00501.90 411 PART 00500 - BRIDGES Description

00501.00 Scope - This Work consists of removing and disposing of existing Bridge s or portions of

existing Bridge s as shown or specified. Construction

00501.40 Removal and Disposal - Perform removal and disposal Work according to Section 00290

and Section 00310. Measurement

00501.80 Measurement - No measurement of quantities will be made for Bridge removal Work

performed under this Section. Payment

00501.90 Payment - The accepted quantities of Bridge removal Work will be paid for at the Contract

lump sum am ount for the item "Bridge Removal Work". Payment will be payment in full for furnishing all Equipment , labor, and Incidental s necessary to complete the Work as specified.

Get an email when 00501 changes

Oregon revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 477–477 of 1,268. View official source ↗

Ask about this section

Scoped to Oregon 2024 Standard Specifications for Construction, Section 00501 — Bridge Removal. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.