503 — CHIP SEAL SURFACE TREATMENT 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 500 PAVING SECTION 503 — CHIP SEAL SURFACE TREATMENT
503.01 Description
Apply one or two seal coats or a prime coat followed by one or two seal coats as specified. The seal coat consists of emulsified asphalt followed by an application of aggregate. The prime coat, when required, consists of preparing and treating an existing surface with emulsified asphalt.
503.02 Materials
MATERIAL SECTION APPLICATION SIZE OR GRADE SPREAD RATE lb/yd2 SPRAY TEMP F SPRAY RATE SINGLE COAT OR FIRST COAT gal/yd2 SPRAY RATE FOR SECOND COAT (Double) gal/yd2 Single or First Coat No. 7 25-50 — — — Aggregate 901 Second (Double Coat) No. 8 20-35 — — — CRS-1 — 70-140 0.3-0.5 0.2-0.4 CRS-2 — 140-160 0.3-0.5 0.2-0.4 RS-1 — 70-140 0.3-0.5 0.2-0.4 Emulsified Asphalts 904.03 Seal Coat RS-2 — 140-160 0.3-0.5 0.2-0.4
503.03 Construction
At least 30 days prior to the start of placement of the chip seal surface treatment, submit a proposed plan, including equipment and material sources, for approval. Protect the treated pavement against damage from all causes. Repair or replace damaged areas as directed.
503.03.01 Equipment. All equipment is subject to approval.
503.03.02 Weather Restrictions. Place when the ambient air and surface temperatures are at
least 50 F and rising and the pavement is clean and dry. When weather conditions differ from these limits, placement of material en route from the plant to the job site shall be at the Contractor’s risk. When the Engineer stops placement of the material, dispose of all material en route at no additional cost to the Administration.
503.03.03 Foundation Preparation. Construct the foundation as specified. When paving over
existing pavement, repair ruts and potholes to provide a smooth surface for the application of the chip seal surface treatment.
503.03.04 Prime Coat. Prior to the application, clean the surface of all loose and foreign
materials. Uniformly apply the prime coat to the surface at the application rate specified in 503.02. Remove pooled material before applying the next coat. 503 — CHIP SEAL SURFACE TREATMENT 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
503.03.05 First Seal Coat.
503.03.06 Rolling. Immediately following the aggregate application, roll the surface until the
aggregate is uniformly embedded into the asphalt. Discontinue rolling if the aggregate begins to crush.
503.03.07 Second Seal Coat. When specified, after the first seal coat has cured at least 24 hours,
apply a second seal coat to the surface, omitting the prime coat. Apply emulsified asphalt and aggregate at the application rate specified in 503.02. Remove excess aggregate and correct all areas containing insufficient aggregate. Roll the surface as specified in 503.03.06.
503.03.08 Traffic. Close completed sections to traffic until the final seal coat has completely
cured. Maintain the treated surface after it has been opened to traffic until final acceptance.
503.04 Measurement and Payment
The payment will be full compensation for the foundation preparation, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Chip Seal Surface Treatment will be measured and paid for at the Contract unit price for one or more of the items listed below.
503.04.01 No. 7 Aggregate for Single Coat Chip Seal Surface Treatment per ton.
503.04.02 No. 8 Aggregate for Second Coat Chip Seal Surface Treatment per ton.
503.04.03 Emulsified Asphalt for Seal Coat per gallon.
The actual number of gallons of emulsified asphalt distributed will be corrected to the corresponding volume at 60 F as determined by use of conversion tables furnished by the Administration.
Get an email when 503 changes
Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.