00850.20 871 Section 00850 - Common Provisions for Pavement Markings Description
00850.00 Scope - This Work consists of furnishing, preparing, and installing all forms of pavement
markings. Materials
00850.10 Materials - Furnish the following Material s from the QPL:
• Adhesive for Pavement Markers • High Performance Pavement Markings • Methyl Methacrylate • Pavement Markers • Reflective Elements* • Marking Paint • Marking Tape • Thermoplastic * Reflective elements used with materials other than marking paint are not required to be from the QPL. Use reflective elements according to the manufacturer's recommendations.
00850.11 Flexible Bituminous Adhesive - At least 2 week s before using, submit for Agency testing
and approval a 15 pound brick sample of flexible bituminous adhesive for each manufacturer lot number, including previously tested and approved lot numbers that are over 1 year old, that will be used on the Project . All previously rejected lot number samples will not be retested. Agency testing and approval is only for acceptance of use of the adhesive. Equipment
00850.20 Equipment - Use Equipment acceptable by the marking material manufacturer for the
method specified and the following:
00850.30 Manufacturer 's Representative - For Sections referencing 00850.30, provide the
services of a manufacturer's representative on-site during the installation, authorized to sign a warranty on behalf of the manufacturer.
00850.31 Manufacturer -Certified Installers - For Sections referencing 00850.31, provide installers
certified by the marking materials manufacturer for the specified marking material and method. Do not begin instal lation before receiving the Engineer's approval. Construction
00850.40 Plans : For Projects with partial striping Plans or Projects without striping Plans, document
all existing striping that is not shown in the Supplemental Drawings. Submit documentation to the Engineer at least 7 Calendar Days before the loss of existing pavement markings.
00850.42 Pre -Striping Conference - Meet with the Engineer and striping Subcontractor, if striping
is done by a Subcontractor, at least 2 weeks prior to beginning striping Work to discuss methods and practices of accomplishing all required striping Work . Submit the following in writing at least 5 Calendar Day s before the pre-striping conference for approval: • A striping schedule showing areas and timing of Work , and placing of material. • A list of materials proposed for use and the application method. • A copy of the manufacturer's installation instructions and Material Safety Data Sheets (MSDS). • Proof of installer's certification for those Sections referencing 00850.31. • Equipment specifications. • A spill recovery plan including: • Name, address, and phone number of the Contractor's contact with the DEQ. 00850.45 873 • Name, address, and phone number of the persons certified and on- call to do clean-up.
00850.43 Prepare and Prime Pavement - Prepare Pavement surfaces according to the following:
• Existing Pavement Surfaces - When required by the pavement marking manufacturer, remove pavement markings from existing Pavement surfaces that will adversely affect the bond of new pavement marking Material to the Roadway surface according to 00225.45 . Remove all other contaminants from existing Pavement surfaces that may adversely affect the installation of new pavement mar kings by sandblasting, shot -blasting, or sweeping. Air blast the Pavement with a high-pressure system to remove extraneous or loose material. • New Asphalt Concrete Surfaces - Remove contaminants from new AC surfaces that may adversely affect the installation of the pavement markings by sandblasting, shot -blasting, or sweeping. Air blast the Pavement with a high-pressure system to remove extraneous or loose material. Apply Materials to new asphalt concrete that is sufficiently cured according to the manufacturer's recommendations. • New Portland Cement Concrete Surfaces - Remove curing compounds and laitance by an approved mechanical means . Air blast the Pavement with a high- pressure system to remove extraneous or loose material . Apply M aterials to concrete that has reached a minimum compressive strength of 3,000 psi and that is sufficiently cured according to the manufacturer's recommendations. After the Pavement surface is clean and dry, apply primer as recommended by the manufacturer to the area receiving the pavement markings. Apply the primer in a continuous, solid film according to the recommendations of the primer manufacturer and the pavement markings manufacturer.
00850.44 Alignment Layout - Place control points for lines every 50 feet on tangent and
every 25 feet on a curve. Using these control points, layout a continuous narrow guideline for each line, along one edge of, or uniformly offset from the intended per manent line location. Do not proceed with installation until the guidelines are approved by the Engineer. For inlaid/grooved markings, indicate the exact grind-out location with a 4 inch wide line as the guideline. For broken lines, lane drop lines, and dotted lines, use 10 feet, 3 feet, and 2 feet long sections respectively, at the cycle length shown. For solid lines, use a continuous line. Use marking paint from the QPL applied at a thickness of 6 mils. Reflective elements are not required.
00850.45 Installation - Apply pavement marking Materials to clean dry Pavement surfaces and
according the following: • Place Material between May 1 and October 15. Place Material according to the manufacture r's installation instructions . • Place parallel double lines in one Pass. • Place the specified width of lines in one Pass. • The Pavement surface shall not be visible in the striped areas. • The top of pavement marking shall be smooth and uniform. • Skip line ends shall be square and clean. • Place pavement marking lines parallel and true to line. • Place skip lines so that they are in cycle with at least one end of any adjacent project. • Place markings in proper alignment with existing markings. • Immediately clean up marking material dribbled beyond the cutoff. 00850.46 874 For inlaid/grooved markings, grind the slot as shown. For each grinder operator and piece of Equipment , obtain the Engineer's and manufacturer representative's approval of the slot within the first 150 feet for solid lines and within the first 300 feet for skip lines. Do not proceed with grinding until the slot is approved. Repeat this process for each new grinder operator or new piece of Equipment used. After grinding, obtain the Engineer's and manufacturer representative's approval before placing marking material. Clean the area with high pressure air immediately before placing the marking material.
00850.46 Placement Tolerance - Allowable tolerances for insta llation are:
Lateral location on roadway: 1/2 inch on tangents; 1 inch on curves • 40-foot skip cycle length: ± 2 inches for skip length, ± 2 inches for gap length • 12-foot skip cycle length: ± 3/4 inch for skip length, ± 1 inches for gap length • 8-foot skip cycle length: ± 1/2 inch for skip length, ± 3/4 inches for gap length • Skip Cycle: A tolerance of 1/10 of the skip line length on the first skip line of a run, but it shall be on cycle within one skip • Double lines: Parallel, with a gap tolerance of ± 1/2 inch • Width of lines: + 3/8 inch, - 1/16 inch • Thickness of flat, surface applied lines: + 1/3 of the specified thickness, − 1/10 of the specified thickness • Divergence of parallel double lines: ± 3/8 inch 00850 .47 Quality Control - Record the following readings for each type and color of marking material and the locations where they were taken. Submit the results to the Agency within 1 Day of taking the readings.
00850.50 General - Protect all applied markings from traffic until sufficiently cured so as not to be
damaged or tracked by traffic movements. Finishing and Cleaning Up
00850.70 Disposal of Waste - Dispose of all materials according to 00290.20.
00850.71 Removal and Repair of Unacceptable Work - Remove unacceptable materials according
to 00225.45. If more than one repair is required in a single 300-foot section, grind and repair the entire 300-foot section. 00855.00