General Provisions (Items 1-10)

10Maintenance/Traffic Materials Contracts

TX · 2024 Standard SpecificationsBook pages 84108View official source ↗

ITEM 10 APPLIES TO MAINTENANCE MATERIALS CONTRACTS (MMC) AND TRAFFIC MATERIALS CONTRACTS (TMC) WITH NO FEDERAL FUNDS BEING USED. ITEMS 1 –9 DO NOT APPLY TO MMC AND TMC CONTRACTS.

Article 1 — Abbreviations and Definitions

1.1 Applicability . Wherever the following terms are used in these specifications or other Contract documents,

the intent and meaning will be interpreted as shown below.

1.2 Abbreviations .

AASHTO American Association of State Highway and Transportation Officials AMRL AASHTO Materials Reference Laboratory ANSI American National Standards Institute ASNT American Society for Nondestructive Testing ASTM American Society for Testing and Materials CFR Code of Federal Regulations DMS Departmental Materials Specification EPA U.S. Environmental Protection Agency FHWA Federal Highway Administration, U.S. Department of Transportation MPL Material Producer List NEMA National Electrical Manufacturers Association NEPA National Environmental Policy Act NRM Nonhazardous Recyclable Material OSHA Occupational Safety and Health Administration, U.S. Department of Labor PS&E Plans, Specifications, and E stimates QA Quality Assurance QC Quality Control SBE Small Business Enterprise TAC Texas Administrative Code TCEQ Texas Commission on Environmental Quality USC United States Code

1.3 Definitions.

1.3.1 Actual Cost . Contractor’s actual cost to provide material, including labor, equipment, and project overhead

necessary for the work.

1.3.2 Addendum . Change in proposal forms developed between advertising and bid submittal deadline.

1.3.3 Advertisement . The public announcement required by law inviting bids for work to be performed or materials

to be furnished.

1.3.4 Affiliates . Two or more Bidders are affiliated if they share common officers, directors, or stockholders; a

family member of an officer, director, or stockholder of one Bidder serves in a similar capacity in another of the Bidders; an individual who has an interest in, or controls a part of, one Bidder either directly or indirectly also has an interest in, or controls a part of, another of the Bidders; the Bidders are so closely connected or associated that one of the Bidders, either directly or indirectly, controls or has the power to control another Bidder; one Bidder controls or has the power to control another Bidder; or the Bidders are closely allied 75 through an established course of dealings including, but not limited to the lending of financial assistance. Refer to 43 TAC §9.12(g), “Affiliated Entities.”

1.3.5 Anticipated Profit . Profit for work not performed.

1.3.6 Apparent Low Bidder . The Bidder determined to have the numerically lowest total bid as a result of the

tabulation of bids by the Department.

1.3.7 Award . The Commission’s acceptance of a Contractor’s bid for a proposed Contract that authorizes the

Department to enter into a Contract.

1.3.8 Bid. The offer from the Bidder for performing the work described in the proposal.

1.3.9 Bid Bond. The security executed by the Contractor and the Surety furnished to the Department to guarantee

payment of liquidated damages if the Contractor fails to enter i nto an awarded Contract.

1.3.10 Bid Error . A mathematical mistake made by a Bidder in the unit price entered into the proposal.

1.3.11 Bidder . An individual, partnership, limited liability company, corporation, or joint venture submitting a bid for

a proposed Contract.

1.3.12 Bidders Questionnaire. A prequalification form that reflects detailed equipment and experience data but waives audited financial data.

1.3.13 Callout Work . A type of Contract that requires a Contractor’s response on an as -needed basis through

issuance of a work order.

1.3.14 Certificate of Insurance. A form approved by the Department covering insurance requirements stated in the

Contract.

1.3.15 Change Order . Written order to the Contractor detailing changes to the specified work, item quantities, or

any other modification to t he Contract.

1.3.16 Commission . The Texas Transportation Commission or authorized representative.

1.3.17 Confidential Questionnaire . A prequalification form that reflects detailed financial and experience data.

1.3.18 Contract . The agreement between the Department and the Contractor establishing the obligations of the

parties for furnishing of materials and performance of the work prescribed in the Contract documents.

1.3.19 Contract Documents. Elements of the Contract including, but not limited to the plans, specifications

incorporated by reference, special provisions, special specifications, bid bond, change orders, and supplemental agreements.

1.3.20 Contract Term . The number of calendar days until the Contract terminates or the date the Contract

terminates, unless extended by mutual agreement.

1.3.21 Contractor . The individual, partnership, limited liability company, corporation, or joint venture and all

principals and representatives with which the Contract is made by the Department. For MMC and TMC Contracts and these specifications , the contracted material supplier is considered a Contractor.

1.3.22 Debar (Debarment) . Disqualification of an entity from bidding on or entering into a Contract with the

Department, from participating as a subcontractor under a Contract with the Department, and from participating as a supplier of materials or equipment to be used under a Contract with the Department. Refer to 43 TAC §10.2, “Definitions.” 76 1.3.23. Department . The Texas Department of Transportation (TxDOT).

1.3.24 Departmental Materials Specifications. Reference specifications for various materials published by the

Materials and Tests Division.

1.3.25 Electronic Vault . The Department’s bidding system where electronic bids are stored before bid opening.

1.3.26 Engineer . The Chief Engineer of the Department or the authorized repr esentative of the Chief Engineer.

1.3.27 Escalation Ladder . A process to determine issue resolution during the course of the Contract.

1.3.28 Expedited Work Order . A work order requiring material to be delivered within 48 hr .

1.3.29 Family Member . A family member of an individual is the individual’s parent, parent’s spouse, stepparent,

stepparent’s spouse, sibling, sibling’s spouse, spouse, child, child’s spouse, spouse’s child, spouse’s child’s spouse, grandchild, grandparent, uncle, uncle’s spouse, aunt, aunt’s spouse, first cousin, or first cousin’s spouse. Refer to 43 TAC § 9.12(g), “Affiliated Entities.”

1.3.30 Hazardous Materials or Waste. Hazardous materials or waste include but are not limited to explosives,

compressed gas, flammable liquids, flammable solids, combustible liqui ds, oxidizers, poisons, radioactive materials, corrosives, etiologic agents, and other material classified as hazardous by 40 CFR 261, or applicable state and federal regulations.

1.3.31 In Writing . Communication memorialized, including written or electronic documentation by email or letter

only.

1.3.32 Independent Assurance Tests. Tests used to evaluate the sampling and testing techniques and equipment

used in the acceptance program. The tests are performed by the Department and are not used for acceptance purposes.

1.3.33 Inspector . The person assigned by the Engineer to inspect for compliance with the Contract and the

materials used.

1.3.34 Joint Venture . Any combination of individuals, partnerships, limited liability companies, or corporations

submitting a single bid proposal.

1.3.35 Letting . The receipt, opening, tabulation, and determination of the apparent low Bidder.

1.3.36 Letting Official. The Executive Director or any Department employee empowered by the Executive Director to officially receive bids and close the receipt of bids at a letting.

1.3.37 Licensed Professional Engineer . A person who has been duly licensed by the Texas Board of Professional

Engineers to engage in the practice of engineering in the State of Texas; also referred to as a Professional Engineer.

