725— Shop Plans and Working Drawings for Structures

SC · 2025 Standard Specifications✓ Full text on BuildSpecBook pages 818–818 Save this section

Ask about Section 725

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Division 700 — Section 725

700-223 Section 725 — Shop Plans and Working Drawings for Structures

725.1 Description

1 Submit Shop Plans and Working Drawings for construction projects as required in the Standard Construction Specifications, Supplemental Specifications, Supplemental Technical Specifications, and Special Provisions. 2 Shop Plans become a permanent part of the project, such as structural steel fabrication drawings, prestressed concrete beam drawings, or any other supplementary plans or similar data that the Contractor is required to submit to the RCE for review before fa brication. Shop Plans, including any red- lined revisions, become part of the as -built drawings for the completed structure. 3 Working Drawings as defined in Subsection 101.3 may include erection plans, falsework plans, cofferdam plans, temporary structure plans, or any other supplementary plans or similar data that the Contractor is required to submit to the RCE for review before assembly of the subject of the drawings on the project site.

725.1.1 Shop Plans

1 Submit Shop Plans and supporting engineering calculations to the RCE no later than 30 days before fabrication. Submit Shop Plans through an approved electronic system in Adobe PDF format. No extension of Contract time is granted for delays due to failure to observe this time requirement. Ensure that the fabricator of the material component of the structure notif ies the OMR a minimum of 14 days before the start of fabrication. 2 Clearly identify the SC File Number, Project ID, County Name(s), Route Number(s), and Project Description in the Shop Plan submittal. 3 Ensure that Shop Plans are accurate, complete, neat, and legible. Shop Plans should be scaled such that they are legible on an 11- in. × 17-in. paper size, when printed. 4 Electronically submit Shop Plans for the following items: • Armor plates; • Bridge bearings ; • Bearing or sole plates, shims, booster plates, and other structural steel bearing assembly components; • Anchor bolt assemblies; • Tie rod assemblies; • Intermediate steel diaphragms; • Structural steel members;

Get an email when 725 changes

South Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: South Carolina Standard Specifications for Highway Construction, 2025 Edition. Pages 818–818 of 908. View official source ↗

Ask about this section

Scoped to South Carolina Standard Specifications for Highway Construction, Section 725 — — Shop Plans and Working Drawings for Structures. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.