General Provisions (00100-00999)

937MAINTENANCE AND MOVEMENT OF TRAFFIC PROTECTIVE DEVICES

RI · 2024 Standard SpecificationsBook pages 612615View official source ↗

9−80 Specification. All such maintenance and movement work on these devices shall take place after their initial installation on the project and prior to their final removal from same.

937.02 MATERIALS. Not applicable.

937.03 CONSTRUCTION METHODS. 937.03.1 Normal Operations. The Contractor shall maintain all signs, barricades and other protective devices in a sturdy, clean, and legible condition. In this regard "maintenance" involves the following: repairing; adjusting; washing; repainting; and the re-application of reflective sheeting.

The various devices shall be located in their proper positions such that they reflect existing traffic conditions. As conditions change, signs and devices shall be removed and covered so that the respective messages are not visible to appr oaching traffic. Where c hanged condi tions warrant, new devices will be provided. When construction operations are not in progress, all unnecessary signs shall be appropriately covered. Care shall be exercised such that weeds, sh rubbery, and cons truction materials, equipment, and spoils do not obscure the message of any sign, light, or barricade. No defective and/or damaged devices shall be installed. Devices showing defects or damages caused as a result of the Contractor's oper ations or negligence shall be either repaired or removed and replaced at no additional cost to the St ate. When the Engineer determines that a sign or device requires replacement due to normal wear and tear, or that said sign or device has been severely damaged by causes other than the Contra ctor's operations, these signs and devices shall be replaced and paid for in accordance with the provisions of those Sections of these Specifications that apply to the particular devices in question. 937.03.2 Emergencies. At the preconstruction conference, the Contractor shall provide the Department with both the home telephone and beeper nu mbers of at least three personnel who will be available on a 24-hour basis for the duration of the Contract. These persons shall constitute the "contacts" in the event of an emergency. Upon notification by the Engineer, the Contra ctor, through its contact personnel, will respond to the site of an emergency within ninety minutes and immediately take steps to commence repair operations. 937.04 METHOD OF MEASUREMENT. This work does not require a measurement for payment.

937.05 Basis of Payment.

937.05.1 Payment for Full Compliance. "Maintenance and Movement of Traffic Protective

Devices" will be paid for at the contract lump sum price as listed in the Proposal. The price so-stated constitutes full and complete compensation for all labor, materials, and equipment, including removing the devices from their initial locations, handling, maintaining, transporting and relocating said devices to storage or to subsequent intermediate locations at which they are to be used for traffic control, and all incidentals required to finish the work, comp lete and accepted by the Engineer. 9−81 Monthly progress payments under this item will be made at a rate determined by dividing the contract lump sum price by the number of months allocated for completion of the contract. Said number of months shall be equal to the difference between the contract completion date and the date of the Notice to Proceed. At the discretion of the Engineer, payment fo r authorized contract time extensions will be made at either the calculated monthly rate as defined above or on a Force Account basis in accordance with Subsection 109.04; Differing Site Conditions, Changes, Extra Work and Force Account Work , of these Specifications. If the contract is completed prior to the authorized completion date, the final monthly payment will consist of the remaining balance of the contract lump sum price. No payment will be made for unauthorized contract time extensions.

937.05.2 Failure to Comply.

a.Maintenance. If, in the judgment of the Engineer, the Contractor fails to adequately and safely maintain traffic control devices along any portion of the project, a charge will be assessed as follows: For each day the Engineer determines that the Contractor has failed to comply with the provisions of this Section, the daily charge set forth in Special Provision Code 937.1000 will be deducted from monies due the Contractor.
b.Movement. If the Contractor fails to remove and/or relocate traffic control devices for compliance with the traffic-related work restrictions included in the Transportation Management Plan or to otherwise meet changes in traffic condi tions, construction operations, or other conditions affecting the safety and/or mobility of the traveling public, a charge(s) will be assessed as follows: When the Engineer determines that the Contractor has failed to comply with the provisions of this Section, the appropriate charge(s) set forth in Special Provision Code 937.1000 will be deducted from monies due the Contractor.