1.3.38 Maintenance Mate rials Contract . A type of Contract for the purchase of roadway materials.

1.3.39 Material Producer List . Department maintained list of approved products, materials, laboratories, service

providers, manufacturers, and producers.

1.3.40 Materially Unbalanced Bid . A bid th at generates a reasonable doubt that award to the Bidder submitting a

mathematically unbalanced bid will result in the lowest ultimate cost to the State.

1.3.41 Materials Contract . A Contract entered under Transportation Code, § 223.001(b)(2) and (3), for roadway

materials, traffic control devices, or safety devices. These Contracts are designated as “MMC” and “TMC” for Maintenance Materials Contracts or Traffic Materials Contracts , respectively. 77 1.3.42. Materials Supplier’s Questionnaire. A prequalification form that ref lects basic information, such as company contact, signature authority, and other requirements, but waives financial, equipment, and experience data.

1.3.43 Mathematically Unbalanced Bid . A bid containing bid prices that do not reflect reasonable actual costs plus

a reasonable proportionate share of the Bidder’s anticipated profit, overhead costs, and other indirect costs.

1.3.44 National Holidays . January 1, the last Monday in May, July 4, the first Monday in September, the fourth

Thursday in November, December 24, and December 25.

1.3.45 Nonhazardous Recyclable Material . A material recovered or diverted from the nonhazardous waste stream

for the purposes of reuse or recycling in the manufacture of products that may otherwise be produced using raw or virgin materials.

1.3.46 Nonresident Bidder . A Bidder whose principal place of business is not in Texas. This includes a Bidder

whose ultimate parent company or majority owner does not have its principal place of business in Texas.

1.3.47 Nonresponsive Proposal . A proposal that does not meet the criteria for acceptance contained in the

proposal form.

1.3.48 Notification . Either written or oral instruction to the Contractor. Voice mail is oral notification.

1.3.49 Plans . The drawings approved by the Engineer, including true reproductions of the drawings that may show

the location, character, dimensions, and details of the work and are a part of the Contract. Documents may include drawings or digital files.

1.3.50 Power of Attorney for Bid Bonds . An instrument under corporate seal appointing an attorney in fact to act

on behalf of a Surety in signing bonds.

1.3.51 Prequalification . The process for determining a Contractor’s eligibility to bid work.

1.3.52 Prequalification Statement . The forms on which required information is furnished concerning the

Contractor’s ability to per form and finance the work.

1.3.53 Producer Price Index (PPI) . As defined by the U .S. Bureau of Labor Statistics, program measures the

average change over time in the selling prices received by domestic producers for their output. The prices included in the PPI ar e from the first commercial transaction for many products and some services.

1.3.54 Proposal . The offer from the Bidder submitted on the prescribed form, including addenda issued, giving unit

bid prices for performing the work described in the plans and specific ations.

1.3.55 Proposal Form . The form printed and sent to the Bidder by the Department or printed by the Bidder from the

Department’s bidding system.

1.3.56 Proposal Guaranty. The security furnished by the Bidder as a guarantee that the Bidder will enter into a

Contrac t if awarded the work.

1.3.57 Quality Assurance (QA) . Sampling, testing, inspection, and other activities conducted by the Engineer to

determine payment and make acceptance decisions.

1.3.58 Quality Control (QC) . Sampling, testing, and other process control activities c onducted by the Contractor to

monitor production and placement operations.

1.3.59 Referee Tests. Tests requested to resolve differences between Contractor and Engineer test results. The

referee laboratory is the Materials and Tests Division. 78 1.3.60. Regular Item . A bid i tem contained in a proposal.

1.3.61 Responsive Bid . A proposal that meets all requirements of the proposal form for acceptance.

1.3.62 Roadside . The areas between the outside edges of the shoulders and the right of way boundaries.

1.3.63 Special Provisions. Additions or revisions to these standard specifications or special specifications.

1.3.64 Special Specifications. Supplemental specifications applicable t o the Contract not covered by these

standard specifications.

1.3.65 Specifications. Directives or requirements issued or made pertaining to the method and manner of

performing the work or to quantities and qualities of materials to be furnished under the Contract . References to DMSs, ASTM or AASHTO specifications, or Department bulletins and manuals, imply the latest standard or tentative standard in effect on the date of the proposal. The Engineer will consider incorporation of subsequent changes to these documents in accordance with Article 10.4, “Scope of Work.”

1.3.66 State . The State of Texas.

1.3.67 State Holiday. A holiday authorized by the State Legislature excluding optional State holidays and not listed

in Section 10.1.3.44., “National Holidays.” A list of State holidays can be found on the Department’s website.

1.3.68 Subsidiary . Materials, labor, or other elements that because of their nature or quantity have not been

identified as a separate item and are included within the items on which they necessarily depend.

1.3.69 Supplier’s Agent . The representative of the Contractor who is available at all times and able to receive

instructions from the Engineer or authorized Department representatives and to act for the Contractor.

1.3.70 Suspension. Action taken by the Department or federal government pursuant to regulation that prohibits a person or company from entering into a Contract, or from participating as a supplier of materials or

equipment used in a highway improvement Contract as defined in Transportation Code, Chapter 223, Subchapter A.

1.3.71 Traffic Materials Contract . A type of Contract for the purchase of traffic control and safety devices.

1.3.72 Verification Tests. Tests used to verify accuracy of QC and QA and mixture design testing.

1.3.73 Wholly Owned Subsidiary . A legal entity owned ent irely by the Contractor.

1.3.74 Work . The furnishing of all approved materials necessary for the successful completion of the Contract.

1.3.75 Work Authorization. A letter issued to the Contractor by the Department to notify when calendar day

charges are beginning on the Contract. This letter of notification could be tied with the issuance of the first work order.

1.3.76 Work Order . Written notice to the Contractor to provide a specified quantity of materials in accordance with

the Contract. The work order may contain other specific instructions for the Contractor. A work order is part of the Contract.

1.3.77 Work Order Time . Time (days) specified in the Contract for the completion of all deliveries specified in a

work order. The time begins with the date of the work order.

1.3.78 Written No tice. Written notice is considered to have been duly given if delivered in person to the individual

or member to whom it is intended or if sent by regular, registered, or certified mail and delivered to the last known business address; sent by facsimile to the last known phone number; or sent by email to the last 79 known address. The date of the letter will serve as the beginning day of notice. Unclaimed mail or failure to provide current contact information will not be considered a failure to provide written notice.

Article 2 — Instructions To Bidders

2.1 Introduction. Instructions to the Contractor in these specifications are generally written in active voice,

imperative mood. The subject of imperative sentences is understood to be “the Contractor.” The Department’s responsibilities are generally written in passive voice, indicative mood. Phrases such as “as approved,” “unless otherwise approved,” “upon approval,” “as directed,” “as verified,” “as ordered,” and “as determined” refer to actions of the Engineer unless otherwise stated, and it is understood that the directions, orders, or instructions to which they relate are within the limitations of and authorized by the Contract.

