6-163
653.02 General Insulating material shall be extruded polystyr ene insulating board
conforming to the requirements of AASHTO M230. Pegs shall be hard wood, approximately 6 inches by ¼ inch roun d, pointed on one end.
653.03 Preparation of Foundation The insulating boards shall be placed on a
compacted layer of granular mater ial graded to a tolerance of ½ inch above or below the required grade and cross section. The surface shall be free of rocks that would cause damage to the insulating boards . The type and thickness of the granular material will be as shown on the plans.
653.04 Placing Insulating Boards The insulating boards shall be secured to the
ground with pegs placed at each corner or where directed by the Resident, and driven flush with the surface of the insul ating board. Joints between the i nsulating boards shall be staggered. The openings in all joint shall be kept to a minimu m.
653.05 Placing Backfill After the insulating boards have been placed, granular
material shall be placed using care to avoid pushing or punctur ing the boards. The depth of the first layer of aggregate subbase sand shall not be less tha n 10 inches loose measure. The aggregate subbase sand shall be spread with a crawler type bull dozer of not more than 2000 lb/ft² ground contact pressure or with other approved equipment but not supported directly on the insulating boards. Trucks and other heavy construction equipment shall not be operated directly on the insulating boards. The type and thick ness of granular material will be shown on the plans.
653.06 Compaction Compaction of the first layer of aggregate subbase sand shall be
by vibratory methods to the satisf action of the Resident. Afte r the first layer has been compacted, normal construction practices may be followed provid ing no loads are placed on the area that produce more than 2000 lb/ft² ground contact pres sure.
653.07 Protection of Polystyrene Since gasoline, oil, heat, a nd sunlight will damage
polystyrene, all precautions shall be taken to prevent them fro m damaging the insulating board. The insulating boards shall not be stored in sunlight f or more than one day.
653.08 Method of Measurement Polystyrene plastic insulation w ill be measured by
the square yard in place.
653.09 Basis of Payment The accepted quantities of polystyren e plastic insulation
will be paid for at the contract unit price per square yard com plete in place. Payment shall be full compensation for and for furnishing and placing the ins ulating boards of pegs. Payment will be made under: 6-164 Pay Item Pay Unit
653.20 1 inch Polystyrene Plastic Insulation S q u a r e Y a r d
653.21 1½ inch Polystyrene Plastic Insulation S q u a r e Y a r d
653.22 2 inch Polystyrene Plastic Insulation S q u a r e Y a r d
653.23 3 inch Polystyrene Plastic Insulation S q u a r e Y a r d
SECTION 654 - INTELLIGENT TRANSPORTATION SYSTEMS Reserved SECTION 655 - ELECTRICAL WORK Reserved SECTION 656 - TEMPORARY SOIL ER OSION AND WATER POLLUTION CONTRO L 656.1 Responsibility of the Contractor-Prepare and Follow Plan The Contractor shall provide continuous and effective temporary soil erosion and wat er pollution control for the Project that is appropriate to the construction means, methods and sequencing allowed by the Contract and selected by the Contractor. To do so, the Con tractor shall prepare and submit a Soil Erosion and Water Pollution Control Plan (SEWPCP) and properly implement its approved SEWPCP. The Contractor shall have its SEWPCP appr oved, perform a preconstruction field review, and install and certify initial c ontrols before commencing any Work, which could disturb soils or impact water quality. Failur e by the Contractor to follow Standard Specification or Sp ecial Provision - Section 656 will result in a violation letter and a reduction in payment as shown in the schedule list in 656.5.1 . The Department’s Resident or any other representative of The Department reserves the righ t to suspend the work at any time and request a meeting to discuss violations and remedies. The Department shall not be held responsible for any delay in the work due to any suspensio n under this item. If the Contractor properly imple ments its approved SEWPCP, then (1) any Work required in excess of that required by the SEWPCP will be Extra Work, (2) any Delay resulting from any such excess Work will be analyzed in accorda nce with Section 109.5 - Adjustments for Delay, and (3) t he Contractor will not be resp onsible for damages relating to insufficient soil erosion and water pollution control includ ing the cost of all environmental enforcement actions, penalties, or monetary settl ements assessed any environmental regulatory entity and all costs incurred by or th rough the Department. If the Contractor fails to prep are, submit, or seek approval of a SEWPCP or fails to properly implement its approved SEWPCP, then (1) the Departmen t may suspend all Work,