SECTION 510 - SPECIAL DETOURS
510.01 Description This work shall consist of the design, construction, maintenance in
good condition and removal of temporary structures and approaches required for the satisfactory maintenance of vehicular and pedestrian traffic. Easements or right-of-way for the Special Detour will be furnished by the Department and will be shown on the Contract Plans. If the Contractor proposes an alternative location for the Special Detour, and the alternative location is approved by Department, that easement may only be acquired by the Department. All additional costs associated with the acquisition, including, but not limited to, obtaining easements, environmental mitigation, restoration and Department time, shall be borne by the Contractor.
510.02 Materials Materials used for the Special Detour structure and approaches shall
conform to the detailed plans and specifications submitted by the Contractor.
510.03 Vehicular and Pedestrian Traffic Not Separated The Special Detour shall be
located as close as practicable to the new Work, or as shown on the Plans. 5-110 The Special Detour, including the temporary structure and approaches, shall be designed and sealed by a Professional Engineer, licensed in accordance with the laws of the State of Maine. The Contractor shall submit the design computations and detailed plans of the temporary structure and approaches that will serve as the temporary detour to the Resident prior to beginning construction of the Special Detour. If the Department requires changes to Temporary Detour plans or computations, based on Contract requirements, then the Contractor shall implement the changes at no additional cost to the Department. The Department shall have no obligation to review or comment on any design, construction, maintenance or removal of Temporary Detours. No review or comment by the Department, or any lack of review or comment by the Department, shall relieve the Contractor of its responsibility to properly design, construct, maintain in good condition, and remove Temporary Detours in accordance with the Contract, or shall shift any responsibility to the Department. The Contractor shall be responsible for all damages resulting from the failure of temporary structures or approaches. The Special Detour shall not be opened to traffic until the Contractor’s Professional Engineer inspects the temporary structure and provides the Department with a signed and sealed document certifying that the structure was built in accordance with the previously submitted sealed plans and design details of the structure and approaches. 510.031 Structure Design Temporary structures shall be designed in accordance with the AASHTO Standard Specifications for Highway Bridges, 17th Edition, 2002, or the current edition of AASHTO LRFD Bridge Design Specifications, except as noted herein, to meet live load requirements of HS25 for ASD and LFD, or HL-93, Maine Modified, for LRFD designs.
510.04 Pedestrian Traffic Only The provisions of Section 510.03 - Vehicular and
Pedestrian Traffic Not Separated, shall apply to this Section with the following modifications:
510.05 Vehicular and Pedestrian Traffic Separated The provisions of both Section
510.03 Vehicular and Pedestrian Traffic Not Separated, and Section 510.04- Pedestrian
Traffic Only, shall apply to this Section. If vehicles and pedestrians are carried on the same structure, each shall have its own lane as specified. The pedestrian lane shall be protected from vehicular traffic by being at least 9 inches above the roadway surface or suitably protected by means of an adequate curb at least 9 inches in height above the roadway surface. No bridge rail will be required between vehicle traffic and pedestrian traffic, unless otherwise specified, but shall be located at the exterior side of the sidewalk.
510.06 Special Detour Construction The Special Detour, including temporary structures
and approaches, shall be constructed in accordance with the plans submitted by the Contractor. Barricades, warning signs, lights and other traffic control devices shall be provided in accordance with the Contract and the approved Traffic Control Plan. The temporary structure’s deck and floor members shall be fastened or anchored so that all contact surfaces with adjacent supporting members bear continuously. If timber plank decking is used, it shall be secured into timber nailer strips with screw-type nails, or securely fastened by an alternate method that will prevent the decking from loosening. 5-113 Immediate corrective action shall be taken by the Contractor to remedy any condition in the structure that results in objectionable or distractive noise levels, or results in the decking becoming loose, when subject to traffic loads. Screw-type nails will not be required to anchor timber plank decking for pedestrian traffic use. The approach road surface, including shoulders, whether paved or graveled, shall be maintained in a compacted and smooth condition. The temporary structure travel surface shall be constructed and maintained in an acceptably smooth condition, as determined by the Resident. Immediate corrective action shall be taken by the Contractor to remedy objectionable roughness of the Special Detour riding surface. Provisions shall be made for a skid resistant wearing surface throughout the period of time the temporary structure is open to public travel for vehicular and pedestrian traffic. A steel grid floor may be used for vehicular traffic if installed in accordance with the design plans and these specifications. Erosion control shall be accomplished in accordance with Section 656 - Temporary Soil Erosion and Water Pollution Control. When the Project has been opened to traffic, the temporary structure and approaches shall be removed to, or below, the streambed, finish ground line or original ground line, as applicable. The approaches shall be obliterated and the disturbed areas shall be stabilized to original, or better than original, conditions. The provisions of Section 104 - General Rights and Responsibilities, shall apply.
510.07 Contractor's Responsibility The Contractor shall be responsible for removal of
snow from areas provided for pedestrian traffic as well as vehicular traffic in accordance with Section 105, General Scope of Work. In addition to normal maintenance, should any part, or all, of the Special Detour be damaged or destroyed by high water, or any other cause, prior to, or after, opening the Special Detour to traffic, it shall be repaired or replaced by the Contractor without additional compensation.
510.08 Method of Measurement Special Detours will be paid by the lump sum.
510.09 Basis of Payment The accepted Special Detour will be paid for at the Contract
lump sum price which price shall be full compensation for the respective items, as called for in the Contract, including design, construction, maintenance, complete removal, rehabilitation and permanent stabilization including loaming, seeding and mulching. All gravel or borrow material and excavation needed to accommodate changes in elevation between temporary structures and existing roadways shall be incidental to this item. The lump sum price shall also include the cost of furnishing and revising, as necessary, all plans, computations and certifications, as called for in the Contract. Payment will be made as follows: 60 percent of the lump sum price will be paid when the Special Detour is acceptable and open to traffic; another 20 percent of the lump sum price will be paid when 5-114 the Special Detour is no longer needed and is closed to traffic; the final 20 percent of the lump sum price will be paid when the Special Detour is removed and the area encompassing the Special Detour is acceptably restored. Traffic control devices, temporary erosion control, pavement, and dust control will be paid for in accordance with the applicable Contract items. Payment will be made under: P a y I t e m P a y U n i t
510.10 Special Detour, ___ foot Roadway L u m p S u m
Width Vehicular and Pedestrian Traffic N o t S e p a r a t e d
510.11 Special Detour, Pedestrian Traffic Only L u m p S u m
510.12 Special Detour, ___ foot Roadway L u m p S u m
Width Vehicular and Pedestrian Traffic S e p a r a t e d
Get an email when 510 changes
Maine revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.