2.2 Eligibility of Bidders. Obtain a prequalification form from the Department’s website. A Bidder may choose

to be prequalified by submitting either a Confidential Questionnaire (CQ), a Bidder’s Questionnaire (BQ), or a Materials Supplier’s Questionnaire (MQ). Submit the appropriate questionnaire at least 10 calendar days before the last day of the bid opening for the District or statewide letting. Comply with all technical prequalification requirements in the proposal. Once prequalified, a Bidders eligibility is valid for a period of one year. Bidding capacity and available bidding capacity does not apply to MMC and TMC contracts. Reference 43 TAC §§ 9.11, “Definitions,” and 9.12, “Qualification of Bidders.”

2.2.1 Confidential Questionnaire (CQ) . Submit a CQ and an audited financial statement for approval. Once

prequalified, a Bidder’s eligibility is valid for a period of 1 yr. from the balance sheet statement date.

2.2.2 Bidder’s Questionnaire (BQ) . Bidders prequalified with a BQ are only eligible to bid on projects identified as

being waived from the requirements of Section 10.2.2.1., “Confidential Questionnaire (C Q).” Materials Contract proposals are designated with a “MW” on the Proposal Request Form. Submit a BQ for approval. Once prequalified, a Bidder’s eligibility is valid for a period of 1 yr. from the date the BQ was received by the Department.

2.2.3 Materials Sup plier’s Questionnaire (MQ) . Bidders that submit only an MQ are eligible to bid only on a

materials contract. Moreover, bidding capacity does not apply for a materials contract. An uncompleted materials contract does not affect the bidding capacity or available bidding capacity of a Bidder who submits a CQ or a BQ.

2.3 Issuing Proposal Forms . The Department will issue a proposal form to a prequalified Bidder as prescribed

in Section 10.2.2. “Eligibility of Bidders.” Request a proposal form electronically from the Department’s website. A proposal form printed directly from the Department’s website is for informational purposes only and will not be accepted as an official proposal form. In the case of a joint venture (JV), all JV participants must be prequalified. The Department will not issue a proposal form if one or more of the following apply:  the Bidder is suspended or debarred by the Commission or the Department,  the Bidder has not fulfilled the requirements for prequalification,  the Bidder is prohibited from rebidding a specific proposal form due to a bid error on the original proposal form,  the Bidder failed to enter into a Contract on the original award,  the Bidder was defaulted or terminated on the original Contract, unless the Department terminated in the best interest of the State or the public,  the Bidder or a subsidiary or affiliate of the Bidder has received compensation from the Department to participate in the preparation of the plans or specifications on which the bid or Contract is based,  the Bidder is ineligible to bid on any proposed Contract in accordance with Article 10.7. 8., “Responsibility for Damage Claims,” 80  the Bidder is prohibited from participating in the C ontract because of a decision of the Deputy Executive Director under 43 TAC § 9.24 (relating to Performance Review Committee and Actions),  the Bidder failed to attend a mandatory pre- bid conference, or  the Bidder or affiliate of the Bidder that was originally determined as the apparent low Bidder on a project but was deemed nonresponsive for failure to register or participate in the Department of Homeland Security (DHS) E -Verify system as specified in Section 10.2.14., “Department of Homeland Security (DHS) E -Verify System,” is prohibited from rebidding that specific project. Reference 43 TAC § 9.12, “Qualification of Bidders,” and § 9.13, “Notice of Letting and Issuance of Bid Forms.”

2.4 Interpreting Estimated Quantities. The quantities listed o n the proposal form are approximate and will be

used for the comparison of bids. Payments will be made for the work performed in accordance with the Contract.

2.5 Examining Documents and Work Locations . Examine the proposal form, plans, specifications, and

specified work locations before submitting a bid for the work. Submitting a bid will be considered evidence that the Bidder has performed this examination. Oral explanations, instructions, or consideration for Contractor -proposed changes in the proposal form given during the bidding process are not binding. Only requirements included in the proposal form, associated specifications, plans, and Department -issued addenda are binding. Request explanations of documents in adequate time to allow the Department to reply before the bid opening. Immediately notify the Department of any error, omission, or ambiguity discovered in any part of the proposal form and Contract documents. The Department will issue addenda when appropriate.

2.6 Preparing the Bid. Prepare the bid on the proposal form furnished by the Department. Informational

proposal forms printed from the Department’s website will not be accepted. Specify a unit price in dollars and cents for each regular item. The Department will not accept an incomplete bid. A bid that has one or more of the deficiencies listed below is considered incomplete:  certifications were not acknowledged,  a regular item is left blank,  the proposal form submitted had the incorrect number of items,  the Bidder did not acknowledge all addenda, or  additionally, for printed bids: • the blank spaces for each item as required o n the bid form are not filled in by writing in words in ink, • the bid was not signed in ink in the complete and correct name of the bidder making the bid, and signed by the person or persons authorized to bind the bidder, or • unit prices were not stated in dollars and cents for each bid item listed o n the bid form. Reference 43 TAC § 9.14, “Submittal of Bid.”

2.7 Nonresponsive Bid . The Department will not accept a nonresponsive bid. A bid that has one or more of the

deficiencies listed below is considered nonresponsive:  the bid was not in the hands of the Letting Official at the time and location specified in the advertisement, 81  a proposal form was submitted for the same project by a Bidder or Bidders and one or more of its partners or af filiates, unless the Executive Director has granted an affiliation exception under 43 TAC § 9.12,  the Bidder was not authorized to receive a proposal form under Section 10.2.3., “Issuing Proposal Forms,”  the Bidder failed to acknowledge receipt of all addenda issued,  the proposal form was signed by a person who was not authorized to bind the Bidder or Bidders,  the proposal guaranty did not comply with the requirements contained in this Item,  the bid was in a form other than the official proposal form issued by the Department,  the Bidder modified the bid in a manner that altered the conditions or requirements for work as stated in the proposal form,  a typed proposal form does not contain the information in the format shown on the “Example of Bid Prices Submit ted by Computer Printout” o n the proposal form,  the Bidder did not meet the requirements of the technical qualification, or  the Bidder failed to participate in the Department of Homeland Security (DHS) E -Verify system as specified in Section 10.2.14., “Department of Homeland Security (DHS) E -Verify System.” Reference 43 TAC § 9.15, “Acceptance, Rejection, and Reading of Bids.”

2.8 Electronic Bid . The Bidder is responsible for taking the appropriate measures to submit a bid. These

measures include, but are not l imited to acquiring hardware, software, and Internet connectivity needed for submitting a bid via the Department’s bidding system.

2.8.1 Proposal Form . Use the electronic proposal form in the Department’s bidding system. Acknowledge all

addenda listed in the Department’s bidding system. The electronic proposal form does not contain the special provisions, special specifications, general notes, and other Contract documents. These documents are included by reference.

2.8.2 Proposal Guaranty. Provide a proposal guaranty i n the amount indicated on the proposal form. Use an

electronic bid bond. Guaranty checks or printed bid bonds will not be accepted. For a JV , the bond must be in the name of all JV participants. Enter the bond authorization code into the Department’s biddi ng system. It is the Bidder’s responsibility to ensure the electronic bid bond is issued in the name or Department vendor identification numbers of the Bidder or Bidders.

