311Riprap Ditches

MD · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 361–362 Save this section

Ask about Section 311

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

311 — RIPRAP DITCHES 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 300 DRAINAGE SECTION 311 — RIPRAP DITCHES

311.01 Description

Construct riprap ditches and riprap ditches with capping.

311.02 Materials

Riprap 901.02 and 901.03 Geotextile Section 919, Class as specified 2 in. to 4 in. Stone M 43, No. 1

311.03 Construction

311.03.01 Excavation. Excavate to the specified line and grade. Ensure that ditch sides and

bottom are smooth and firm, free from protruding objects that would damage the geotextile, and constructed in an acceptable manner. For excavated material, refer to 402.03.01.

311.03.02 Geotextile Placement. Place geotextile on the prepared subgrade with the adjacent

edges overlapped at least 2 ft. Replace or repair damaged geotextile as directed.

311.03.03 Riprap Placement. Place stones by mechanical or other acceptable methods to

produce a reasonably graded mass of stone. Methods that cause extensive segregation are unacceptable. Place the riprap to the specified depth.

311.03.04 Backfill. Backfill any excavation voids existing along the edges and ends of the placed

riprap. Use suitable material to blend in with contiguous slopes, ditch lines, and existing ground. Cap riprap placed in the clear recovery area with a layer of 2 in. to 4 in. stone.

311.04 Measurement and Payment

The payment will be full compensation for all excavation, geotextile, stone, backfill, disposal of excess material, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.

311.04.01 Riprap Ditches and Riprap Ditches with Capping will be measured and paid for at the

Contract unit price per square yard of finished surface. 311 — RIPRAP DITCHES 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS

311.04.02 Bottom Cutoff Walls and Side Cutoff Walls will be measured and paid for at the

Contract unit price per linear foot.

Get an email when 311 changes

Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction and Materials, 2026 Edition. Pages 361–362 of 1,138. View official source ↗

Ask about this section

Scoped to Maryland Standard Specifications for Construction and Materials, Section 311 — Riprap Ditches. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.