653— U-Section Posts

SC · 2025 Standard Specifications✓ Full text on BuildSpecBook pages 539–539 Save this section

Ask about Section 653

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Division 600 — Section 653

600-213 Section 653 — U-Section Posts

653.1 Description

1 Furnish, fabricate, and install U -section posts.

653.2 Materials

1 Use the specified number of steel U -section posts weighing either 2 lb/ft (2P) or 3 lb/ft (3P) of the specified length in feet to support flat sheet signs and delineators or to brace certain flat sheet signs indicated on the Plans (e .g., 2-3P-12′). The sizes indicate the weight of the posts per linear foot (tolerance of ±5%) before galvanizing. 2 Use posts that are made of either re- rolled rail steel or billeted steel conforming to the mechanical and implied chemical requirements of ASTM A499, Grade 60. 3 Use 2P U -section posts, 10 ft long, for bridge end markers and 2P U -section posts, 7.5 ft long, for delineators. For all other posts, use the weight and length indicated on the Plans and the Standard Drawings . 4 Use retroreflective sign post panels constructed of a nonmetallic composite or 3mm aluminum composite material covered with a 3- in. wide Type III sheeting. Use sheeting that complies with Subsection 651.2.3 . Use approved panels included on the Approved Products List For Traffic Control Devices in Work Zones .

653.3 Construction

653.3.1 Fabrication

1 Ensure that U -section posts have a minimum of fifty -eight, ⅜-in. diameter holes punched on 1- in. centers beginning 1 in. from the top of the post. If additional holes are necessary, conform to the standard punching procedures, but do not locate holes less than 1 in. on centers. 2 After fabrication, hot -dip galvanize the full length and total area of each post according to ASTM A123.

653.3.2 Erection

1 Unless otherwise directed by the RCE , drive the U -section posts firmly into ground at the required line and grade. Protect the posts while driving with a special driving cap. Install post s in a true vertical position. 2 Align signs, delineators, and bridge end markers accurately. Mount signs and delineators on the flange side of the U -section posts, except where the Plans show signs mounted on both sides. Mounting of signs may be by some other

Referenced in this section

Get an email when 653 changes

South Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: South Carolina Standard Specifications for Highway Construction, 2025 Edition. Pages 539–539 of 908. View official source ↗

Ask about this section

Scoped to South Carolina Standard Specifications for Highway Construction, Section 653 — — U-Section Posts. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.