851 – PAVEMENT WATERPROOFING MEMBRANE 800-117
851.1 Description
Install the pavement waterproofing membrane at the locations designated in the Contract Documents. This product is primarily used over localized pavement failures, over joints and cracks, and on bridge decks before an overlay. B I D I T E M S U N I T S Pavement Waterproofing Membrane Square Yard Pavement Waterproofing Membrane (*) Linear Foot * width
851.2 Materials
Provide pavement waterproofing membrane that meets DIVISION 1700. When the unit of measure is square yards, the minimu m width of material is 36 inches. When the unit of measure is linear foot, the width of material is that specified in the Contract Documents.
851.3 Construction Requirements
Provide the Project Engineer with a copy of the fabric manufacturer’s recommendations for installation. Before placing the pavement waterproofing membrane, clean the existing pavement or bridge deck of any dirt, debris or deteriorating paveme nt materials, according to the manufac turer’s recommendations. Clean milled surfaces with compressed air to remove all dust and files. Before placing the pavement waterproofing membrane on existing pavement, fill all holes and cracks wider than ½ inch in the existing pavement with approved crack filler. Remove and fill spalled areas greater than 3 inches in width with hot/cold-mix asphalt or a suitable crack filler. Before placing the pavement waterproofing membrane on an existing bridge deck, if necessary, place concrete patches on the existing bridge deck according to the details in the Contract Documents. Do not place the pavement waterproofing membrane un less the ambient and pavement temperatures are at least 50°F and rising. The pavement surface or bridge deck must be dry prior to installation. Apply a prime coat (at the rate recommended by th e manufacturer of the fabric) when recommended by the fabric manufacturer. In addition, apply a prime coat on th e existing pavement if the su rface has been milled, if the dry pavement temperature is below 70ºF, or if the application is on a bridge deck. Place the pavement waterproofing membrane according to the manufacturer’s recommendations. Overlap the pavement waterproofing membrane joints as recommended by the fabric manufacturer. When possible, construct the succee ding overlay as soon as recommende d by the manufacturer, without allowing any traffic on the membrane. When the succeeding overlay can not be immediately placed, open the roadway to traffic as recommended by the manufacturer. Construct th e succeeding overlay with in 10 calendar days of placing the pavement waterproofing membrane. On slopes greater than 5%, construct the overlay within 48 hours. Remove and replace all pavement wa terproofing membrane that is dama ged before it is covered with the overlay.
851.4 Measurement and Payment
When the unit of measure specified in the Contract Documents is linear foot, the Engineer will measure each individual strip of pavement waterproofing membrane placed by the linear foot. When the unit of measure specified in the Contract Documents is square yard, the Engineer will measure the pavement waterproofing membrane by the square yard. Payment for "Pavement Waterproofing Membrane" at the contract unit price is full compensation for the specified work.