- 737 - SECTION 908 -- CONCRETE SLOPE PROTECTION, DITCH LINING, FLUMES AND DISCHARGE STRUCTURES
908.03 Flumes and Discharge Structures
- 738 - 4. The Contractor shall place join ts and reinforcing steel as described in the contract.
5.The backfill shall be graded and co mpacted to the elevation of the top of the concrete structur e as shown in the contract.
6.a. The concrete shall be placed the full thickness of the slab in one operation and shall be consolidated by tamping and the excess concrete screeded off flush with the forms.
b.The edges adjacent to all forms, expansion joints, curbs, or fixtures in the surface shall be thoroughly spaded for the full depth.
c.After consolidation, the surface shall be alternately tamped and struck off with a strike board until all voids are removed and the surface has the required grade and cross section.
7.The Contractor shall finish t he edges with a suitable edging tool after the concrete has been floated.
8.The concrete shall be cured by one of the methods described in Section 603. 9.a. Concrete ditch liners shall hav e joints cut through them at least 25% of their slab thickness with an approved tool at intervals of not more than 8 feet (2.4 m).
b.The concrete shall be edged on both sides of the cuts. c. Each cut shall be vertical and normal to the forms. 10. a. The concrete ditch lining footings and structure turndowns shown in the contract do not need to be formed if concrete is placed directly into excavated trenches that have smooth walls and level bases.
b.Footings and turndowns shall be placed monolithic with the ditch lining.
11.If the trenches are excavated larg er than shown in the contract, the entire trench volume is still filled with concrete.
12.The Contractor shall dispose of all excess soil.
908.04 Method of Measurement
1.Concrete slope protection will be measured by the square yard (square meters) of finished surface area, including turndowns.
2.Concrete ditch lining will be measured by the Square Yard (SY) [Square Meter (m 2)] or Linear Foot (LF) [Meter (meter)] along the center of the flow line and will be continuous through the end sections.
3.Concrete flumes and discharge structures shall be measured by the each. Concrete Slope Protection, Ditch Lining, Flumes and Discharge Structures 908.05 - 739 - 908.05 -- Basis of Payment
1.P a y I t e m P a y U n i t Concrete Flume, Type _____ Each (ea) Concrete Flume Each (ea) Concrete Discharge Structure Each (ea) Concrete Ditch Lining _____ Linear Foot (LF) [Meter (m)] Concrete Ditch Lining _____ Square Yard (SY) [Square Meter (m 2)] Concrete Slope Protection Square Yard (SY) [Square Meter (m2)]
2.In the event that more than one type of discharge structure is shown in the contract, an appropriate designation will be added to the pay item to differentiate as to t he type or dimensions required.
3.a. The 28-day compressive stre ngth of each day's production will be determined from cyli nder strength tests.
b.Payment shall be reduced by the amount described in Table 603.03. 4.Payment is full compensation for all work described in this Section. - 740 - SECTION 909 -- INSTALLING TIE BARS
Source: Nebraska Standard Specifications for Highway Construction, 2017 Edition. Pages 771–773 of 1,048.