SECTION 667 - LOCAL ROAD GRAVEL SURFACE, BASE, AND SUBBASE COURSES (Last Revised September, 2016)
667-1 Description.
667-1.01 General. The work consists of furnishing, placing and compacting gravel surface, base and
subbase courses in conformity with the lines, grades, thicknesses and typical sections shown on the plans, or as determined by field conditions and ordered in writing by the municipality.
667-1.02 Material Types. Provide materials as specified by the following options.
667-2 Materials.
667-2.01 Test and Control Methods. All tests shall be performed by laboratories accredited under the
AASHTO accreditation program. Materials tests and quality control methods pertaining to the work of this section will be performed in conformance with the procedures contained in the appropriate New York State Department of Transportation (NYSDOT) and/or American Association of State Highway and Transportation Officials (AASHTO) publications which are current on the date of advertisement of bids.
667-2.02 Materials Requirements. Provide materials for road gravel surface, base, and subbase courses
667-2 02
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 that consist of Sand and Gravel, approved Blast Furnace Slag or Stone that meet the requirements contained herein. Provide materials well graded from coarse to fine, and free from organic or other deleterious materials. Any gravel material will be rejected if it is determined to contain any unsound or deleterious materials.
667-2 03
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3
667-2.03 Stockpiling. Stockpile all material in accordance with the geotechnical control procedure
“Procedure for the Control and Quality Assurance of Granular Materials”.
667-3 Construction Details.
667-3.01 General. Use uniform gravel types and materials between the roadbed limits.
667-3.02 Placement.
667-3.03 Compaction. When the moisture content is within the limits for proper compaction, compact
the material in accordance with the requirements of Section 203, Compaction. Density tests are not required for the acceptance of these courses. If a subbase course has been disturbed by frost action prior to placing the next course, recompact the layer.
667-3.04 Traffic and Contamination. The movement of highway traffic over the final surface of the
base or subbase may be permitted at locations designated by, and under such restrictions as directed by the Municipality, provided such movements take place prior to the final finishing of this course to the specified tolerance. The movement of construction equipment on this course may be permitted at locations designated by and under such restrictions as directed by the Municipality. No payment will be made for furnishing, placing, maintaining, removing and disposing any protective layer. Include the cost thereof in the price bid. If a layer is damaged or mixed with the subgrade or any other material due to the Contractor’s operation, remove such material and replace it with the appropriate material at no additional cost to the Municipality.
667-3.05 Tolerance.
667-4 METHOD OF MEASUREMENT. The quantity is the number of cubic yards of material,
computed from payment lines shown on the plans or, where changes has been ordered, from payment lines established by the Municipality.
667-5 BASIS OF PAYMENT. The unit price bid for this work includes the cost of furnishing all labor,
material and equipment necessary to complete the work. Include the cost of adding water in the price bid unless the items for furnishing and applying water are included in the contract. No direct payment will be made for losses of material resulting from compaction, foundation settlement, erosion, or any other cause. Include the cost of such losses in the price bid for this item. No deductions will be made for the volumes
667-3 05
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 2026 VOLUME 3 occupied by manholes, catch basins and other such objects. Progress payments will be made after each Type course has been properly placed and compacted. Payment will be made at the unit price bid for seventy-five (75) percent of the quantity. The balance of the quantity will be paid for after the final finishing to the required tolerance and just prior to the placing of the next course or Type. Payment will be made under: Item No. Item Pay Unit 667.01 Local Road Gravel Surface Course Cubic Yard 667.02 Local Road Gravel Base Course Cubic Yard 667.03 Local Road Gravel Subbase Course Cubic Yard SECTIONS 668 AND 669 (VACANT)
Get an email when 667 changes
New York revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.