SECTION 503 – DRILLED SHAFT FOUNDATIONS
503.01 Description
This Section describes the requirements for installing and testing drilled shafts.
503.02 Materials
503.02.01 Materials
Provide materials as specified: Concrete ................................ ................................ ................................ ................................ ....................... 903.03 Self-Consolidating Concrete (SCC) ................................ ................................ ................................ ............... 903.06 Grout. ................................ ................................ ................................ ................................ ...................... 903.08.02 Reinforcement Steel ................................ ................................ ................................ ................................ . 905.01.01 Drilled Shaft Casing ................................ ................................ ................................ ................................ ...... 906.03 Steel Tube ................................ ................................ ................................ ................................ ..................... 906.08 Structural Steel Paint (Organic Zinc) ................................ ................................ ................................ ........ 912.01.01 Water ................................ ................................ ................................ ................................ ............................ 919.08 Provide clay-mineral based slurry (processed attapulgite or bentonite) for mineral slurry. Ensure that the mineral slurry has a mineral grain size that will remain in suspension and has sufficient viscosity and gel characteristics to transport excavated material to a suitable screening system. Ensure that the percentage and specific gravity of the material used to make the mineral suspension is sufficient to maintain the stability of the excavation and to allow proper concrete placement. Provide polymer slurry as recommended by the manufacturer. Perform control tests on the mineral slurry in the presence of the RE to determine density, viscosity, and pH. Adjust the slurry to meet the requirements shown in Table 503.02.01-1. Table 503.02.01-1 Mineral Slurry3 Property Range Test Density at time of slurry introduction 64.3 – 69.11 lbs/ft3 API 13B, Bentonite Slurry Section (Mud Balance) ASTM D 4380 Density in hole at time of concreting 64.3 – 75.01 lbs/ft3 API 13B, Bentonite Slurry Section (Mud Balance) ASTM D 4380 Viscosity at time of slurry introduction 28 – 452 sec/quart API 13B, Section 2 (Marsh Funnel and Cup) Viscosity in hole at time of concreting 28 – 452 sec/quart API 13B, Section 2 (Marsh Funnel and Cup) Sand content by volume 4% max API 13B, Section 4 (Sand Screen Set) ASTM D 4381 pH at time of slurry introduction 8 – 11 API 13B, Section 6 (Paper Test Strips or Glass-Electrode pH Meter) pH in hole at time of concreting 8 – 11 API 13B, Section 6 (Paper Test Strips or Glass-Electrode pH Meter)
503.02.02 Equipment
Provide equipment as specified: Concrete Batching Plant ................................ ................................ ................................ .............................. 1010.01 Concrete Trucks ................................ ................................ ................................ ................................ .......... 1010.02 Provide Crosshole Sonic Logging (CSL) test equipment as per ASTM D 6760.
503.03 Construction
503.03.01 Furnishing Drilled Shaft Equipment
Ensure that equipment does not introduce uncontrolled exhaust fumes into the surrounding areas, or other occupied areas adjacent to the work site. Use crane and drilling equipment that is fitted with their own separate exhaust systems to adequately vent engine exhaust fumes to the atmosphere away from all confined work sites. Ensure that equipment used for final bottom cleaning does not have a centralizing guide at the tip. Use excavation and drilling equipment having adequate capacity, including power, torque, and down thrust to excavate a hole of both the maximum specified diameter and equal to the deepest shaft shown in the Plans, plus 15 feet or three times the shaft diameter, whichever is greater.
503.03.02 Demonstration Drilled Shaft
503.03.07 Perform CSL as specified in 503.03.04.
Load tests and evaluation of the results must be completed and approved prior to installing the production drilled shafts. Failure to demonstrate the adequacy of methods and equipment to the RE may require the installation of an additional demonstration shaft with appropriate alterations in equipment, methods by the Contractor, or both to elimin ate unsatisfactory results. An additional demonstration shaft and all testing required to demonstrate the adequacy of method or equipment will be at Contractor’s expense. Cut off the concreted demonstration shafts 2 feet below finished grade or 3 feet below the mudline if in water. Restore disturbed areas at demonstration shaft holes to their original condition.
