00197.01 141 Section 00197 - Payment for Force Account Work Force Account Work
00197.00 Scope - The Materials, Equipment and labor rates and procedures established in this
Section apply to Extra Work ordered by the Engineer to be performed as Force Account Work. With the exceptions identified in 00197.01(b), these rates and procedures also apply to other Work when according to other Sections this Section 00197 applies, including, without limitation , the following: • 00140.70 - Cost Reduction Proposals • 00195.20 - Changes to Plans or Character of Work • 00195.30 - Differing Site Conditions • 00199.30(b) - Claims Requirements
00197.01 General :
00197.10 Materials:
00197.20 Equipment :
00197.30 Labor - The Contractor will be paid for all labor engaged directly on Force Account Work,
including Equipment operators and supervisors in direct charge of the specific force account operations, as follows:
00197.40 Invoices for Special Services - Invoices for Special Services that reflect current market
pricing may be accepted without complete itemization of Materials, Equipment, and labor costs, if the itemization is impractical or not customary. The invoice for Special Services shall show credit for commercial trade discounts offered or available. No percentage markup will be allowed other than that specified in 00197.80. 00197.90
00197.80 Percentage Allowances - To the Contractor's actual costs incurred, as limited in this
Section 00197, amounts equal to a percentage markup of such costs will be allowed and paid to the Contractor as follows: Subsection Percent
00197.10 Materials 17
00197.20 Equipment 17
00197.30 Labor 22
00197.40 Special Services 17
When a Subcontractor performs ordered Force Account Work, the Contractor will be allowed a supplemental markup of 8% on each Force Account Work order. These allowances made to the Contractor will constitute complete compensation for overhead, general and administrative expense, profit, and all other Force Account Work costs that were incurred by the Contractor, or by other forces that the Contractor furnished. No other reimbursement, compensation, or payment will be made.
00197.90 Billings - Billings for Force Account Work by the Contractor shall be submitted for the
Engineer's approval on forms provided by the Agency or approved by the Engineer. Billings for Materials (other than Incidental items out of the inventory of the Contractor or Subcontractors), rental Equipment from sources other than the Contractor or Subcontractors, and Special Services, shall be accompanied by copies of invoices for the goods and services. The invoices shall be fully itemized showing dates, quantities, unit prices, and complete descriptions of goods and services provided. Invoices for amounts of $10 or less per invoice are not required, unless requested by the Engineer. Costs included on the billings shall comply with 00197.01(a) and 00197.10 through 00197.40. When a billing for Force Account Work has been paid at the Project level, no further corrections will be made because of further review if those corrections amount to less than $10. 00199.00