ITEM 656 ROADSIDE CLEANUP

656.01 Description. This work consists of cleaning up outside the excavated and filled areas and

disposing of undesirable plants and other vegetative growth, prunings, rubbish, stumps, conspicuous stones, all down timber, dead brush, logs and timbers; felling and destroying of all snags and such dangerous trees; and pruning trees, native shrubs and similar vegetation but does not include work to be performed under Item 201.

656.02 Intensity of Cleanup. Control the intensity of cleanup to effect a natural transition in

cleanup treatment from the edge of the pavement outward to the limits of the Right -of-Way to avoid sharp demarcation between the artificial and the natural.

656.03 Cleaning. After removal of large objects, clean the designated areas with grubbing rakes

or wide-spaced tooth rakes. Do not disturb or injure desirable grass, vines, or wild flowers.

656.04 Pruning. Prune trees 6 inches (150 mm) or less in diameter and native shrubs and similar

vegetation according to Item 666. Consider the diameter of existing trees to be the diameter measured at 54 inches (1.4 m) above the ground.

656.05 Disposal of Refuse. Use removed materials in the Work when the material conforms to

the specifications; if not, then recycle or dispose of the material according to 105.16 and 105.17.

656.06 Method of Measurement. The Department will measure Roadside Cleanup by the

number of M square feet (square meters) cleaned up and accepted. The Department will determine the boundaries of the area to be cleaned up and the number of units.

656.07 Basis of Payment. The Department will pay for accepted quantities at the contract price

as follows: Item Unit Description 656 M Square Feet Roadside Cleanup (Square Meter)

Roadside Cleanup in other states

Get an email when 656 changes

Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Construction and Material Specifications, 2023 (rev. 7/17/2026) Edition. Pages 624–625 of 892. View official source ↗

Ask about this section

Scoped to Ohio Construction & Material Specifications, Section 656 — Roadside Cleanup. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.