2.8.3 Submittal of Bid . Submit the bid to the vault using the Department’s bidding system.

2.8.4 Revising the Proposal Form . Make desired changes in the Department’s bidding system up until the time

and date set for the opening of bids. The last bid submitted to the vault will be used for tabulation purposes.

2.8.5 Withdrawing a Bid. Submit an electronic or written request to withdraw a bid before the time and date set

for the opening. The Department will not accept oral requests. An electronic request must be made using the Department’s bidding system. If a bidder is unable to withdraw an electronic bid usi ng the Department’s bidding system, a written request may be submitted. A written request must be signed and submitted to the Letting Official conducting the letting with proof of identification. The request must be made by a person authorized to bind the Bidder or Bidders. In the case of JV , the Department will accept a request from any person authorized to bind a party to the JV . The Department may require written delegation of authority to withdraw a bid when the individual sent to withdraw the bid is not authorized to bind the Bidder or Bidders. 82 2.9. Printed Bid .

2.9.1 Proposal Form . Mark all entries in ink. As an alternative to hand writing the unit prices o n the proposal form,

submit a typed proposal form. A typed proposal form must contain the information in the format shown on the “Example of Bid Prices Submitted by Computer Printout” o n the proposal form. Acknowledge all addenda by checking the appropriat e box on the addendum acknowledgement page. Provide the complete and correct name of the Bidder submitting the bid. A person authorized to bind the Bidder must sign the proposal form. In the case of a JV , provide the complete and correct name of all Bidder s submitting the bid. In the case of a JV , the person signing the proposal form must be authorized to bind all JV participants.

2.9.2 Proposal Guaranty. Provide a proposal guaranty in the amount indicated on the proposal form. Use either a

guaranty check or a printed bid bond. An electronic bid bond may be used as the guaranty. Ensure the electronic bid bond meets the requirements of Section 10.2.8.2., “Proposal Guaranty,” and submit the electronic bid bond with the printed bid. 2.9.2.1. Guaranty Check. When used, make the check payable to the Texas Transportation Commission or the Texas Department of Transportation. The check must be a cashier’s check, money order, or teller’s check drawn by or on a state or national bank, or a state or federally chartered credit union (collectively referred to as “bank”). The check must be dated on or before the date of the bid opening. Postdated checks will not be accepted. The type of check or money order must be indicated on the face of the instrument, except in the case of a teller’ s check, and the instrument must be no more than 90 days old. A check must be made payable at or through the institution issuing the instrument , be drawn by a bank and on a bank , or be payable at or through a bank. The Department will not accept personal c hecks, certified checks, or other types of money orders. 2.9.2.2. Bid Bond. When a bond is used, use the bid bond form provided by the Department. Submit the bid bond in the amount specified with the powers of attorney dated and attached. The bond must be dated on or before the date of the bid opening, bear the impressed seal of the Surety, and be signed by the Bidder or Bidders and an authorized individual of the Surety. As an alternative for JV Bidders, each Bidder may submit a separate bid bond completed as outli ned in this Section. Bid bonds will only be accepted from Sureties authorized to execute a bond under and in accordance with state law.

2.9.3 Submittal of Bid . Place the completed proposal form and the proposal guaranty in a sealed envelope

marked to indicate the contents. When submitting by mail or delivery service, place the envelope in another sealed envelope and address as indicated in the official advertisement. It is the Bidder’s responsibility to ensure that the sealed bid arrives at the location described on or before the time and date set for the bid opening. To be accepted, the bid must be in the hands of the Letting Official by that time of opening regardless of the method chosen for delivery.

2.9.4 Revising the Proposal Form . Make desired changes to the proposal form in ink, initial each change made,

and submit the proposal to the Letting Official. Correction fluid or tape will be considered a change to the bid and requires the initials of the Bidder. The Department will not revise a bid on behalf of a Bidder .

2.9.5 Withdrawing a Bid. Submit to the Letting Official conducting the letting a written request to withdraw a bid

before the time and date set for the opening. The Department will not accept oral requests. A written request must be signed and submitted to the Letting Official conducting the letting, with proof of identification. The request must be made by a person authorized to bind the Bidder or Bidders. In the case of a JV , the Department will accept a request from any person authorized to bind a party to t he JV. The Department may require written delegation of authority to withdraw a bid when the individual sent to withdraw the bid is not authorized to bind the Bidder or Bidders.

2.10 Opening and Reading of Bids . At the time, date, and location specified in the official advertisement, the

Letting Official will publicly open and read bids. 83 2.11. Tabulating Bids .

2.11.1 Official Total Bid Amount . The Department will sum the products of the quantities and the unit prices bid o n

the proposal form to determine the official total bid amount, except as provided in Section 10.2.11.5., “Consideration of Unit Prices.” The official total bid amount is the basis for determining the apparent low Bidder. The total bid amounts will be compared and the results made public.

2.11.2 Consideration of B id Format . When a Bidder submits both an electronic bid and a printed bid that are

responsive, the unit bid prices in the electronic bid will be used to determine the total bid amount. If the electronic bid is incomplete or nonresponsive, the printed bid w ill be used in the tabulation of the total bid amount. If a Bidder submits two or more printed bids, all responsive bids will be tabulated. The bid with the lowest tabulation will be used to determine the total bid amount.

2.11.3 Rounding of Unit Prices . The Department will round off all unit bids involving fractional parts of a cent to the

nearest one- tenth cent ($0.001) in determining the amount of the bid as well as computing the amount due for payment of each item under the Contract. For rounding purposes, ent ries that contain five- hundredths of a cent ($0.0005) or more will be rounded up to the next highest tenth of a cent, while entries that contain less than five- hundredths of a cent will be rounded down to the next lowest tenth of a cent and in accordance w ith Section 10.2.11.5, “Consideration of Unit Prices.” Bids less than one- tenth of a cent ($0.001 ) will be rounded to one- tenth of a cent ($0.001). When credit items are included (negative unit prices), rounding is performed on the absolute value.

2.11.4 Interpre tation of Unit Prices . The Department will make a documented determination of the unit bid price if

a unit bid price is illegible. The Department’s determination will be final.