937.05.3 Emergencies. In the event that emergency repair work has not been initiated within the

ninety-minute time frame specified above, the sum of three times the daily charge set forth in Special Provision Code 937.1000 will be deducted from monies then due the Contractor for each day until said repair work is undertaken.

a.Repair Work by Others. If emergency repair work is performed by a party other than the Contractor or one of its first-tier subcontractors, and if the other party is not compensated for its work within 60 days following completion of the repair work, the Engineer reserves the right to withhold monies then due the Contractor in or der to provide payment to the other party. 9−82 SECTION 938 PRICE ADJUSTMENTS

938.01 DESCRIPTION. The intent of this provision is to insure adequate and fair compensation for

unpredictable and fluctuating costs which, from time to time, occur in the prices of Liquid Asphalt and Diesel Fuel. The price adjustment provisions are made part of the Contract to assure more realistic bidding and encourage competition. 938.02 DEFINITIONS. 938.02.1 Base Price. The base price is the unit price of the material (FOB Terminal), as determined by the Department, just prior to the first date that the NOTICE TO CONTRACTORS is advertised in the public press. 938.02.2 Period Price. The period price is the unit price of the material (FOB Terminal), as determined by the Department, for any one mont h period following the NOTICE TO PROCEED during which the price varies from the base price. 938.03 PRICE ADJUSTMENT. Price adjustment will be determined by the difference between the Period Price and the Base Price. Price adjustments will be made at the end of each month during which a); work was accomplished on the project and b); prices varied. Price adjustments for work performed after the contract completion date, as may be modified by approved time extension(s), will be t he lesser amount calculated from the following two algorithms (a & b); whereas credit due the Department will be greater of the two calculations.

a.The price adjustment calculated using the actual monthly Period Prices in effect at the time of the construction.
b.The price adjustment calculated using the monthly Period Prices in effect during a period determined by setting the last day of relevant work to the contract completion date as may have been modified by approved time extensions. Price adjustments due the contractor will be m ade in accordance with an approved Contract Addendum. Credit due the Department will be proc essed by deducting monies from progress payments or by other means if there are insufficient progress payments remaining.

938.03.1 Liquid Asphalt Cement. The asphalt content will be the optimum amount used in every

ton of bituminous concrete mixture, as determined by the Department's Materials Engineer, using the method for determination of optimum asphalt cement content as set forth in SECTION M.03 of these Specifications. The Price Adjustment will be determined by multiplying the total weight of liquid asphalt, in tons, by the difference between the base price and period price. The Base Price of Liquid Asphalt Cement is set forth in Special Provision Code 938.1000 . 9−83938.03.2 Diesel Fuel. The fuel for operating the plant, and the fuel for hauling and placing bituminous concrete, will equal the total number of tons of bituminous concrete placed during the month in question times a fuel adjustment factor of 2.5 gallons of fuel per ton of bituminous concrete. Tonnage of bituminous concrete placed during the month in question will equal the sum of the weights indicated on the Daily Automated Recordation printout slips provided at the plant. The Price Adjustment will be determined by multiplying the total volume of fuel, in gallons, by the difference between the base price and the period price. No price adjustment will be made unless the amount of the adjustment, plus or minus, exceeds $250.00 for the month. The Base Price of Diesel Fuel is set forth in Special Provision Code 938.1000 . SECTION 939 STONE WALLS IN HISTORIC, SCENIC OR RURAL AREAS 939.01 DESCRIPTION . This work consists of the resetting and construction of stone walls in historic, scenic, or rural areas. Such walls require special treatment as indicated herein, and shall be constructed at locations indicated on the Plans or as directed by the Engineer, all in accordance with these Specifications. 939.02 MATERIALS .

939.02.1 Stones . Stones for walls to be reset shall include stones in the existing wall, with

additional stones as required to complete the wall construction. Additional stones shall conform to the stones in the existing wall relative to shape, color, texture and geological composition. Stones for new walls shall conform to stones found in nearby walls relative to the aforementioned characteristics, unless otherwise noted on the Plans or directed by the Engineer. Stones used below grade, for the core, or for the back of a retaining wall need not meet these criteria. However, the stones must conform to SECTION M.14; STONE FOR MASONRY , of these Specifications, and must be appropriately sized and shaped to permit proper interlocking with the existing stones. Any special features such as lintels, gate posts, copings, markers, etc., shall be retained for resetting. 939.02.2 Mortar . Mortar shall conform to the requirements of Subsection M.04.03.5; Mortar , of these Specifications.

Source: Rhode Island Standard Specifications (Bluebook), 2024 Edition. Pages 612615 of 826.