SECTION 829 — BRIDGE SCUPPER PIPING — BRIDGE SCUPPER PIPING

829.01 Description.

This work includes providing polyvinyl chloride (PVC) scupper piping on bridges at the required locations.

829.02 Materials.

Polyvinyl Chloride Scupper Piping.

a.Pipe. Use pipe that conforms to ASTM D 1785, PVC 1120, Schedule 80. Use solvent cement fittings that conforms to ASTM D 2467, Schedule 80.
b.H ardware. Use straps, angles, etc., that conform to SECTION M05 and are galvanized according to AASHTO M111.
c.M anufacturer ’s Certification. Furnish the manufacturer ’s certification that the materials provided meet specification requirements.

829.03 Construction Methods.

Polyvinyl Chloride (PVC) Scupper Piping.

a.Field Measurements . Make all appropriate field measurements and evaluate special conditions for installation before the preparation of Shop Drawings.
b.S hop Drawings . Submit Shop Drawings of the pipe assembly according to Subsection 105.02.
c.H andling. D uring handling and storage, avoid damage to the pipe from impact, bending, compression or abrasion.
d.P reparation . Cut pipe with saws or pipe cutters designed specifically for polyvinyl chloride material. Protect t he pipe and fittings from serrated holding devices and abrasions. Remove all burrs and wipe clean dust and dirt from the jointing surface. Bevel pipe ends according to the manufacturer’s recommendations.
e.I nstallation. Install and support the pipe, and construct joints according to the manufacturer’s recommendations. Soften the j ointing surface and make semi -fluid, and apply sufficient cement to fill the gap between pipe and fittings. Remove all excess cement.

829.04 Method of Measurement.

Polyvinyl Chloride Scupper Piping will be measured by the number of linear feet of each type of drainpipe installed.

Part 800 — Bridge Structures August 2025

SECTION 829 — BRIDGE SCUPPER PIPING 800-175

829.05 Basis of Payment.

The Department will pay for the completed and accepted quantities as follows. Pay Item Pay Unit Polyvinyl Chloride Scupper Piping LF The price constitutes full compensation for all labor, materials and equipment, including straps, hardware, bolts and all incidentals required to finish the work, complete and accepted.

Referenced in this section

Get an email when 829 changes

Rhode Island revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction (Blue Book), 2022 (Aug 2025 compilation) Edition. Pages 543–544 of 951. View official source ↗

Ask about this section

Scoped to Rhode Island RIDOT Standard Specifications for Road & Bridge Construction, Section 829 — Bridge Scupper Piping. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.