B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
General Conditions

00811Cable Barrier

OR · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 919–920 Save this section

Ask about Section 00811

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

00811.41 853 Section 00811 - Cable Barrier Description

00811.00 Scope - This Work consists of furnishing and installing cable barri er to the lines, grades,

and at the locations shown or directed. Materials

00811.10 Cable Barrier - Furnish cable barrier from the QPL. Provide all cable barriers on the

Project from the same manufacturer regardless of the number of runs of cable barr ier required and regardless of the types of cable barrier required. Use precast or cast -in-place concrete socketed foundation line posts. Furnish and place concrete meeting the requirements of Section 00440.

00811.11 Cable Barrier Terminals - Use the following options as specified:

• Option 1 - Use cable barrier terminals from the QPL that matches the system used. • Option 2A - Tie the cable barrier to new guardrail as approved by the cable barrier manufacturer. • Option 2B - Tie the cable barrier to existing guardrail as approved by the cable barrier manufacturer. Equipment

00811.20 Tension Measuring Device - Measure the cable barrier tension with a manufacturer

supplied measuring device. Labor

00811.30 Manufacturer's Representative - If it is a requirement of the manufacturer to have a

manufacturer's representative on-site during installation, provide the services of a manufacturer's representative at no additional cost to the Agency. Constr uction

00811.40 Cable Barrier - Install cable barrier according to the manufacturer's directions at the

locations shown. Cable anchors and cable overlap as shown are approximate. Locate and overlap the actual anchor according to manufacturer's instruc tions. Keep a tension log and give it to the Engineer upon completion of installation. The tension log shall show the time, date, location, ambient temperature, and the final tension readings, and be signed by the person performing the tension readings. Provide a copy of the manufacturer's recommended tension chart along with the tension log. Perform all tension checks or adjustments required by the manufacturer within a 30 Day period of installation.

00811.41 Cable Barrier Terminals - Place terminals according to the manufacturer's directions, at

locations shown, and as required by the cable barrier manufacturer to meet their minimum requirements. Ensure that there is compatibility between terminals and the cable barrier system installed. 00811.42

00811.42 Placement - Place the concrete anchors and footings, and backfill them at least 2 weeks

prior to tensioning the cables. Set the concrete anchors into the excavation as shown. Set the bottom of the anchor so it has full and even bearing in the s urface under it. Excavate and backfill according to 00810.41. Maintenance

00811.60 Training - After installation, provide at least one 4 hour manufacturer presented training

session to Agency maintenance personnel at no additional cost to the Agency. Measurement

00811.80 Measurement - The quantities of cable barrier will be measured on the length basis, from

center of end post to center of end post along the line and grade of each separate run. Measurement will be made through the ends of the term inals and guardrail connections. The quantities of cable barrier terminals and cable barrier guardrail connections will be measured on the unit basis. Payment

00811.90 Payment - The accepted quantities of cable barrier will be paid for at the Contract unit

price, per unit of measurement, for the following items: Pay Item Unit of Measurement

a.Cable Barrier, Test Level 3 ................................................................... Foot
b.Cable Barrier, Test Level 4 ................................................................... Foot
c.Cable Barrier Terminals ........................................................................ Each
d.Cable Barrier Guardrail Connections .................................................... Each Items (c) and (d) include all special rail elements, brackets, posts , and all necessary appurtenances and hardware. Payment will be payment in full for furnishing and placing all Material s, and for furnishing all Equipment , labor, and Incidental s necessar y to complete the Work as specified.

Cable Barrier in other states

Get an email when 00811 changes

Oregon revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 919–920 of 1,268. View official source ↗

Ask about this section

Scoped to Oregon 2024 Standard Specifications for Construction, Section 00811 — Cable Barrier. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.