843 - FLOWABLE FILL 800-107

843.1 Description

Backfill the designated structures or excavations with flowable fill. B I D I T E M U N I T S F l o w a b l e F i l l ( * ) C u b i c Y a r d *Low Strength or High Strength

843.2 Materials

a. General. Provide materials that comply with the applicable requirements. Fine Aggregate ...................................................................................................... DIVISION 1100 Cement and Fly Ash (approved for stabilization & cold recycle) ......................... DIVISION 2000 Water ..................................................................................................................... DIVISION 2400 The Engineer will approve the use of admixtures to achieve flowability and acceptable set time, based on performance. b. Mix Design. Design a flowable fill mixture that possesses adequate flow characteristics to fill all voids, and complies with the compressive strength and unit weight requirements shown in TABLE 843-1. TABLE 843-1: REQUIREMENTS FOR FLOWABLE FILL MIXTURE LOW-STRENGTH MIXTURE HIGH-STRENGTH MIXTURE 3 Day Compressive Strength (minimum) 20 psi - 7 Day Compressive Strength (minimum) - 50 psi 28 Day Compressive Strength 100 psi (max) 1500 psi Unit Weight (maximum) 120 pcf - Obtain approval from the District Materials Engineer for the job mixture. Supply 3 and 28 day compressive strength information for low-strength mixtures, or 7 and 28 day compressive strength information for high-strength mixtures, along with the mix design. c. KDOT Assurance and Acceptance. The Engineer will make test cy linders for each 100 cubic yards of flowable fill placed, and whenever th e mixture is changed. The cylinders will be made and tested according to

Division 2500

 For the low-strength mixture, 3 cylinders will be made. The 1st cylinder will be tested on the 3rd day. The 2nd cylinder will be laboratory cured and tested on the 28th day. The 3rd cylinder will be laboratory cured and held in reserve to verify any questionable cylinder breaks.  For the high-strength mixture, 3 cylinders will be made. The 1 st cylinder will be tested on the 7 th day. The 2nd cylinder will be laboratory cured and tested on the 28th day. The 3 rd cylinder will be laboratory cured and held in reserve to verify any questionable cylinder breaks.  The Engineer will test the unit weight a minimum of every 50 cubic yards of flowable fill placed.  The Engineer will accept the flowable fill based on the results of the compressive strength and unit weight tests, and visual inspection of the mixture placed on the project.

843.3 Construction Requirements

Place the flowable fill in the excavation so all voids around the structure or in the excavation are filled. Place the flowable fill around structures in lifts preventing the buildup of excess hydrostatic pressure. Observe the weather limitations specified in DIVISION 400 when placing the flowable fill.

843.4 Measurement and Payment

The Engineer will measure flow able fill placed in the specified locations by the cubic yard. Payment for "Flowable Fill" at the contract unit price is full compensation for the specified work.

Get an email when 843 changes

Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for State Road and Bridge Construction, 2015 Edition. Pages 598–598 of 978. View official source ↗

Ask about this section

Scoped to Kansas KDOT Standard Specifications for Road & Bridge Construction, Section 843 — Flowable Fill. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.