ITEM 254 PAVEMENT PLANING

254.01 Description. This work consists of planing asphalt concrete and disposing of the cuttings,

and, if specified in the Contract, patching the planed surface.

254.02 Equipment. Use self-propelled planing equipment that has sufficient power and stability

to consistently and efficiently meet the requirements of 254.05 and the plans. Use equipment with either grinding, sawing, or milling type cutters. Ensure that the cutters are mounted rigidly to the carrier and are adjustable to control the depth of cut and cross -slope. Use equipment with a suitable carrier wheelbase or with an automatic control system having an external reference. Ensure that cross -slope adjustments or automatic controls are capable of producing either a variable or a constant cross-slope, as required. For small or confined areas, the Contractor may use suitable supplemental equipment or methods approved by the Engineer.

254.03 Planing. Make one or more planing passes, as necessary, over the designated area to the

depth specified in the plans. Remove irregularities such as bumps, corrugations, and wheel ruts, when required, to establish a new pavement surface elevation or cross-slope. Remove cuttings from the surface following each pass. Before opening the completed area to traffic, thoroughly clean the surface of all loose material that would create a hazard or nuisance, or would redeposit into the surface texture. Dispose of cuttings according to 202. Implement effective measures to control dust, pavement contamination, and the scattering of loose particles during planing and cleaning operations. If planing damages the adjacent pavement, repair the damaged area to the Engineer ’s satisfaction. Ensure that the repaired area matches the adjacent pavement in terms of smoothness and mix type.

254.04 Surface Patching. Patch areas of the planed surface that the Engineer designates that

have spalling or dislodged unsound pavement. Before patching, clean areas of loose material, coat with

407.02 asphalt material, and fill with Item 441 Type 1 or 442 9.5 mm or 12.5 mm material. Level and

compact new material flush to the adjacent planed pavement.

254.05 Surface Tolerances. Plane the surface free from grooves, ridges, gouges, or other

irregularities detrimental to the safe operation of vehicles on the planed surface. If the Contract specifies planing without resurfacing, plane the surface to a smoothness of 1/8 inch in 10 feet (3 mm in 3 m). If the Contract specifies resurfacing after planing, plane the surface to a smoothness of 1/4 inch in 10 feet (6 mm in 3 m). Matc h the surfaces at the edges of adjacent passes within 1/8 inch (3 mm). Ensure that the cross -slope of the planed surface is within 3/8 inch in 10 feet (10 mm in 3 m) of the specified cross-slope.

254.06 Method of Measurement. The Engineer will measure the quantity of Pavement Planing,

Asphalt Concrete by the number of square yards (square meters). The Engineer will measure the quantity of Patching Planed Surface by the number of square yards (square meters).

254.07 Basis of Payment. The Department will not pay for repairs due to damage caused by

planing operations. If the depth of the planed surfaces is increased by more than 3/8 inches (10 mm) the Department will compensate for the additional work. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 254 Square Yard Pavement Planing, Asphalt Concrete (Square Meter) 254 Square Yard (Square Meter) Patching Planed Surface

Get an email when 254 changes

Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Construction and Material Specifications, 2023 (rev. 7/17/2026) Edition. Pages 132–134 of 892. View official source ↗

Ask about this section

Scoped to Ohio Construction & Material Specifications, Section 254 — Pavement Planing. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.