321Cracking and Seating Non-Reinforced Concrete Pavement

OH · 2023 (rev. 7/17/2026) Standard Specifications✓ Full text on BuildSpecBook pages 155–157 Save this section

Ask about Section 321

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

321.01 Description. This work consists of cracking and seating non -reinforced concrete

pavement or concrete base before placing an asphalt concrete pavement.

321.02 Equipment. Use devices for cracking the concrete capable of producing the desired crack

pattern without extensive spalling or excessive shattering. Extensive spalling is spalling over 1 1/4 inches (30 mm) in depth. Do not use whiphammers. Use watering equipment capable of wetting the cracked surface uniformly to reveal the crack pattern. Use a 50-ton (45 metric tons) pneumatic tire roller conforming to the requirements of Item 204 for seating the cracked concrete slabs. Use pneumatic tire towing equipment capable of moving the roller forward and backward along predetermined lines.

321.03 Construction Details. Demonstrate, to the Engineer ’s satisfaction, the ability of the

selected equipment and procedures to produce cracking of acceptable quality by cracking at least three, but no more than five, concrete slabs. When cracking the test slabs, furnish and apply water to dampen the cracked c oncrete to enhance visual determination of the cracking pattern. In addition to 107.07, provide positive provision to contain any flying debris during cracking operations. Crack concrete into nominal 4  4-foot (1.2  1.2 m) segments. In the event panels are already cracked into segments, crack these segments further into nominally equal -sized square or rectangular pieces having longitudinal and transverse dimensions not more than 5 feet (1.5 m) and not less than 3 feet (0.9 m), wherever feasible. Do not allow the cracking equipment to impact the slabs within 1 foot (0.3 m) of another break line, joint, or the edge of the concrete. Furnish and apply water to a check section of three to five slabs at least once each day to verify that a satisfactory crack pattern is being maintained. Make adjustments to the energy or striking pattern when the Engineer deems it necessary, based on the check sections. Roll the cracked concrete until the concrete pieces are firmly seated. Perform rolling with at least two coverages as specified in Item 204. The Engineer will determine the maximum number of coverages of the roller on the test sections to ensure seating without damage to the concrete. Before placing the asphalt concrete, remove all loose pieces of broken concrete that are not firmly seated. Repair all voids, such as spalls, removed loose pieces, joints, or cracks that, in the Engineer ’s opinion, will make uniform compaction of the first asphalt concrete course difficult. Repair voids by applying 407 tack coat, filling with asphalt concrete, and compacting as directed by the Engineer. Do not allow traffic on the cracked concrete before the asphalt concrete base and intermediate courses are in place.

321.04 Method of Measurement. The Engineer will measure the area of non -reinforced

concrete pavement or concrete base satisfactorily cracked and seated in square yards (square meters). The Engineer will use the width of the concrete pavement prior to cracking and will measure the length along the centerline of each roadway or ramp.

321.05 Basis of Payment. Include the cost of all crack pattern test and check sections including

water; and for repairing of joint, cracks, spalls, and voids in the contract unit price for Cracking and Seating Non-Reinforced Concrete Pavement. The Department will pay for the accepted quantities at the contract price as follows. Item Unit Description 321 Square Yard Cracking and Seating Non- Reinforced (Square Meter) Concrete Pavement 400 FLEXIBLE PAVEMENT

Get an email when 321 changes

Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Construction and Material Specifications, 2023 (rev. 7/17/2026) Edition. Pages 155–157 of 892. View official source ↗

Ask about this section

Scoped to Ohio Construction & Material Specifications, Section 321 — Cracking and Seating Non-Reinforced Concrete Pavement. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.