503.03.03 Load Test
If required, perform Axial and Lateral load tests according to ASTM D 1143, D 3966, or D 7383.
503.03.04 Crosshole Sonic Logging
Perform the Non-Destructive Integrity Crosshole Sonic Logging (CSL) testing on completed shafts including rock socket in accordance with ASTM D 6760 (Standard Test Method for Integrity Testing of Concrete Deep Foundations by Ultrasonic Crosshole Testing). Begin CSL on demonstration and all production drilled shafts 72 hours after placing concrete in the shaft. RE may specify a longer minimum time if concrete mix designs or other factors results in slower setting concrete. Ensure that the testing is completed within 20 days after placing concrete. The number of access tubes is provided in the drilled shaft detail in the contract Plans.
503.03.05 Tomography
Use the same equipment and access tubes as the CSL method. Submit the Tomography analysis results to RE for review. Provide the two dimensional (2 -D) horizontal and vertical slices and three dimensional (3 -D) tomographs for the entire shaft between the respective tube pairs. Present these images in color and coded to identify the variations in sonic velocity. Include the complete discussion of the Tomography tests results in the report.
503.03.06 Shaft Coring
If the Department determines the drilled shafts are unacceptable based on CSL test results or CSL test results and tomographic analyses, or observed problems during drilled shaft construction, the RE will direct the Contractor to core the drilled shaft concrete to obtain samples in the area of the possible defects for further evaluation of accepting, repairing, or replacing the drilled shaft. The Department will determine the number, location, and depth of cores required. Ensure the concrete core samples are obtained in accordance with ASTM D 2113. Drill cores at a diameter between 2 to 4 inches. Keep an accurate coring log, properly mark cores with the depth at each interval of core recovery, and place the cores in a crate. Perform strength test on core samples that exhibit questionable concrete as determine by the Department.
503.03.07 Constructing Drilled Shafts
202.03.05 Dispose of regulated material including solids from dewatered slurry as specified in 202.03.09.
903.06.01 B.
503.03.08 Obstructions Removal
The RE will determine if an object is considered an obstruction. Remove surface and subsurface obstructions at drilled shaft locations. The Contractor may need to use special procedures and tools when the obstruction cannot be removed using conventional augers fitted with soil or rock teeth, drilling buckets , or underreaming tools. Special procedures and tools may include chisels, boulder breakers, core barrels, air tools, hand excavation, temporary casing, and increasing the hole diameter. Do not blast without obtaining written approval from the RE.
503.04 Measurement and Payment
The Department will measure and make payment for Items as follows: Item Pay Unit FURNISHING DRILLED SHAFT EQUIPMENT LUMP SUM DEMONSTRATION DRILLED SHAFT LINEAR FOOT LOAD TEST UNIT CROSSHOLE SONIC LOGGING UNIT TOMOGRAPHY UNIT SHAFT CORING LINEAR FOOT DRILLED SHAFT IN SOIL ___" DIAMETER LINEAR FOOT DRILLED SHAFT IN ROCK ___" DIAMETER LINEAR FOOT OBSTRUCTION REMOVAL LINEAR FOOT The Department will make payment for each load test completed and accepted. The Department will not include payment for tomography under CROSSHOLE SONIC LOGGING. If the RE directs Tomography, the Department will make payment for the number of 3 -D evaluations performed and accepted under TOMOGRAPHY. The Department will make payment for CSL performed on all completed shafts under CROSSHOLE SONIC LOGGING. The Department will make payment under SHAFT CORING if the drilled core confirms that the shaft is acceptable. The Department will not make payment for SHAFT CORING if the core confirms that there is a defect. The Department will make payment for 60 percent of the lump sum price bid for furnishing drilled shaft equipment when the equipment necessary for drilling shafts is furnished and drilling of shafts has be gun. The Department will make payment for the remaining 40 percent when all shafts have been drilled and all shaft concrete has been placed to the top of the shafts. The Department will not make payment for sampling and analysis for regulated waste under DEMONSTRATION DRILLED SHAFT, DRILLED SHAFT IN SOIL, or DRILLED SHAFT IN ROCK.