00599.00 680 Section 00599 - Concrete Slope Paving
Description
00599.00Scope - This Work consists of constructing concrete slope paving on bridge end slopes as
shown, specified, or directed.
Materials
00599.10Materials - Furnish Materials meeting the following requirements:
Grout ..................................................................................................... 02080.40
Construction
00599.40Slope Preparation - Grade the slopes for slope and berm paving, and curbs to the lines
and grades established. Finish the area to a smooth, firm, compacted condition. Dispose of excess materials according to 00330.41(a)(4). If slopes constructed under a separate contract require additional Materials to prepare slopes to the established lines and grades, furnish such M aterials according to 00140.30.
00599.42Slope Paving - Pave slopes with precast or cast -in-place blocks as the Contractor elects
Give the tops of blocks a wood float and brush finish parallel with the long dimension of the block.
00599. 43 Berm Paving - Construct berm paving according to the Plans and Section 00440, except finish the berm paving to a neat, smooth surface.
00599.44Slope Paving Curbs - Construct slope paving curbs according to the Plans and to
Measurement
00599.80Measurement - The quantities of Work performed under this Section will be measured
according to the following:
surface for each bridge end slope.
for each berm.
00599.90 681 Payment
00599.90Payment - The accepted quantities of Work performed under this Section will be paid for
at the Contract unit price, per unit of measurement, for the following items: Pay Item Unit of Measurement
Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment , labor, and Incidentals necessary to complete the Work as specified.
Payment for furnishing additional embankment Materials required for slope preparation constructed under a separate contract will be made according to 00195.20.
00599.90 682
Blank Page