B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Division 150 — Contract Requirements

151Performance Bond and Payment Bond

NJ · 2019 (rev. 2022-12-21) Standard Specifications✓ Full text on BuildSpecBook pages 120–120 Save this section

Ask about Section 151

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 151 – PERFORMANCE BOND AND PAYMENT BOND

151.01 Description

This Section describes the requirements for providing a performance bond and a payment bond.

151.02 Materials

(Intentionally Blank)

151.03 Procedure

151.03.01 Performance Bond and Payment Bond

Using bond forms issued by the Department, provide a performance bond and a payment bond to the Department within 14 days of the date of Award or Conditional Award. Ensure that the penal sum of the bond is equal to at least the Total Contract Price less the bid price for PERFORMANCE BOND AND PAYMENT BOND . With the bond, provide a certification authorizing the attorney-in-fact to commit the Surety and a true and correct statement of the Surety’s financial condition. With the bond, submit the schedule of broker’s fees, the certified rate schedule, paid invoices and the report of execution for the bond to the RE. Obtain bonds from sureties listed in the US Treasury Department Circular 570 and authorized to do business in the State. Reinsurance is prohibited as per N.J.A.C 16:44-6.1(b)6. If the S urety becomes insolvent before Acceptance, provide a performance bond and a payment bond issued by another surety to the Department. The Department may adjust Contract Time, require extra work, or issue other changes authorized by the Contract without obtaining the consent of the surety of the bonds.

151.04 Measurement and Payment

The Department will measure and make payment for Items as follows: Item Pay Unit PERFORMANCE BOND AND PAYMENT BOND DOLLAR The Department will make payment for PERFORMANCE BOND AND PAYMENT BOND as follows: BIP = the lesser of BB and BI BFP = the lesser of [BIP +R(CF − CO)] and BF Where: BIP = Initial payment for the PERFORMANCE BOND AND PAYMENT BOND made by the Department at the start of Work. BB = Bid price of the PERFORMANCE BOND AND PAYMENT BOND. BI = Actual price of the PERFORMANCE BOND AND PAYMENT BOND at the start of Work. BF = Actual price of the PERFORMANCE BOND AND PAYMENT BOND at Completion of Work. BFP = Final payment for the PERFORMANCE BOND AND PAYMENT BOND made by the Department at the Completion of Work. R = (for Final Contract Price greater than the Original Contract Price) = Rate or rates from the certified schedule corresponding to the portion of the Contract Price greater than the Original Contract Price. R = (for Final Contract Price less than the Original Contract Price) = Rate from the certified schedule corresponding to the Final Contract Price. CF = Final Contract Price excluding adjustments for LAYOUT and PERFORMANCE AND PAYMENT BOND CO = Original Contract Price The Department will not make payment for PERFORMANCE BOND AND PAYMENT BOND until after receipt of the certified rate schedule. The Department will make adjustments to PERFORMANCE BOND AND PAYMENT BOND in the final monthly Estimate. The Department will not make adjustments of less than $100.00.

Sections that cite this one

Get an email when 151 changes

New Jersey revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction, 2019 (rev. 2022-12-21) Edition. Pages 120–120 of 651. View official source ↗

Ask about this section

Scoped to New Jersey 2019 Standard Specifications for Road & Bridge Construction, Section 151 — Performance Bond and Payment Bond. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.