B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Category 400 — Structures

403Temporary Support of Excavation or Fill

MD · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 391–392 Save this section

Ask about Section 403

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

403 — TEMPORARY SUPPORT OF EXCAVATION OR FILL 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 400 STRUCTURES SECTION 403 — TEMPORARY SUPPORT OF EXCAVATION OR FILL

403.01 Description

Provide temporary support of excavation or fill, as provided in the Contract Documents, for staged construction and as needed for safety and for the support of adjacent pavements and existing structures.

403.02 Materials

Not applicable.

403.03 Construction

Sheet, shore, brace, and support all excavation or fill contiguous to existing or proposed pavements and existing structures to prevent settlement, movement, or damage to the pavement or structure. See Section 402 for support requirements for Class 3 Excavation and Section 405 for support requirements for the Removal of Existing Structures. Design all temporary supports, retained earth structures, sheeting, and shoring by a professional engineer registered in the State of Maryland. When material retained by the temporary support of excavation or fill is greater than 6 ft high, submit details, procedures, and computations the same as specified for falsework details in TC-4.01 and Section 499. The experience specified under TC- 4.01 will be waived. Do not attach bracing for temporary support of excavation to permanent existing or proposed structures, unless specified in the plans or approved in writing by the Office of Structures. Requests should include calculations prepared by a professional engineer registered in the State of Maryland, showing that the temporary bracing will not affect the stability, maintenance, and the long term performance of the permanent structure. Do not extend any temporary support structures directly under any portion of proposed structures and pipes or within 5 ft of proposed pile locations, unless specified in the plans or approved in writing by the Office of Structures. Contractors should consider the configuration of the batter on piles when installing the supports. Remove temporary support of excavation or fill when no longer needed. Remove supports in their entirety or as specified in Section 405. 403 — TEMPORARY SUPPORT OF EXCAVATION OR FILL 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS

403.04 Measurement and Payment

The payment will be full compensation for all excavation, backfilling, materials, shipping, installation, complete or partial removal of temporary support of excavation or fill, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.

403.04.01 Support of Excavation or Fill will not be measured but will be paid for at the Contract

lump sum price.

403.04.02 Support of Excavation or Fill will be measured and paid for at the Contract unit price

per linear foot, for the actual installed quantity measured.

403.04.03 Support of Excavation or Fill will be measured and paid for at the Contract unit price

per square foot as measured vertically from the ground line on the front face (lower face) of the support to the groundline on the back face of the support and measured horizontally along the front face of the temporary support structure.

Get an email when 403 changes

Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction and Materials, 2026 Edition. Pages 391–392 of 1,138. View official source ↗

Ask about this section

Scoped to Maryland Standard Specifications for Construction and Materials, Section 403 — Temporary Support of Excavation or Fill. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.