662.01 680 the Project Completion date. After the replacement plantings complete the one year establishment period, the Department will inspect the replacement plantings and notif y the Contractor of the Departments’ findings. As final remedy under the contract, the Contractor is required to install replacement plants for all plantings that did not survive the establishment period at no additional cost to the State. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 661 Each Tree Seedling, (Size), (Species) 661 Each Perennials, (Size), (Species) 661 Each Groundcover and Vines, (Size), (Species) 661 Each Deciduous Shrub, (Size), ( Species) 661 Each Evergreen Shrub, (Size), (Species) 661 Each Deciduous Tree, (Size), (Species) 661 Each Evergreen Tree, (Size), (Species) ITEM 662 LANDSCAPE WATERING
662.01 Description
662.02 Watering
662.03 Method of Measurement
662.04 Basis of Paymen t
662.01 Description. This work consists of furnishing, delivering, applying,
measuring, and scheduling a sufficient amount of water necessary to keep each plant included in Item 661 in a healthy growing condition throughout the period of establishment and the Contract. 662.0 2 Watering. Furnish the water used in watering landscape plants. Thoroughly water all plant material at the time of planting regardless of soil moisture content. Continue to water throughout the period of establishment. Saturate the root zone and mulche d area of each plant without causing run -off according to Table 662.03 -1. During fall planting, continue to water until the ground is frozen and recommence watering after the spring thaw. Furnish a rain gauge approved by the Engineer.
662.03 Method of Me asurement. The Department will measure Landscape
Watering by the number of gallons (liters) delivered to plants from approved metered tanks or individually measured containers as follows: