5-109 culverts; the horizontal end reinforcing ribs for aluminum allo y structural plate pipe and pipe arches; the headwalls, wingwalls, toewalls, full metal inv ert and/or footing pads for metal box culverts; anchor bolts embedded in concrete; the rece iving channels for metal box culverts on concrete substructures; and all incidental items re quired to complete the work, including, but not limited to, the calibrated torque wrench for use by the Resident. Reinforced concrete headwalls and wingwalls are not included fo r payment under this item. Whenever the minimum cover material extends above the subgrade line, the removal of the material which is necessary to complete the work in accorda nce with the Plans will be measured and paid for as Common Excavation as provided in Secti on 203 - Excavation and Embankment. Payment will be made under: Pay Item P a y U n i t
509.11 Steel Structural Plate Pipe Lump Sum
509.12 Steel Structural Plate Pipe Arch Lump Sum 509.13 Steel Structural Plate Arch Lump Sum
509.141 Steel Structural Plate Box Culvert Lump Sum 509.18 Aluminum Alloy Structural Plate Pipe Lump Su m
509.19 Aluminum Alloy Structural Plate Pipe Arch Lump Sum
509.20 Aluminum Alloy Structural Plate Arch Lump Sum
509.411 Aluminum Structural Plate Box Culvert Lump Sum SECTION 510 - SPECIAL DETOURS
510.01 Description This work shall consist of the design, cons truction, maintenance in
good condition and removal of temporary structures and approach es required for the satisfactory maintenance of vehicular and pedestrian traffic. Easements or right-of-way for t he Special Detour will be furnis hed by the Department and will be shown on the Contract P lans. If the Contractor pro poses an alternative location for the Special Detour, and the alternative location is approve d by Department, that easement may only be acquired by the Department. All additiona l costs associated with the acquisition, including, but not limited to, obtaining easements , environmental mitigation, restoration and Department time, shall be borne by the Contract or.
510.02 Materials Materials used for the Special Detour structu re and approaches shall
conform to the detailed plans and specifications submitted by t he Contractor.
510.03 Vehicular and Pedestrian Traffic Not Separated The Spec ial Detour shall be
located as close as practicable to the new Work, or as shown on the Plans. 5-110 The Special Detour, including the temporary structure and appro aches, shall be designed and sealed by a Professional Engineer, licensed in accordance w ith the laws of the State of Maine. The Contractor shall submit the design computations and detailed plans of the temporary structure and approaches that will serve as the tempo rary detour to the Resident prior to beginning construction of the Special Detour. If the Department requires changes to Temporary Detour plans or computations, based on Contract requirements, then the Contractor shall implement t he changes at no additional cost to the Department. The Department shall have no obligation to review or comment on any design, construction, maintenance or removal of Temporary Detours. No review or comment by the Department, or any lack of review or comment by the Department, shall relieve the Contractor of its responsibility to properly design, construct, maintain in good condition, and remove Temporary Detours in accordance with the Contract, o r shall shift any responsibility to the Department. The Contractor shall be resp onsible for all damages resulting from the failure of temporary structures or approache s. The Special Detour shall not be opened to traffic until the Con tractor’s Professional Engineer inspects the temporary structure and provides the Depa rtment with a signed and sealed document certifying that the structure was built in acco rdance with the previously submitted sealed plans and design details of the structure and approaches. 510.031 Structure Design Temporary structures shall be designe d in accordance with the AASHTO Standard Specifica tions for Highway Bridges, 17th Edition, 2002, or the current edition of AASHTO LRFD B ridge Design Specifications, ex cept as noted herein, to meet live load requirements of HS25 for ASD and LFD, or HL-93, Maine Modified, for LRFD designs.
510.04 Pedestrian Traffic Only The provisions of Section 510. 03 - Vehicular and
Pedestrian Traffic Not Separated, shall apply to this Section w ith the following modifications:
510.05 Vehicular and Pedestrian Traffic Separated The provisio ns of both Section
510.03 Vehicular and Pedestrian Traffic Not Separated, and Se ction 510.04- Pedestrian
Traffic Only, shall apply to thi s Section. If vehicles and ped estrians are carried on the same structure, each shall have its own lane as specified. The pede strian lane shall be protected from vehicular traffic by being a t least 9 inches above the roa dway surface or suitably protected by means of an adequate curb at least 9 inches in hei ght above the roadway surface. No bridge rail will be required between vehicle traff ic and pedestrian traffic, unless otherwise specified, but shall be located at the exterior side of the sidewalk.
510.06 Special Detour Construction T he Special Detour, includin g temporary structures
and approaches, shall be constructed in accordance with the pla ns submitted by the Contractor. Barricades, warning s igns, lights and other traffi c control devices shall be provided in accordance with the Contract and the approved Traff ic Control Plan. The temporary structure’s deck and floor members shall be faste ned or anchored so that all contact surfaces with adjacent supporting members bear cont inuously. If timber plank decking is used, it shall be secured into timber nailer strips with screw-type nails, or securely fastened by an alternate method that will prevent the decking from loosening.