2.11.5 Consideration of Unit Prices . Unit bid price entries such as no dollars and no cents, zero dollars and zero

cents, or numerical entries of less than $0.001 will be tabulated as one- tenth of a cent ($0 .001). The Department will consider proposals in which unit bid prices have been left blank incomplete and nonresponsive. 2.11.5.1. Home State Bi dding Preference . For the purpose of determining the apparent low Bidder on proposed Contracts, the Department will select the option that results in the greatest bidding preference to the resident Bidder. 2.11.5.1.1. Reverse Application of Non -Resident Bidder’s Home State Bidding Preference. The total bid amount will be based upon the reverse application of the non- resident Bidder’s home state bidding preference, if any. This will also apply to another state’s preference for a Bidder that offers materials grown, produced, processed, or manufactured in that state. Any reverse application of the home state bidding preference w ill be the greater of the following:  the amount by which a resident Bidder would be required to underbid the non- resident Bidder to obtain a compar able contract in the state in which the non- resident’s principle place of business is located; or  the amount by which a resident Bidder would be required to underbid the non- resident Bidder to obtain a comparable contract in the state in which a majority of the manufacturing relating to the Contract will be performed. 2.11.5.1.2. Texas Home State Bidding Preference. A Bidder will be considered the apparent low Bidder if the Bidder’s home office is located in this state and their bid does not exceed an amount equal to 105% of the apparent low bid received from a Bidder whose home office is not located in this state. This will not apply to a Bidder from a bordering state whose state does not give a preference to a Bidder in a manner similar to this Section. 84 2.12. Consideration of Bid Errors . The Department will consider a claim of a bid error by the apparent low Bidder if the following requirements have been met:  a written notification is submitted to the Department within 5 business days after the date the bid is opened and  the submittal identifies the items of work involved and includes bidding documentation. The Department may request clarification of submitted documentation. The Department will evaluate the claim of a bid error by the apparent low Bidder by considering the following:  the bid error relates to a material item of work,  the bid error amount is a significant portion of the total bid,  the bid error occurred despite the exercise of ordinary care, and  the delay of the proposed work will not impact cost and safety to the public. Acceptance of the bid error claim by the Department will result in the rejecti on of all bids. The erring Contractor will not be allowed to bid the project when it is re- let. Rejection of bids due to the Contractor’s bid error may result in the application of remedial actions by the Department. Reference 43 TAC § 9.24, “Performance R eview Committee and Actions.”

2.13 Tie Bids . If the official total bid amount for two or more Bidders is equal and those bids are the lowest

submitted, each tie Bidder will be given an opportunity to withdraw their bid. If two or more tie Bidders do not withdra w their bids, the low Bidder will be determined by a coin toss or a series of coin tosses when there are more than two Bidders. If all tie Bidders request to withdraw their bids, no withdrawals will be allowed and the low Bidder will be determined by a coi n toss or a series of coin tosses when there are more than two Bidders. The Letting Official will preside over the proceedings.

2.14 Department of Homeland Security (DHS) E -Verify System . The Department will not award a Contract to a

Contractor that is not regi stered in the DHS E -Verify system. Remain active in E -Verify throughout the life of the Contract. If the apparent low Bidder does not appear i n the DHS E -Verify system before award, the Contractor must submit documentation showing that they are compliant within 5 calendar days after bid opening. A Contractor that fails to comply or respond within the deadline will be declared nonresponsive. The Bidder forfeiting the proposal guaranty will not be considered in future proposals for the same work unless there has been a substantial change in the scope of the work. The Department may recommend that the Commission:  reject all bids, or  award the Contract to the new apparent low Bidder, if the Department is able to verify the Bidder’s participation in the DHS E -Verify system. If the Department is unable to verify the new apparent low Bidder’s participation in the DHS E -Verify system:  the new apparent low Bidder will not be deemed nonresponsive,  the new apparent low Bidder’s guaranty will not be forfeited,  the Department will reject all bids,  the new apparent low Bidder will remain eligible to receive future proposals for the same project, and  the proposal guaranty of the original low bidder will become the property of the State, not as a penalty, but as liquidated damages. 85 3. AWARD AND EXECUTION OF CONTRACT

3.1 Award of Contract . The Commission or original award authority will award, reject, or defer the Contract

within 30 days after the opening of the proposal. The Department reserves the right to reject any or all propos als and to waive technicalities in the best interest of the State.

3.1.1 Award . The Commission or original award authority will award the Contract to the low Bidder as determined

in accordance with Section 10.2.11., “Tabulating Bids.” The Commission may award a Contract to the second lowest Bidder when the following requirements have been met:  the Contract is for maintenance work with an Engineer’s estimate less than $300,000,  the low Bidder withdraws their bid or fails to enter into Contract,  the second lowest Bidder agrees to perform the work at the unit bid prices of the low Bidder,  the Executive Director recommends in writing the award of the Contract to the second lowest Bidder, and  the Commission agrees with the Executive Director’s recommendation for award to the second lowest Bidder.

3.1.2 Rejection . The Commission or original award authority will reject the Contract if:

 collusion may have existed among the Bidders. Collusion participants will not be allowed to bid future proposals for the same Contract,  the low bid is mathematically and materially unbalanced. The Bidder will not be allowed to bid future proposals for the same Contract,  the lowest bid is higher than the Department’s estimate and re- advertising for bids may result in a lower bid,  the low bid contains a bid error that satisfies the requirements and criteria in Section 10.2.12., “Consideration of Bid Errors,” or  rejection of the Contract is in the best interest of the State.

3.1.3 Deferral . The Commission may defer the award or rejection of the Contract when deferral is in the best

interest of the State.

3.2 Rescinding of Award. The Commission or original award authority reserves the right to cancel the award of

any Contract before Contract execution with no compensation due when the cancellation is in the best interest of the State. The Department will return the proposal guaranty to the Contractor.

3.3 Execution of Contract . Provide the following within 15 days after written notification of award of the

Contract.

3.3.1 Contract . Execute the Contract as prescribed by the Department.

3.3.2 Insurance. Refer to Section 10.3.7, “Beginning of Work.”

Once work begins, insurances must cover the work for the duration of the Contract and must remain in effect until final acceptance. Provide project -specific insurance, not listed in Table 1, until acceptance of the work covered by the project -specific insurance or as approved by the Engineer. Failure to obtain and maintain insurance for the contracted work may result in suspension of work or default of the Contract. If the insuranc e expires and coverage lapses for any reason, stop all work until the Department receives an acceptable certificate of insurance. Provide the Department with a certificate of insurance verifying the types and amounts of coverage shown in Table 1. The certificate of insurance must be in a form approved by the Texas Department of Insurance. Certificates of insurance for commercial general liability, auto liability, and workers’ compensation must 86 include the Contractor’s prequalified name in the “Insured” fiel d. Any certificate of insurance provided must be available for public inspection. Table 1 Insurance Requirements Type of Insurance Amount of Coverage Commercial general liability insurance Not less than: $600,000 each occurrence Business automobile policy Not less than: $600,000 combined single limit Workers’ compensation Not less than: Statutory By signing the Contract, the Contractor certifies compliance with all applicable laws, rules, and regulations pertaining to workers’ compensat ion insurance. Pay all deductibles stated in the policy. The workers’ compensation policy must include a waiver of subrogation endorsement in favor of the Department. The work performed under this Section will not be measured or paid for directly but will be subsidiary to pertinent Items.

3.3.3 Business Ownership Information. Submit the names and Social Security numbers of all individuals owning

25% or more of the firm, or firms in the case of a joint venture, on the Department’s form.

3.4 Failure to Enter Contract . If the Contractor fails to comply with all the requirements in Section 10.3.3.,

“Execution of Contract,” the proposal guaranty will become the property of the State, not as a penalty, but as liquidated damages. The Contractor forfeiting the proposal guaranty will not be considered in future proposals for the same work unless there has been a substantial change in design of the work and may result in the application of remedial actions by the Department. Reference 43 TAC § 9.24, “Performance Review Committee and Actions.”

3.5 Approval and Execution of Contract . The Contract will be approved and signed under authority of the

Commission.

3.6 Return of Proposal Guaranty . The proposal guaranty check of the low Bidder will be retained until after the

Contract has been rejected or awarded and executed. Bid bonds will not be returned.

