SECTION 660 - UTILITIES
660-1 DESCRIPTION. The work in this section shall include special construction required for service
utilities that are publicly, privately or cooperatively owned. The extent of work, and construction specifications will be covered by special provisions in the contract documents.
660-2 MATERIALS. Materials shall meet the requirements specified by the respective utility company.
660-3 Construction Details
660-3.01 General. The installation and testing procedures shall conform to the requirements specified by
the utility company.
660-3.02 Schedule of Work. Work shall be scheduled for minimum interruption of service and must
meet the approval of the utility company and the Engineer. A specified, advance notice, period must be given to the utility company and Engineer prior to interruption of services for construction.
660-3 03
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
660-3.03 Excavation. The requirements specified in Section 206, Trench, Culvert and Structure
Excavation, shall apply.
660-3.04 Backfilling. The requirements specified in Section 203, Select Granular Fill , shall apply.
660-4 METHOD OF MEASUREMENT. As specified in the special specifications.
660-5 BASIS OF PAYMENT. As specified in the special specifications.
Get an email when 660 changes
New York revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.