00270Temporary Fences

OR · 2024 Standard SpecificationsBook pages 288289View official source ↗

00270.00 222 Section 00270 - Temporary Fences

Description

00270.00Scope - This Work consists of constructing, maintaining, and removing temporary fences,

gates, and gateways as shown or directed.

Materials

00270.10Material - Provide new Material meeting the requirements of 01050.10

Provide temporary barrier meeting the requirements of 0022 6.11(a).

Construction

00270.40Construction - Construct temporary fences, gates, and gateways according to the

applicable parts of Section 01050.

00270.42Rock Protection Fence - Construct concrete barrier according to Section 00 820. Attach

fence to barrier as shown.

Maintenance

00270.60Maintenance - Maintain temporary fences and appurtenances in good condition. Keep the

fences in place until they are no longer needed.

Finishing and Cleaning Up

00270.70General - When t emporary fences and appurtenances are no longer needed remove and

dispose of them according to the applicable parts of Section 00310 except fence fabric, fence wire, posts, and braces may be used in permanent fence installations if the following conditions are met:

• The material was new when installed for temporary purposes. • The material has not been used on previous projects. • The material meets the requirements of 01050.10. • The material is undamaged. • The material is acceptable to the Engineer.

Measurement

00270.80Measurement - The quantities of temporary fence will be measured on the length basis of

each type of temporary fence. Measurement will be from center to center of posts, measured along the line and grade of each separate continuous run of fence as constructed, exclusive of gates.

The quantities of temporary gates will be measured on a unit basis regardless of size or type. The quantities of temporary rock protection fence, barrier mounted will be m easured on the length basis. Measurement will be from center to center of posts, measured along the line and grade of each separate continuous run.

00270.90 223 Payment

00270.90Payment - The accepted quantities of Work performed under this Section will be paid fo r

at the Contract price, per unit of measurement, for the following items: Pay Item Unit of Measurement

(a)Temporary Type _ ___ Fence ................................................................ Foot
(b)Temporary Gates .................................................................................. Each
(c)Temporary Rock Protection Fence, Barrier Mounted ............................ Foot

In item (a) the type of fence will be inserted in the blank.

Payment will be payment in full for furnishing, placing, maintaining, and removing all Materials, including the temporary barrier, and for furnishing all Equipment , labor, and Incidentals necessary to complete the Work as specified.

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 288289 of 1,268.