B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Structures (500-599)

589REMOVAL OF STRUCTURAL STEEL

NY · 2024 Standard SpecificationsBook pages 461462View official source ↗

589-3 01

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 B. Thrie Beam Railing Installation. Measurement will be taken as the number of feet of railing installed. Measurement will be taken along the top of the thrie beam, end -to-end of railing between the limits indicated on the contract plans. No additional measurement will be taken for overlapping sections of railing. If transition sectio ns are installed, measurement will be taken to the end of the transition section indicated on the contract plans.

587-5 BASIS OF PAYMENT. The unit price bid shall include the cost of all labor, materials and

equipment necessary to complete the work. When required, mortar leveling courses, anchor bolts, nuts and washers shall be included in the unit price bid. The drilling and grouting of anchor bolts, when required will be paid for under a separate item. Painting of the railing, if required, shall be paid under a separate item. Payment will be made under: Item No. Item Pay Unit 587.01 Bridge Railing Removal and Disposal Foot 587.02 Bridge Railing Removal and Storage Foot 587.03 Installation of Stored Bridge Railing Foot 587.1001 Box Beam Bridge Rail, One Rail Foot 587.1002 Box Beam Bridge Rail, Two Rail Foot 587.20 Thrie Beam Bridge Rail - Attachment to Existing Bridge Rail Foot 587.21 Thrie Beam Bridge Rail - New Post Installation Mounted on Concrete Surfaces Foot 587.22 Thrie Beam Bridge Rail - New Post Installation Mounted on Steel Surfaces Foot SECTION 588 - BRIDGE JOINT REHABILITATION

588-1 DESCRIPTION. The work in this section shall include work required for bridge joint

rehabilitation.

588-2 MATERIALS. Materials shall meet the requirements specified in the special specifications.

588-3 CONSTRUCTION DETAILS. The extent of work and construction requirements will be

covered by special specifications in the contract documents.

588-4 METHOD OF MEASUREMENT. As specified in the special specifications.

588-5 BASIS OF PAYMENT. As specified in the special specifications.

SECTION 589 - REMOVAL OF STRUCTURAL STEEL (Last Revised September, 2016)

589-1 DESCRIPTION. The work shall consist of removal and disposal of existing structural steel as

shown in the contract documents and as directed by the Engineer.

589-2 MATERIALS. Not Specified.

589-3 Construction Details

589-3.01 General. A minimum of 14 days prior to the removal of existing structural steel, the Contractor

shall submit a written Structural Steel Removal plan meeting the requirements of §202 -3.01A. Demolition Plan to the Engineer for approval. The Structural Steel Removal plan shall set forth all expected

589-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 supports, disconnections and adjustments to steel which is to remain. If, during the course of the work it becomes necessary to support, disconnect, or adjust steel not previously noted in the Structural Steel Removal plan, the Contractor shall submit a r evised plan to the Engineer for approval. All work performed on steel which is to remain shall be in accordance with the applicable requirements of the Steel Construction Manual (SCM). Materials removed as part of this work shall become the property of the Contractor, and shall be removed from the work site. Cutting of steel to remain shall be performed in a manner to produce edges and surfaces suitable for welding, in accordance with the requirements of the SCM, Part 603 Surfaces and Edges to be Welded . Thermal cutting of A709 steels shall be performed in accordance with the requirements of the SCM, Part 602 Thermal Cutting of A709 Steels . Replacement of steel removed will be paid for separately.

589-3.02 Steel Structures Coated with Paint. If the steel is coated with paint, prior to the start of steel

removal operations, the paint shall be removed for a minimum distance of 4 inches on each side of the centerline of cut, bolt row, rivet row, or weld, as applicable. The paint removal work s hall be performed in accordance with the requirements of §202 -3.01D. Paint Removal.

589-3.03 Fastener Removals. If rivet shanks, or bolts, cannot be removed by punching without

damaging the base metal, the rivet shank, or bolt, shall be removed by drilling.

