Division 300 — Subbase and Base Courses

303Asphalt-Stabilized Drainage Course

NJ · 2019 (rev. 2022-12-21) Standard Specifications✓ Full text on BuildSpecBook pages 179–179 Save this section

Ask about Section 303

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 303 – ASPHALT-STABILIZED DRAINAGE COURSE

303.01 Description

This Section describes the requirements for constructing asphalt-stabilized drainage course.

303.02 Materials

303.02.01 Materials

Provide materials as specified: Asphalt-Stabilized Drainage Course ................................ ................................ ................................ ............. 902.06

303.02.02 Equipment

Provide equipment as specified: HMA Paver ................................ ................................ ................................ ................................ ................. 1003.03 HMA Compactor ................................ ................................ ................................ ................................ ........ 1003.05 Vibratory Drum Compactor ................................ ................................ ................................ ......................... 1003.06 Bituminous Material Distributor ................................ ................................ ................................ .................. 1003.07 HMA Plant................................ ................................ ................................ ................................ .................. 1009.01 HMA Trucks ................................ ................................ ................................ ................................ ............... 1009.02

303.03 Construction

303.03.01 Asphalt-Stabilized Drainage Course

A.Paving Plan. At least 20 days before the start of placing the asphalt -stabilized drainage course, submit a detailed plan of operation to the RE for approval as specified in 401.03.07.A.
B.Weather Limitations. Comply with the weather limitations as specified in 401.03.07.B.
C.Transportation and Delivery of HMA. Transport and deliver HMA as specified in 401.03.07.D.
D.Spreading and Grading. Ensure that the prime coat has been applied as specified in 401.03.06. Place asphalt-stabilized drainage course at a laydown temperature betwe en 210 °F and 275 °F . Spread and grade asphalt-stabilized drainage course in 1 lift as specified in 401.03.07.E.
E.Compacting. Compact as specified in 401.03.07.F. Ensure compaction is completed before the material temperature is less than 175 °F.
F.Thickness Requirements. Ensure that the thickness of the drainage course is within ±1/4 inch of the specified thickness and that the elevation of the compacted course is within 1/4 inch of the required elevation. The RE will check elevations of the asphalt-stabilized drainage course as specified in 202.03.03.D.
G.Protecting. Protect the drainage course from damage and contamination. Remove and replace damaged and contaminated areas. Only allow equipment on the drainage course that is necessary for the construction of the subsequent pavement course. If staging requires opening to traffic, then r emove loose material from the traveled way, shoulder, and auxiliary lanes before opening to traffic. Open to traffic or construction equipment, including paving equipment, only after the surface temperature is less than 140 °F.

Get an email when 303 changes

New Jersey revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction, 2019 (rev. 2022-12-21) Edition. Pages 179–179 of 651. View official source ↗