3.7 Beginning of Work . Do not begin work until authorized in writing by the Engineer. Do not begin work until a

certificate of insurance showing coverages in conform ance with the Contract requirements is provided and accepted. Verify all quantities of materials shown on the plans before ordering. For Contracts with callout work and work orders, the purchase of materials before a work order is issued or without prior written approval of the Engineer is at the Contractor’s risk, and the Department is not obligated for the cost of the materials or work to acquire the materials.

3.8 Assignment of Contract . Do not assign, sell, transfer, or otherwise dispose of the Contract or any portion of

the rights, title, or interest (including claims) without the approval of the Commission or original award authority. The Department must deem any proposed assignment justi fied and legally acceptable before the assignment can take place. 87 4. SCOPE OF WORK

4.1 Contract Intent . The intent of the Contract is to describe the completed work to be performed. Furnish

materials, supplies, and other incidentals necessary for the proper delivery of the materials in accordance with Contract documents.

4.2 Coordination Call . Before starting work, schedule and participate in a coordination call or virtual meeting

with the Engineer or designated representative to establish points of contact for communication, an issue escalation ladder, delivery location details, and other Contract requirements. Work with the Engineer to resolve or escalate all issues.

4.2.1 Issue Resolution Process. An issue is any aspect of the Contract where parties of the Contract do not

agree. The individuals identified at the lowest level of the issue escalation ladder will initiate the issue resolution process by escalating any issue that remains unresolved within the timeframe outlined in the issue escalation ladder. Work with the Engineer or designated representative to resolve all issues during the course of the Contract. Refer to Section 10.4.5., “Dispute or Claims Procedure,” for all unresolved issues.

4.3 Changes in the Work . The Engineer reserves the right to make changes in the Contract including addition,

reduction, or elimination of quantities and alterations needed to complete the Contract. Perform the work as altered. If no unit price exists, this will be considered extra work and the Contract will be amended by a change order. The Department does not guarantee a specific volume to be purchased. No minimum compensation to the Contractor is guaranteed. Quantities indicated for each Item in the Contract are estimates only and are based on the previous usage. These estimates should not be construed as a minimum or maximum quantity to be ordered. If a delivery location changes by more than 5 mi ., either party can request an adjustment to the Contract for changes in freight trucking cost.

4.3.1 Contract Extensions. When mutually agreed in writing, the Engineer may extend the Contract if the

Contractor has satisfactorily fulfilled the terms and conditions of the Contract. The extension may be for a period not to exceed the original Contract time and may include additional quantities up to the original bid quantities plus any quantities added by change order. Unit prices may be adjusted with the extension to reflect the current Federal Producer Price Index (PPI) published by the Bureau of Labor Statistics (BLS), Region VI, Washington, DC 20212. The extension will meet the terms and conditions of the original Contract. When mutually agreed, execute the extension prior to the end of the term of the existing or previously extended Contract. Prosecute the original Contract and the extension consecutively. The extension will be allowed once for any Contract greater than 6 mo. in duration not to exceed 12 mo. and twice for any Contract duration 6 mo. or less.

4.4 Requests for Additional Compensation and Damages . Notify the Engineer in writing of any intent to

request additional compensation once there is knowledge of the basis for the request. An assessment of damages is not required to be part of this notice but is desirable. The intent of the written notice requirement is to provide the Engineer an opportunity to evaluate the request and to keep an accurate account of the actual costs that may arise. Minimize impacts and costs . If written notice is not given, the Contractor waives the right to additional compensation unless the circumstances could have reasonably prevented the Contractor from knowing the cost impact before performing the work. Notice of the request and the documentation of the costs will not be construed as proof or substantiation of the validity of the request. Submit the request in enough detail to enable the Engineer to determine the basis for entitlement, adjustment in the number of working days specified in the Contract, and compensation. Compensable damages occur when impacts that are the responsibility of the Department result in additional costs to the Contractor that could not have been reasonably anticipated at the time of letting. 88 4.5. Dispute or Claims Procedure. The dispute resolution policy promotes a cooperative attitude between the Engineer and Contractor. Emphasis is placed on resolving issues while they are still current, at the area office or the district office, and in an informal manner. Open sharing of information is encouraged by all parties involved so the information provided completely and accurately reflects the issues and facts. If information is not shared, decisions may be limited to relying on the documentation that is available for review. It is the Department’s goal to have a dispute settled in the District before elevating it to the Contract Claim Committee (CCC) as a claim. If a dispute cannot be resolved, initiate the Contract claim procedure by submitting a claim to the District Engineer, the Director of the Construction Division, or the CCC. The Department’s Contract claim procedure has been established in accordance with 43 TAC § 9.2, “Contract Claim Procedure.” Detailed instructions for submitting a claim and its components can be found on the Department’s website. The Contractor will file a Contract claim request and a detailed report that provides the basis for the claim. The detailed report will include relevant facts of the claim, cost or other data supporting the claim, a description of any additional compensation requested, and documents supporting the claim. The claim must include the following certification: “I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the Contractor believes the Department is liable; and that I am duly authorized to certify the claim on behalf of the Contractor.” If a claim has been submitted and the Contractor wishes to resume negotiations with the District, notify the CCC in writing of the intent to resume negotiations at the District level and request review of the claim be suspended by the CCC pending the outcome of the negotiations. File a claim after completion of the Contract or when required for orderly performance of the Contract. File the claim no later than 1 yr. after the date the Department issues notice to the Contractor that they are in default, the date the Department terminates the Contract, or the date of final acceptance of the Contract. It is the Contractor’s responsibility to submit requests in a timely manner.

Article 5 — Control of The Work

5.1 Authority of Engineer . The Engineer has the authority to observe, test, inspect, approve, and accept the

material s (either in writing or orally). The Engineer decides all questions about the quality and acceptability of materials, Contract interpretations, and acceptable Contract fulfillment. The Engineer has the authority to enforce and make effective these decisions.  Unless noted elsewhere in the Contract or by the Engineer, payment for Contractor work supports it is in accordance with the Contract requirements at that time. This payment does not eliminate the Contractor’s responsibilities for the work as defined in Se ction 10. 5.4., “Work Order Final Acceptance.”  The Engineer acts as a referee in all questions arising under the terms of the Contract.  The Engineer’s decisions are final and binding. The Engineer will pursue and document actions against the Contractor as warranted to address Contract performance issues. Contract remedies include, but are not limited to, the following:  requiring the Contractor to remove and replace defective material, or reducing payment for defective material,  assessing standard liquidated damages to recover the Department’s administrative costs, including additional project -specific liquidated damages when specified in the Contract in accordance with 43 TAC §9.22, 89  withholding estimates, and  declaring the Contractor to be in default of the Contract. The Engineer will consider and document any events outside the Contractor’s control that contributed to the failure to meet performance standards, including consideration of sufficient time. Follow the issue escalation ladder if there is disagreement regarding the application of Contract remedies.

