contract un it price is full compensation for the specified work.

Get an email when 728 changes

Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for State Road and Bridge Construction, 2015 Edition. Pages 439–439 of 978. View official source ↗