8−85811.04 METHOD OF MEASUREMENT.
811.04.1 Weep Holes and Pavement Subdrains. Unless covered by a Special Provision,
together with a corresponding Proposal Item, weep holes and pavement subdrains will not be measured separately for payment. 811.04.2 Wall Drains. "Wall Drains" will be measured by the number of linear feet actually installed in accordance with the Plans and/or as directed by the Engineer. 811.05 BASIS OF PAYMENT.
811.05.1 Weep Holes and Pavement Subdrains. Unless covered by a specific Proposal Item,
materials for the installation of weep holes and pavement subdrains will not be paid for separately, but will be included as incidental items in the respective contract unit prices per cubic yard as listed in the Proposal for the applicable classes of Portland cement concrete. 811.05.2 Wall Drains. The accepted quantity of "Wall Drains" will be paid for at the contract unit price per linear foot as listed in the Proposal. The price so-stated constitutes full and complete compensation for all labor, materials, and equipment, including fittings and filter stone, filter fabric, and all incidentals required to finish the work, complete and accepted by the Engineer.
812.01 DESCRIPTION. This work consists of the furnishing and installation of waterstops in
various types of concrete joints at the locations shown on the Plans or as directed by the Engineer, all in accordance with these Specifications. 812.02 MATERIALS. Polyvinyl Chloride (PVC) Waterstops. PVC waterstops shall be manufactured by the extrusion process from an elastomeric plastic compound, the basic resin of which shall be PVC. The compound shall contain any additional resins, plasticizers, stabilizers, or other materials needed to assure that, when the material is com pounded, it will meet the performance requirements given in the table below. No reclaimed PVC or other material shall be used. The PVC material shall comply with the fo llowing physical require ments when tested under the indicated ASTM test method. 8−86 Specific Gravity ASTM D792 Max 1.35 Durometer Hardness ASTM D2240 75 +/- 5 Tensile Strength ASTM D412 Min 1.8 ksi Elongation ASTM D412 Min 350% Cold Brittleness ASTM D746 -35° F Stiffness in Flexure ASTM D747 Min 0.350 ksi
812.03 CONSTRUCTION METHODS. Waterstops shall be installed at locations indicated on the
Plans. Where movement at the joint is provided for, the waterstop shall be capable of accommodating such movement without injury. Wa terstops shall be spliced, welded or soldered to form durable continuous watertight joints. Precautions shall be taken so that the waterstops shall be neither displaced nor damaged by construction operations or other means. Damaged components shall be repaired to the satisfaction of the Engineer at no additional cost to the State. All surfaces of the waterstops shall be kept free from oil, grease, dried mortar, or any other foreign matter while the waterstop is being embedded in concrete. Means shall be used to ensure that all portions of the waterstop designed for embedment shall be tightly enclosed by dense concrete per the manufacturer’s recommendations. A Certificate of Analysis from an approved independent test ing laboratory shall be provided to the Engineer. The certificate shall state that the material furnished conforms without exception to all the requirements specified herein; and shall also include all qualitative and quantitative test results.