- 725 - SECTION 902 -- GUARDRAIL AND GUARD POSTS
902.01Description
posts at locations shown in the contract.
that are attached to steel posts.
bolted to the posts with offset blocks. If shown in the contract or approved by the Engineer, the offset blocks may be omitted.
902.02Material Requirements
contract. Table 902.01 Material Requirements Applicable Materials Section Reinforcin g Steel ............................................................... .1020 Steel Guardrail Posts, Special Posts, and Offset Blocks ... .1067 “W” and “Thrie”-Beam Guardrail ........................................ .1066 Wood Guardrai l Posts........................................................ .1075 Concrete Aggregate 1033
readily available, commercially designed concrete mixture or Contractor- produced concrete, which shall achieve a minimum compressive strength of 3000 psi (20 MPa) at 28 days. The cement shall be Type I, Type II, or Type III. The aggregate shall be from acceptable sources.
the requirements of AASHTO M 30. The cable shall, unless otherwise specified, meet the requirements for “T ype I” rope, with “Class A” galvanized coating.
AASHTO M 30.
requirements of ASTM A 36. Turnbuckles and clevises shall be steel forgings conforming to the requirements of ASTM A 668, Class B. The forgings shall be annealed prior to being machined.
Tension spring assemblies, when tested as installed in a normal cable guard rail installation, shall develop a mini mum tensile strength of 25,000 pounds per 3/4 inch cable. The coil spring shall conform to the requirements of ASTM A 689.
assemblies) shall have a uniform coating of zinc as required in AASHTO M 30.
Guardrail and Guard Posts
- 726 - 4. The Contractor shall order guardr ail items as shown in the contract unless the Engineer furnishes a field checked list of items, lengths, and locations.
902.03Construction Methods
shown in the contract and to lines and grades given.
posts in prebored holes.
rejected. The Contractor shall remove and replace the posts with acceptable materials.
surfaced shoulder during post placem ent due to the Contractor's driving operation, the Engineer will require that the posts be set in prebored holes.
shall construct a blockout in the surfacing around each post as shown in the contract documents.
any cracking that may occur in the su rfacing. The hot pour sealant shall comply with Section 519. This work will be considered subsidiary to the Cable Guardrail.
with Repair Method 2 as described in Section 1061.
cutting, boring, or other means shall be thoroughly coated with 3 applications of preservative. Each application shall be reasonably dry before the next coat is applied.
Contractor shall backfill all post holes with material approved by the Engineer. The material shall be compacted leaving a space around the post as defined in the contract. This remaini ng part of the hole shall be backfilled with granular material and approved bituminous material or flowable fill concrete placed to the elevation of the surrounding surfacing as shown in the contract. The material near the post shall be sloped to help any water run off away from the post.
surfacing shall be backfilled with material approved by the Engineer and placed to the elevation of the existing surface.
.04
- 727 - b. Curved elements described in the contract shall be manufactured with the curve.
erection.
with cast in place welded assemblies of threaded inserts or bolts through bridge rail as shown in the contrac t. Curb mountings, anchor bolts, and incidentals will be considered as par t of the bridge approach sections.
902.04Method of Measurement
Department will compute the cable guar drail length in linear feet (meters) from terminal section to terminal section, excluding intermediate anchorage sections.
sections will be measured as single units complete and in place as shown in the contract.
(meter). The Department will compute the "W" and "thrie"-beam guardrail length in linear feet (meters) from c enter to center of the end splices and shall not include the distance of the section of rail projecting beyond these points.
with bridge approach sections, the pay length of these items shall be measured to the limits indicated in the contract.
with terminal end sections, the pay length of these items shall be measured to the limits indicated in the contract.
with "W" and "thrie"-beam guardrail will be measured by the each.
902.05Guardrail and Guard Posts
- 728 - 902.05 -- Basis of Payment
Cable Guardrail Linear Feet (LF) [Meter (m)] Intermediate Anchorage Sections Each (ea) Terminal Anchorage Sections Each (ea) Bridge Approach Sections Each (ea) Special Bridge Approach Section Each (ea) W-Beam Guardrail Linear Feet (LF) [Meter (m)] Thrie-Beam Guardrail Linear Feet (LF) [Meter (m)] W-Thrie Beam Transition Section Each (ea) Terminal Sections _____ Each (ea) Special Guardrail Posts Each (ea) Special Guardrail Posts _____ Each (ea) Guardrail Adapter _____ Each (ea) E a c h ( e a ) Guardrail End Treatment _____ Each (ea) End Anchorage Assembly Each (ea) B u l l n o s e E a c h ( e a ) 2. Terminal end shoes, when required in the contract, shall not be measured for payment but shall be cons idered subsidiary to the items for which direct payment is provided.
unless otherwise shown in the contract.
- 729 - SECTION 903 -- REMOVE AND RESET GUARDRAIL
903.01Description
sections, terminal sections, anchorage sections, and beam guardrail materials, fittings, and posts from locations shown in the contract or designated by the Engineer. Concrete anchors shall be removed in their entirety and disposed of by the Contractor.
project or furnished and delivered to the project by others as indicated in the contract. New anchors shall be furnished by the Contractor. The Contractor shall furnish all new posts, offset blo cks, hardware, and incidentals required to install the salvaged rail and cable elements.
903.02Material Requirement
to the requirements of Section 902.
903.03Construction Methods
shown in the contract. The salvaged guardrail materials shall be stockpiled as indicated in the contract.
each spool shall not exceed 2,000 feet (610 m).
way at locations designated by the Engineer.
shall be placed in a single container.
materials damaged during removal at no additional cost to the Department.
or needed by the Department shall bec ome the property of the Contractor. The Contractor shall remove all nons alvagable materials from the project site and properly dispose these materials in accordance with all-applicable laws and regulations.
belong to the Contractor and mu st be removed from the site.
in the contract or as directed by t he Engineer. The work shall be done in accordance with the requirements of Section 902.
903.04Method of Measurement
Department will compute the length of guardrail reset by the linear foot