808 - REMOVAL OF EXISTING PAVEMENT MARKINGS 800-32

808.1 Description

Remove the existing pavement markings and symbols as shown in the Contract Documents. B I D I T E M S U N I T S Pavement Marking Removal Linear Foot Pavement Marking Removal (Plowable Raised Marker) Each

808.2 MATERIALS - None specified.

808.3 Construction Requirements

a. Removal of Existing Stripes and Symbols. Completely remove the existing pavement markings and symbols without damaging the asphalt or concrete pavement surface or longitudinal and transverse joints. Waterblasting will only be allowed for removal of markings on concrete surfaces. As th e work progresses, remove all material deposited on the pavement as a result of the removal operations. When blast cleaning within 10 feet of the traveling public, continuously remove all residue and dust. When replacement of the removed existing markings is a part of the Contract Documents, follow the manufacturer’s requirements for the new pavement markings as to the method of removal of the existing markings, or surface preparation requirements. b. Removal of Plowable Raised Markers. If the plowable raised markers ar e to be reinstalled, remove them without damaging. All damaged plowable raised markers will be replaced at the Contractor’s expense. c. Repair. Use methods approved by the Engineer to repair all pavement damaged during the pavement marking removal operations.

808.4 Measurement and Payment

The Engineer will measure the removal of each skip and solid line of existin g pavement marking by the linear foot. NOTE: Removal of temporary pavement marking is subsidiary to the temporary pavement marking bid item. The Engineer will measure each plowable raised marker removed. The Engineer will not measure removal of existing pavement marking symbols for payment. Payment for "Pavement Marking Removal" and "Pav ement Marking Removal (Plo wable Raised Marker)" at the contract unit prices is full compensation for the specified work.

Removal of Existing Pavement Markings in other states

Get an email when 808 changes

Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for State Road and Bridge Construction, 2015 Edition. Pages 523–523 of 978. View official source ↗