Division 200 — Grading and Removals

208Interception Ditch

MO · 2026 (Oct) Standard Specifications✓ Full text on BuildSpecBook pages 140–140 Save this section

Ask about Section 208

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

208.1 Description. This work shall consist of all work necessary to construct an interception ditch or levee, or

both, as shown on the plans or as directed by the engineer.

208.2 Construction Requirements. Interception ditches shall be constructed in a manner to provide a profile

free from sharp breaks or irregularities. The work shall be finished to a reasonably smooth and uniform surface. Loose rock shall be removed from the finished surfaces.

208.3 Method of Measurement. Measurement will be made to the nearest 10 feet along the flow line of the

ditch for each segment and totaled to the nearest 100 feet for the sum of all segments.

208.4 Basis of Payment. The accepted quantity of interception ditch will be paid for at the contract unit price.

Get an email when 208 changes

Missouri revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Missouri Standard Specifications for Highway Construction, 2026 (Oct) Edition. Pages 140–140 of 874. View official source ↗

Ask about this section

Scoped to Missouri Missouri Standard Specifications for Highway Construction, Section 208 — Interception Ditch. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.