16-22 (E) Attachment Device
Provide plastic ties, wire fasteners or other approved attachment d evice. 1640 -3 CONSTRUCTION METHODS Place the coir fiber baffles immediately upon construction of sediment dams and basins. Install 3 baffles in basins with a spacing of 1/4 the basin length and according to the detail sheets. Install 2 coir fiber baffles in basins less than 20 f eet in length with a spacing of 1/3 the basin length. Place s teel posts at a depth of 2 f eet below the basin surface, with spacing of no more than 4 feet. The top height of the coir fiber baffles shall not be below the elevation of the emergency spillway base of dams and basins. Attach a 9 -gauge high -tension wire strand to the steel posts at a height of 3 f eet with plastic ties or wire fasteners. Install a steel post into side of the basin at a variable depth and a height of 3 f eet from the bottom of the basin to anchor coir fiber mat. Secure anchor post to the upright steel post in basin wit h wire fasteners. Drape t he coir fiber mat over the wire strand with at least 3 feet of material on each side of the strand. Secure the coir fiber mat to the posts and wire strand with approved fastener . Place staples across the matting at ends and junct ions approximately one foot apart at the bottom and side slopes of basin. Overlap matting at least 6 inches where 2 or more widths of matting are installed side by side. Refer to details in the plans. The Engineer may require adjustments in the stapling requirements to fit individual site conditions. 1640 -4 MEASUREMENT AND PAYMENT Coir Fiber Baffle will be measured and paid as the actual number of linear feet of coir fiber baffle s which are installed and accepted. Such price and payment will be full compensation for all work covered by this section, including, but not limited to, furnishing all materials, labor, equipment and incidentals necessary to install the coir fiber baffles. Payment will be made under: Pay Item Pay Unit Coir Fiber Baffle Linear Foot 1642 -1 DESCRIPTION Work includes furnishing materials, installation of wattles, matting installation, maintenance and removing wattles. Install wattles as shown in the plans or as directed by the Engineer to intercept runoff, act as a velocity break and contain sediment. The actual conditions which occur during the construction of the project will determine the quantity of wattles constructed. The quantity of wattles may be increased, decr eased or eliminated entirely as directed by the Engineer. Such variations in quantity will not be considered as alterations in the details of construction or a change in the character of the work . 1642 -2 MATERIALS Refer to Division 10. Item Section Matting for Erosion Control 1060-8 Staples 1060-8(D)
16-23 (A) Stakes
Place structural stone in the channel, ditch diversion, swale or drainage turnouts with 2:1 side slope on the upstream side and 3:1 side slope on the downstream side. Plate the upstream side with sediment control stone approximately 12 inches thick. Use a minimum spacing of 15 f eet and as directed by the Engineer for the coir fiber baffles. Provide a weir sectio n approximately 2/3 of the channel width and with an 8 foo t maximum height from the bottom of the channel. In the center of the device, place the weir section approximately 12 inches lower than the sides of the device or the top of the channel, whichever is lower.
1642-3 Construction Methods
16-24 inches.
Installation of matting shall be in accordance with the plans, and in accordance with
Article 1631 — 3.
Only apply flocculant on wattles per plans and as directed by the Engineer. When required, flocculant shall be applied over the lower center portion of the wattle where the water is going to flow over at a rate of 2 oz per wattle, and 1 o z of flocculant on matting on each side of the wattle. Flocculant applications shall be done during construction activities after every rainfall event that is equal to or exceeds 0.50 inches . Do not apply flocculent to a wattle that serves as a stormwater disch arge outfall .
Get an email when 1642 changes
North Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.