Division 12 — Landscaping

1251RAISED PAVEMENT MARKERS

NC · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 695–695 Save this section

Ask about Section 1251

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

12-15 (E) Pavement Marker Installer Qualifications

Ensure at least one member of every pavement marker crew is certified through the NCDOT Pavement Marking Technician Certification Process. Keep the certification current throughout the life of the project. A certified crewmember shall be present anytime this work is being performed. The certified crewmember is not required to be the same person throughout the life of the contract. 1251 -1 DESCRIPTION Furnish, install, maintain and remove temporary and permanent raised pavement markers in accordance with the contract. 1251 -2 MATERIALS Refer to Division 10. Item Section Temporary Raised Pavement Markers 1086 -1 Permanent Raised Pavement Markers 1086 -2 Use pavement markers that are on the NCDOT APL . 1251 -3 CONSTRUCTION METHODS Install temporary raised pavement markers on the nonfinal pavement surfaces with epoxy, pressure sensitive adhesives or hot bitumen adhesives. Insta ll permanent raised pavement markers using a hot bitumen adhesive in accordance with

Article 1081 — 3.

On final pavement surfaces, install temporary raised pavement markers using a pressure sensitive adhesive or hot bitumen adhesive. When using a pressure s ensitive adhesive, install per the manufacturer's specifications. 1251 -4 MAINTENANCE Maintain all installed temporary raised pavement markers. Replace all damaged or missing temporary raised pavement markers if any of the following occurs:

A.Three segment failures occur in any roadway section. Three consecutive damaged or missing markers in any group of 7 represents a segment failure.
B.Twenty percent of the markers in any roadway section are damaged or missing.
C.Engineer determines replacement is necessary. Maintain all installed permanent raised pavement markers until final acceptance of the project . 1251 -5 MEASUREMENT AND PAYMENT Temporary Raised Pavement Markers will be measured and paid as the actual number of temporary raised pavement markers satisfactorily placed and accepted by the Engineer. Permanent Raised Pavement Markers will be measured and paid as the actual number of permanent raised pavement markers satisfactorily placed and accepted by the Engineer. Payment will be made under: Pay Item Pay Unit Temporary Raised Pavement Markers Each Permanent Raised Pavement Markers Each
Referenced in this section

Get an email when 1251 changes

North Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: North Carolina Standard Specifications for Roads and Structures, 2024 Edition. Pages 695–695 of 857. View official source ↗