5.2 Coordination of Plans, Specifications and Special Provisions . The specifications, accompanying plans,

special provisions, change orders, and supplemental agreements are intended to work together and be interpreted as a whole. Numerical dimensions govern over scaled dimensions. Special provisions govern over plans (including general notes), which govern over standard specifications and special specifications. Job- specific plan sheets govern over standard plan sheets when included. Notify the Engineer or designated representative promptly of any omissions, errors, or discrepancies upon discovery so necessary corrections and interpretations can be made. Failure to promptly notify the Engineer of discovered omissions, errors, or discrepancies will constitute a waiver of all Contract claims against the Department for misunderstandings or ambiguities that result from the errors, omissions, or discrepancies.

5.3 Inspection . Inspectors are authorized representatives of the Engineer. Inspectors are authorized to examine

all materials furnished, including preparation, fabrication, and material manufacture. Inspectors inform the Contractor of failures to meet Contract requirements. Inspectors may reject materials. Inspectors cannot alter, add, or waive Contract provisions or issue instructions contrary to the Contract. Inspection or lack of inspection will not relieve the Contractor from obligation to provide materials or perform the work in accordance with the Contract.

5.4 Work Order Final Acceptance. The Engineer or designated representative will determine if all material was

provided and met Contract specifications according to the work orders issued on the Contract. Work Order Final Acceptance relieves the Contractor from further Work Order responsibilities.

5.5 Contract Termination. The Contract terminates upon the latter of fulfillment of all Work Orders or on the

termination date or after passage of the calendar days shown in the proposal, unless extended by mutual agreement.

Article 6 — Control of Materials

6.1 Source Control . Use only materials that meet Contract requirements. Unless otherwise specified or

approved, provide new materials. Secure the Engineer’s approval of the proposed source of materials to be used before their delivery if requested.

6.1.1 Buy America. Comply with the latest provisions of Buy America in accordance with 23 CFR § 635.410. Use

steel or iron materials manufactured in the United States except when:  the cost of materials, including delivery, does not exceed 0.1% of the total Contract cost or $2,500, whichever is greater,  the Contract contains an alternate item for a foreign source steel or iron product and the Contract is awarded based on the alternate item, or  the materials are temporarily installed. Submit a notarized original FORM D-9- USA- 1 (Department Form 1818) with the pertinent attachments for verification of compliance. 90 Manufacturing is any process that modifies the chemical content, physical shape or size, or final finish of a product. Manufacturing begins with initial melting and mixing and continues through fabrication ( e.g., cutting, drilling, welding, and bending) and coating ( e.g., paint, galvanizing, and epoxy).

6.1.2 Buy Texas. Provide materials produced in Texas when the materials are available at a comparable price and

in a comparable period of time. Provide documentation of purchases or a description of good- faith efforts on request.

6.2 Acceptance or Rejection of Defective Material . When materials fail to meet the Contract requirements but

are still adequate to serve the purpose, the Engineer will decide the extent to which the materials will be accepted and remain. The Engineer will document the basis of acceptance and may adjust the C ontract price. When materials fail to meet C ontract requirements and are inadequate to serve the purpose, they will be considered defective. Correct, or remove and replace the materials at the Contractor’s expense as directed. Reimburse the Department for cost incurred if additional sampling and testing are required by a change of source. Materials not meeting Contract requirements will be rejected, unless the Engineer approves corrective actions. Upon rejection, immediately remove and replace rejected materials. The D epartment has the authority to remove or replace defective materials. Cost for the removal may be deducted from any money due or to become due to the Contractor.

6.3 Manufacturer Warranties. Transfer to the Department warranties and guarantees required by the Contract

or received as part of normal trade practice.

6.4 Sampling, Testing, and Inspection. Refer to the m aterial special specification for more information. The

material requirements and standard test methods in effect at the time the proposed Contract is advertised govern. Unless otherwise specified , the Department will perform testing at its expense. If requested, provide a complete written statement of the origin, composition, and manufacture of materials. Material that has been tested and approved at a supply source or staging area may be inspected or tested within 30 days upon delivery and rejected if it does not meet Contract requirements. Copies of test results are available upon request. Do not supply material that, after approval, becomes unfit for use.

6.5 Plant Inspection and Testing . The Engineer may but is not obligated to inspect materials at the acquisition

or manufacturing source. Material samples will be obtained and tested for compliance with quality requirements. Materials produced under Depart ment inspection are for Department use only unless released in writing by the Engineer. If inspection is at the plant, meet the following conditions unless otherwise specified:  cooperate fully and assist the Engineer during the inspection,  ensure the Engineer has full access to all parts of the plant used to manufacture or produce materials,  provide a facility at the plant for use by the Engineer as an office or laboratory, in accordance with Item 504, “Field Office and Laboratory,”  provide and maintain adequate safety measures and restroom facilities, and  furnish and calibrate scales, measuring devices, and other necessary equipment in accordance with Item 320, “Equipment for Asphalt Concrete Pavement.” The Engineer may provide inspection for periods other than daylight hours if:  continuous production of materials for Department use is necessary due to the production volume being handled at the plant, and  the lighting is adequate to allow satisfactory inspection.

6.6 Hazardous Materials. Comply with the requirem ents of Article 10.7.6., “Responsibility for Hazardous

Materials.” 91 Use materials that are free of hazardous materials. Notify the Engineer immediately if materials are suspected to contain hazardous materials. If materials delivered or provided by the Contractor are suspected to contain hazardous materials, have an approved commercial laboratory test the materials for the presence of hazardous materials as approved. Remove, remediate, and dispose of any of these materials found to contain hazardous materials. The work required to comply with this S ection will be at the Contractor’s expense if materials are found to contain hazardous materials. Work order day charges will not be suspended and extensions of work order day charges will not be granted for activities related to handling hazardous material introduced by the Contractor. If suspected materials are not found to contain hazardous materials, the Department will reimburse the Contractor for hazardous materials testing.

Article 7 — Legal Relations and Responsibilitie S

7.1 Ethics . Honor the Department’s ethics policy. The Department’s ethics policy has been established in

accordance with 43 TAC Chapter 10. A complete copy of the Department’s ethics policy can be found on the Department’s website. By entering into Contract, the Contractor certifies that the Contractor has read and understands the Department’s ethics policy. Failure to honor this policy may result in action by the Department, which includes but is not limited to verbal warning, removal of project personnel, termination of the Contract, and sanctions under the TAC .

7.2 Laws to be Observed . Comply with all federal, state, and local laws, ordinances, and regulations that affect

the performance of the work. The Contractor is not required to comply with city electrical ordinances not included in this Contract. Indemnify and save harmless the State and its representatives against any claim arising from violation by the Contractor of any law, ordinance, or regulation. This Contract is between the Department and the Contractor only. No person or entity may claim third- party beneficiary status under this Contract or any of its provisions, nor may any non- party sue for personal injuries or property damage under this Contract.

7.3 Permits, Licenses, and Taxes. Procure all permits and licenses; pay all charges, fees, and taxes; and give all notices necessary and incidental to the due and lawful prosecution of work, except for permits provided by the Department.

7.4 Patented Devices, Material, and Processes. Indemnify and save harmless the State from any claims for

infringement from the Contractor’s use of any patented design, device, material, process, trademark, or copyright selected by the Contractor and used in connection with the work. Indemnify and save harmless the State against any costs, expenses, or damages that it may be obliged to pay, by reason of this infringement, at any time during the prosecution or after the completion of the work .

