1018.1 Scope. This specification covers fly ash for use in concrete.
1018.2 General. Only fly ash from sources qualified in accordance with these specifications will be permitted.
The mixing of different classes and sources of fly ash will not be permitted. All fly ash shall be in accordance with AASHTO M 295, Class C, F or N, except as herein specified.
1018.2.1 Class C fly ash shall meet either (a) or (b) of the following requirements:
1018.2.1 1 All Class C fly ash shall have a minimum Strength Activity Index with Type IL cement of 85 percent
of the control at 28 days.
1018.2.2 The percent each of silicon dioxide (SiO2), aluminum oxide (Al2O3) and iron oxide (Fe2O3) shall be
reported in addition to the total of the three.
1018.2.3 Loss on Ignition shall not exceed 1.5 percent unless suppliers provide test data verifying performance
and durability of fly ash concrete applications for sources exceeding this requirement.
1018.2.4 The term “manufacturer”, as used in this specification, will be the actual manufacturer of the fly ash.
The term, “marketing entity”, as used in this specification, will be the supplier or broker of the fly ash. The marketing entity shall be responsible to be in accordance with these specifications.
1018.2.5 Cement used for testing fly ash shall be a Type IL in accordance with AASHTO M240.
1018.2.6 All marketing entities, terminals, and independent testing laboratories shall be qualified prior to
acceptance of any material.
1018.3 Laboratory Qualification.
1018.3.1 In order to become qualified, a written request shall be sent by the marketing entity to Construction
and Materials, along with a copy of the laboratory’s QC Plan, the QC department's most recent Cement and Concrete Reference Laboratory (CCRL) certification and the latest CCRL Pozzolan proficiency sample report. The CCRL inspection shall cover all tests required by the specification. Documentation showing satisfactory resolution of all inspection deficiencies shall be included. In addition, the plant may be inspected to verify the information and to establish personal contact with the QC personnel.
1018.3.2 Failure to Comply. Failure to comply with any of these requirements and/or specified herein may
result in the issuance of a strike. If a laboratory accumulates three strikes, the laboratory shall be disqualified. For every year a laboratory does not receive a strike, a strike will be removed from the laboratory’s accumulated total. In cases of dispute, test results obtained by MoDOT will control.
1018.3.3 Disqualified Facilities. If a laboratory has been disqualified, the marketing entity must utilize an
existing MoDOT approved laboratory or qualify a laboratory fulfilling MoDOT requirements. A disqualified laboratory will be unable to maintain qualification based on requirements governed in this specification.
1018.4 Marketing Entity Qualification. In order to become qualified, a written request shall be sent by the
marketing entity to Construction and Materials, along with a copy of the marketing entity’s QC plan and the following information. The power plant and terminals may be inspected to verify the information and to establish personal contact with the QC personnel.
1018.4.1 The following information shall be included in the request for qualification:
1018.4.2 In order to maintain qualification, the following will be required:
1018.4.3 Failure to Comply. Failure to comply with any of these requirements and/or specified herein may
result in the issuance of a strike. If a marketing entity accumulates three strikes, the marketing entity shall be disqualified. For every year a marketing entity does not receive a strike, a strike will be removed from the marketing entities’ accumulated total. In cases of dispute, test results obtained by MoDOT will control.
1018.5 Terminal Qualification. In order to become a qualified terminal, a written request shall be sent from
terminal personnel to Construction and Materials. A letter shall accompany the request from each affected and qualified marketing entity, advising of the intent to ship through the respective terminal. Any changes in fly ash source shall be updated in the same manner. Terminals shall be inspected to ensure adequacy to accept, retain and ship fly ash from qualified marketing entities.
1018.6 Sampling, Testing and Acceptance Procedures. All fly ash will be subject to inspection and sampling
by MoDOT at the power plant, an intermediate shipping terminal or destination. MoDOT shall be allowed unlimited access to all facilities and records in order to conduct inspection and sampling.
1018.6.1 Failure to Comply. Failure to fulfill any of these requirements may result in disqualification of the fly
ash manufacturer, marketing entity or a terminal. In cases of dispute, test results obtained by MoDOT will control.
1018.6.2 Disqualified Facilities. If a facility has been disqualified, the marketing entity may elect to designate
the silo, bin or storage facility from which the marketing entity proposes to furnish fly ash for MoDOT projects. If this option is used, each silo, bin or storage facility designated must be sampled, tested, sealed and approved by MoDOT prior to shipment. The marketing entity shall also sample, test and report the test results for each designated silo, bin or storage facility.
1018.6.3 Shipping. Fly ash shall be continually sampled and tested at a location, frequency and duration
acceptable to MoDOT, and may be continuously shipped direct from a marketing entity or generating station silo.
1018.6.4 Storage. All fly ash intended for use shall be sampled, tested, and placed in designated silos or bins.
1018.6.5 Coal Sources and Process. Fly ash from each coal source at each plant shall be qualified separately.
Coals from different sources may be blended prior to burning, but the qualification shall be based on the blend. When the production procedure or fuel source is changed, or when any change is made by the manufacturer that alters the properties or characteristics of the qualified fly ash, requalification may be required.
1018.6.6 Acceptance. The marketing entity shall certify that the material complies with the specification
requirements. When a qualified marketing entity or terminal is shipping fly ash for, or purchasing fly ash from, another qualified marketing entity, the bill of lading or delivery receipt shall be from the shipping company. The certification statement showing the actual manufacturer shall be prominently placed on the bill of lading or delivery receipt. A copy of the bill of lading or delivery receipt shall accompany each shipment and shall be furnished to MoDOT at the shipping and destination points.
1018.6.7 The bill of lading or delivery receipt for each shipment to MoDOT projects shall carry the following
certification statement: "This is to certify this Class ___ fly ash originated from a MoDOT qualified manufacturer, has been maintained to meet MoDOT specifications and was loaded from silo number ________." _________________________________ Name and Location of Manufacturer __________________________________ Name and Location of Shipping Facility By________________________________ Signature and Name of Marketing Entity