586-4 03
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 586-4.03 Field Drill Holes in Existing Structural Steel. The quantity to be measured for payment will be each hole drilled.
586-5 Basis of Payment
586-5.01 Drilling and Grouting Anchors. The unit price bid for drilling and grouting anchors shall
include the cost of all labor, materials, and equipment necessary to satisfactorily complete the work. The cost of new bolts and/or reinforcing bars will be paid for separately.
586-5.02 Removal of Rivets - Replacement with High Strength Bolts. The unit price bid for removal
of rivets and replacement with high strength bolts shall include the cost of all labor, material and equipment necessary to satisfactorily complete the work, including paint removal and painting. Payment will be made for each installed bolt regardless of whether a rivet was removed from the location.
586-5.03 Field Drill Holes in Existing Steel. The unit price bid for field drill holes in existing steel shall
include the cost of all labor, equipment and materials necessary to satisfactorily complete the work, including paint removal when required. No additional payment will be made for holes drilled through different thicknesses, or through different numb ers of plates. Payment will be made under: Item No. Item Pay Unit 586.0201 Drilling and Grouting Bolts or Reinforcing Bars Each 586.0202 Drilling and Grouting Bolts or Reinforcing Bars (with Non -Destructive Investigation) Each 586.0301 Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test Each 586.0302 Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (with Non - Destructive Investigation) Each 586.0401 Drilling and Grouting Bolts, Overhead or Sustained Tension, with Pullout Test Each 586.0402 Drilling and Grouting Bolts, Overhead or Sustained Tension, with Pullout Test (with Non-Destructive Investigation) Each 586.05 Removal of Rivets -Replacement with High Strength Bolts Each 586.10 Field Drill Holes in Existing Structural Steel Each SECTION 587 - BRIDGE RAILING RECONSTRUCTION
587-1 DESCRIPTION. The work shall consist of the following:
• The removal and disposal of bridge railing. • The Removal and storage of bridge railing. • The installation of stored bridge railing. • The furnishing and installing of box beam bridge railing. • The furnishing and installing of thrie beam bridge railing.
587-1.01 Bridge Railing Removed and Disposed; and Stored Bridge Railing Installed. Material
removed for disposal and material not used for installation shall become the property of the Contractor and shall be removed from the work site.
587-1.02 Bridge Railing Removed and Stored. All bridge railing removed shall remain the property of
the State and shall be transported to a location within the project site designated by the Engineer.
587-2 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 587-2 MATERIALS
587-2.01 New Material. Materials shall meet the requirements of §710 -23, Steel Bridge Railing and the
following: Component ASTM Designation or Standard Specification S3 x 5.7 Post A36 Post Plate A36 Spacer Brackets A36 Rail Connection Angles A36 Rail Plates A36 “U” Bolts, Nuts and Washers A307 Anchor Bolts, Nuts and Washers F3125 GRADE A325 Thrie Beam 710-201 W6 x 25 Post A36 Anchor Bolts (Thrie Beam) A449 Carriage Bolts (Thrie Beam) A307 Nuts and Washers for Carriage Bolts A563 and F436 Attachment Plate A36 Concrete Grouting Material 701-05 NOTE: 1. Thrie Beam Bridge Railing shall be fabricated from 10 gage material.
587-2.02 Stored Material. The Contractor shall choose the best available material for installation,
subject to the approval of the Engineer.
587-3 Construction Details
587-3.01 Bridge Railing Removal. If so indicated on the plans, the existing anchorages shall be reused
for anchoring new or stored railing. Should this be the case, the Contractor shall exercise care removing the railing so as not to damage the existing anchorages. The provisions of §5 89-3.01 shall apply for the removal of any painted bridge railing.
587-3.02 Bridge Railing Storage. The Contractor shall remove, transport, unload and store bridge
railing. Care shall be taken not to damage the railing during the various operations. In the event railing is damaged it shall be repaired or replaced in kind as directed by the Engineer. Such repair or replacement shall be done at no expense to the State.
587-3.03 Stored Bridge Railing Installation. Installation of the railing shall be done in accordance with
the following subsections of section 568, Bridge Railing: Inspection of Railing 568-3.01A1 Base Plates 568-3.01H Field Welding 568-3.01D Non-Metallic Pads 568-3.01I Positioning Railing 568-3.01F Anchor Studs 568-3.01L Positioning Posts 568-3.01G Inspection 568-3.01N NOTE: 1. Bends or kinks in the railing which were present at the place of storage will not be cause for rejection.
587-3.04 Box Beam Bridge Railing Installation. Erection shall be in accordance with requirements of
568-3 01, Erection of Bridge Railing.
The installation procedure shall be coordinated to provide the least disturbance of pedestrian and vehicular traffic, if such traffic is maintained during the course of the work.
587-3 05
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 587-3.05 Thrie Beam Installation
587-4 Method of Measurement
589-3 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 B. Thrie Beam Railing Installation. Measurement will be taken as the number of feet of railing installed. Measurement will be taken along the top of the thrie beam, end -to-end of railing between the limits indicated on the contract plans. No additional measurement will be taken for overlapping sections of railing. If transition sectio ns are installed, measurement will be taken to the end of the transition section indicated on the contract plans.
587-5 BASIS OF PAYMENT. The unit price bid shall include the cost of all labor, materials and
equipment necessary to complete the work. When required, mortar leveling courses, anchor bolts, nuts and washers shall be included in the unit price bid. The drilling and grouting of anchor bolts, when required will be paid for under a separate item. Painting of the railing, if required, shall be paid under a separate item. Payment will be made under: Item No. Item Pay Unit 587.01 Bridge Railing Removal and Disposal Foot 587.02 Bridge Railing Removal and Storage Foot 587.03 Installation of Stored Bridge Railing Foot 587.1001 Box Beam Bridge Rail, One Rail Foot 587.1002 Box Beam Bridge Rail, Two Rail Foot 587.20 Thrie Beam Bridge Rail - Attachment to Existing Bridge Rail Foot 587.21 Thrie Beam Bridge Rail - New Post Installation Mounted on Concrete Surfaces Foot 587.22 Thrie Beam Bridge Rail - New Post Installation Mounted on Steel Surfaces Foot SECTION 588 - BRIDGE JOINT REHABILITATION
588-1 DESCRIPTION. The work in this section shall include work required for bridge joint
rehabilitation.
588-2 MATERIALS. Materials shall meet the requirements specified in the special specifications.
588-3 CONSTRUCTION DETAILS. The extent of work and construction requirements will be
covered by special specifications in the contract documents.
588-4 METHOD OF MEASUREMENT. As specified in the special specifications.
588-5 BASIS OF PAYMENT. As specified in the special specifications.
SECTION 589 - REMOVAL OF STRUCTURAL STEEL (Last Revised September, 2016)
589-1 DESCRIPTION. The work shall consist of removal and disposal of existing structural steel as
shown in the contract documents and as directed by the Engineer.
589-2 MATERIALS. Not Specified.
589-3 Construction Details
589-3.01 General. A minimum of 14 days prior to the removal of existing structural steel, the Contractor
shall submit a written Structural Steel Removal plan meeting the requirements of §202 -3.01A. Demolition Plan to the Engineer for approval. The Structural Steel Removal plan shall set forth all expected