A.Bolts. Nuts shall be removed with wrenches, wherever possible, and the bolts driven out with a hand held punch. Alternate removal procedures shall be set forth in the Removal Plan.
B.Rivets. Rivets shall be removed by either of the following methods:
1.Shearing the rivet head, using a pneumatic rivet breaker (helldog), and driving out the rivet shank with a pneumatic punch
2.Flame -cutting the rivet head 1/16 inch above the base metal, using a rivet scarfing tip, and driving out the shank using a pneumatic punch.

589-3.04 Welded Connection Disassembly. Welded connections shall be disassembled in accordance

with the following:

A.Removal. The affected weld shall be removed by means of air carbon arc gouging equipment. To avoid damaging the base material, 1/8 inch of weld material should be left in place. If more removal is needed to break the weld, then the removal shall be done in the vicinity of the component which will not remain. Any damaged steel to remain shall be repaired or replaced in a manner to be approved by the DCES.
B.Grinding. The weld material on the existing steel to remain in place shall be ground flush with the base metal surface. No base metal shall be removed by grinding.
C.Inspection. The Engineer will perform a visual inspection of all weld removal locations. If the Engineer suspects that damage has occurred, the Contractor shall perform a dye penetrant inspection in accordance with the requirements of the SCM. If the Contractor's operations damage existing steel which is to remain in place, the damaged steel shall be repaired, or replaced, as determined by the DCES at no additional cost to the State.

589-4 Method of Measurement.

The quantity to be measured for payment for removal of existing steel with a pay unit of pounds will be in pounds of existing steel removed, measured to the nearest whole pound. The weight of existing steel

590-4 01

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 removed will be computed from the nominal sizes indicated in the contract documents. If the nominal size is not indicated, field measurements shall be used to determine the weight, using 490 pcf as the density of steel. The weight of bolts, rivets and we lds will be neglected, and no deductions will be made for any rivet or bolt holes in the existing steel or for any section loss due to corrosion. The quantity to be measured for payment for removal of existing steel with an each pay unit will be in each unit of existing steel removed.

589-5 BASIS OF PAYMENT. The unit price bid shall include the cost of all labor, materials and

equipment necessary to satisfactorily complete the work, including the removal of paint and fasteners, and disconnecting, supporting, or adjusting steel as necessary. The treatment, handling and disposal of the paint removal waste will be paid separately. Payment will be made under: Item No. Item Pay Unit 589.01nnnn Removal of Existing Steel Pound 589.52nnnn Removal of Existing Steel Each NOTE: nnnn denotes a serialized pay item . SECTION 590 - ADJUSTMENT OF BRIDGE APPURTENANCES

590-1 DESCRIPTION. This work shall consist of adjusting the elevation of bridge joints and drainage

devices to meet the proposed finished elevations in the manner indicated on the Contract Plans. In order to perform the work, it may be necessary to remove structural concrete. Structural concrete removal, if performed, shall be done under its respective item.

590-2 MATERIALS. Materials shall meet the following requirements:

Structural Steel ASTM A36, A242 or A588 Nuts, Bolts, and Washers ASTM A307 Grade A Galvanized Coatings and Repair Methods 719-01 Preformed Elastic Joint Sealer 705-09

590-3 CONSTRUCTION DETAILS. All steel materials, including nuts, bolts, and washers, used as a

part of this work, shall be galvanized in accordance with §719 -01. Any galvanized surface, either existing or installed as a part of this work, which is damaged by welding or abrasion, shall be repaired in accordance with §719 -01. All welding shall be done in accordance with the applicable requirements of the New York State Steel Construction Manual. The Contractor shall take suitable precautions to prevent damage to materials designated to remain - in-place. Damage to such material, due to the Contractor's operations, shall be repaired or the damaged material replaced, as determined by the Engineer. Dimensions shown on the plans shall be verified by the Contractor and any necessary changes approved by the Engineer prior to construction of any needed fabrications. Preformed elastic joint sealer, where required, shall be installed in accordance with the Contract Plans.

590-4 Method of Measurement

590-4.01 Bridge Drainage Devices. The work will be measured as each bridge drainage device as

defined by the Contract Plans which has had its elevation adjusted in accordance with the Contract Plans.

Source: New York Standard Specifications, 2024 Edition. Pages 461462 of 1,264.