SECTION 664 - SANITARY SEWER UTILITIES
664-1 DESCRIPTION. The work in this section shall include special construction required for sanitary
sewer utilities that are publicly, privately or cooperatively owned. The extent of work and construction specifications will be covered by special provisions in the contract documents.
664-2 MATERIALS. Materials shall meet the requirements specified by the respective utility company.
664-3 Construction Details
664-3.01 General. The installation and testing procedures shall conform to the requirements specified
by the utility company. NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
664-3.02 Schedule of Work. Work shall be scheduled for minimum interruption of service and must
meet the approval of the utility company and the Engineer. A specified advance notice period must be given to the utility company and Engineer prior to interruption of services for construction.
664-3.03 Excavation. The requirements of section 206 Trench, Culvert and Structure Excavation
shall apply except for trench widths for which standard sheet “Sanitary Sewer Main Pipe Installation Details” shall apply.
664-3.04 Backfill. The requirements specified in Section 203, Select Granular Fill , shall apply.
664-4 METHOD OF MEASUREMENT. As specified in the special specifications.
664-5 BASIS OF PAYMENT. As specified in the special specifications.