202 — CHANNEL OR STREAM CHANGE EXCAVATION (CLASS 5) 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 200 GRADING SECTION 202 — CHANNEL OR STREAM CHANGE EXCAVATION (CLASS 5)
202.01 Description
Excavate for changes in channels or streams when specified. Use all suitable material for the construction of the project. Dispose of unsuitable material as directed.
202.02 Materials
Not applicable.
202.03 Construction
Refer to Section 201.
202.04 Measurement and Payment
Class 5 Excavation will be measured and paid for at the Contract unit price per cubic yard. The payment will be full compensation for all excavation and hauling, formation and compaction of embankments and backfill, backfilling old stream beds or otherwise disposing of excess and unsuitable materials, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Material will be measured in its original position and the volume computed by the Method of Average End Area. The cross-sectional area measured will not include liquids. Measurement for Class 5 Excavation excludes any material removed outside the limits of payment as specified in the Contract Documents.
Get an email when 202 changes
Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.