00815.90 857 Section 00815 - Bollards Description

00815.00 Scope - This Work consists of furnishing and installing bollards at locations shown or as

directed. Materials

00815.10 Materials - Furnish Material s meeting the following requirements:

Commercial Grade Concrete ...................................................................... 00440 Granular Drain Backfill .......................................................................... 00430.11 Reflective Sheeting (Type III and Type IV) .......................................... From QPL

00815.11 Posts and Sleeves - Use Schedule 40 steel pipe for the posts and either Schedule 40 or

Schedule 80 steel pipe for the sleeves , as shown. Use st eel pipe conforming to ASTM A53, Type E, Grade A.

00815.12 Plates, Shapes, Fasteners, and Hardware - Use plates and shapes conforming to

ASTM A36. Use fasteners and hardware conforming to ASTM A449.

00815.13 Galvanizing - Hot-dip galvanize all metal components after fabrication according to

AASHTO M 111 ( ASTM A123) or AASHTO M 232 ( ASTM A153), as applicable.

00815.14 PVC Pipe - Use Schedule 40 PVC pipe.

00815.15 Painting Bollards - Paint the exposed portion of designated bollards with one coat of the

type and color of coating, as shown or specified. Construction

00815.40 Bollards - Install bollards as shown or as directed.

Measurement

00815.80 Measurement - The quantities of bollards will be measured on a unit basis.

Payment

00815.90 Payment - The accepted quantities of bollards will be paid for at the Contract unit price,

per unit of measurement, for the following items: Pay Item Unit of Measurement

a.Bollards ................................................................................................. Each
b.Removable Bollards .............................................................................. Each
c.Hydrant Bollards ................................................................................... Each Payment will be payment in full for furnishing and placing all Material s, and for furnishing all Equipment , labor, and Incidental s necessary to complete the Work as specified. No separate or additional payment will be made for excavation, backfill, or painting.

Get an email when 00815 changes

Oregon revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 923–923 of 1,268. View official source ↗

Ask about this section

Scoped to Oregon 2024 Standard Specifications for Construction, Section 00815 — Bollards. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.