7.5 Personal Liability of Public Officials . Department employees are agents and representatives of the State

and will incur no liability, personal or otherwise, in carrying out the provisions of the Contract or in exercising any power or authority granted under the Contract .

7.6 Responsibility for Hazardous Materials. Comply with the requirements of Article 10.6.6., “Hazardous

Materials.” Indemnify and save harmless the State and its agents and employees from all suits, actions, or claims and from all liability and damages for any injury or damage to any person or property arising from the generation or disposition of hazardous materials introduced by the Contractor on any work done by the Contractor on State- owned or controlled sites. Indemnify and save harmless the State and its representatives from any liability or responsibility arising out of the Contractor’s generation or disposition of any hazardous materials obtained, processed, stored, or shipped on sites not owned or controlled by the State. Reimburse the State for all payments, fees, or restitution the State is required to make as a result of the Contractor’s actions. 92 7.7. Protecting Adjacent Property . Protect adjacent property from damage. If any damage results from an act or omission on the part of or on behalf of the Contractor, take corrective action to restore the damaged property to a condition similar or equal to that existing before the damage was done.

7.8 Responsibility for Damage Claims. Indemnify and save harmless the State and its agents and employees

from all suits, actions, or claims and from all liability and damages for any injury or damage to any person or property due to the Contractor’s negligence in the performance of the work and from any claims arising or amounts recovered under any laws, including workers’ compensation and the Texas Tort Claims Act. Indemnify and save harmless the State and assume responsibility for all damages and injury to property of any character occurring during the prosecution of the work resulting from any act, omission, neglect, or misconduct on the Contractor’s part in the manner or method of executing the work; from failure to properly execute the work; or from defective work or material. If the Contractor asserts any claim or brings any type of legal action (including an original action, third- party action, or cross -claim) against any member of the Commission or individual employee of the Department for any cause of action or claim for alleged negligence arising from the Contract, the Contractor will be ineligible to bid on any proposed Contract with the Department during the pendency of the claim or legal action.

7.9 Hauling and Loads on Roadways and Structures . Comply with federal and state laws concerning legal

gross and axle weights.

7.10 Security Incidents.

7.10.1 Reporting of Security Incidents . Immediately notify the Department’s Cyber Security Operations Center

(CSOC) via the Report Cybersecurity Incident form on txdot.gov of any potential cybersecurity incident or breach involving Department data . A breach of system security is the unauthorized acquisition of computerized data that compromises the security, confidentiality, or integrity of sensitive personal information maintained by a person, including data that is encrypted if the person accessing the data has the key required to decrypt the data.

7.10.2 Liability for Costs Incurred . The Department reserves the right to hold the Contractor liable for all costs

incurred by the Department to resolve a security incident introduced by the Contractor or their suppliers.

Article 8 — Prosecution and Progress

8.1 Prosecution of Work . The Contract term begins at the issuance of a Work Order or 30 calendar days from

the execution date, whichever comes first. When work orders are issued, provide approved materials within the specified time. Restrictions on delivery times will be as shown on the plans.

8.2 Contract Term . Contract term will be the calendar days shown in the plans. Calendar days will be charged

Sunday –Saturday, including all holidays, regardless of weather conditions, material availability, or other conditions not under the control of the Contractor.

8.3 Work Orders . There will be a minimum of 7 working days allowed to deliver material as of the date of the

work order except for Expedited Work Orders (EWO). The actual number of days allowed for delivery of materials will be shown in the contract and work order; however, anything less than 7 working days in the contract or work order (except for an EWO) is not allowed.

8.3.1 Delivery of Materials. Materials will be delivered Monday –Friday, excluding national or state holidays, if

weather or other conditions permit the performance of the manufacturing and delivery of materials for a continuous period of 7 hours between 7 A.M. and 5 P.M.

8.4 Shipping. All shipping will be Freight on Board destination. Material prices with delivery by railcar or by truck

must include all shipping and handling fees, including but not limited to fees for any equipment necessary to offload material, unless specifically allowed for in the C ontract ’s general notes. 93 If a delay is foreseen, the Contractor will give written notice to the Department and must keep the Department advised at all times of order status. Default in promised delivery (without written acceptance of reasons) or failure to meet specifications authorizes the Department to purchase materials elsewhere and charge any increased costs for the materials, including the cost of re- soliciting, to the Contractor.

8.5 Issuance of Expedited Work Order . Expedited Work Order (EWO) will only contain bid items identified as

“expedited” in the Contract. An EWO completion time will be 48 hr. or less as shown in the Contract. The time begins when the Department contacts the Contractor with an EWO. A Contractor must accept the work order within 2 hr. from initial contact of the Department, or the Department will obtain the material through another source. The Department could seek damages for any costs exceeding the EWO cost.

8.5.1 Expedited Work Orders Delivery of Materials. EWO delivery days include Sunday –Saturday.

8.6 Late Delivery Damages. The time and date established for the completion of each work order is an essential element of the Contract. The Department will coordinate with the Contractor as shown in the

Contract for specific materials. In the case of conflict, reference Section 10.5.2, “Coordination of Plans, Specifications, and Special Provisions,” for governing language. If the Contractor fails to complete a work order within the number of working days specified, working days will continue to be charged. Failure to complete a work order within the number of working days specified, including any approved additional working days, will result in actual damages being charged as follows.  For roadway operations, any materials specified in the work order will be considered late unless the Department agrees to a new time and date offered by the C ontractor no less than 48 hr. prior to the work order’s time and date of delivery. Actual damages incurred will be deducted from the monthly payment and calculations will be provided upon request. If advanced notice is not approved and the Department obtains material through another source, the Department could seek damages for any costs exceeding the C ontract bid item(s).  For deliveries of stockpile materials, any materials specified in the work order will be considered late unless the Department agrees to a new time and date offered by the C ontractor no less than 24 hr. prior to the work order’s time and date of delivery. If advanced notice is not approved and the Department obtains material through another source, the Department could seek damages for any costs exceeding the Contract bid item(s) . The Department may suspend damages when weather impacts the delivery of the m aterials. Providing material that does not meet specification requirements does not constitute delivery, and applicable damages may continue to accrue until the Contractor delivers materials in full compliance with the specifications to the designated deli very location. The Department reserves the right to require replacement materials or a refund if materials not meeting specifications are discovered after the payment has been made.

8.7 Default of Contract .

8.7.1 Declaration of Default . The Engineer may declare the Contractor to be in default of the Contract if the

Contractor:  fails to complete a work order within the number of days specified;  is uncooperative, disruptive, or threatening;  fails to perform the work in accordance with the Contract requirements;  neglect s or refuses to remove and replace rejected materials or unacceptable work;  discontinues the prosecution of the work without the Engineer’s approval;  makes an unauthorized assignment;  fails to resume work that has been discontinued within a reasonable number of days after notice to do so; 94  fails to conduct the work in an acceptable manner; or  commits fraud or other unfixable conduct as determined by the Department. If any of these conditions occur, the Engineer will give notice in writing to the Contractor of the intent to declare the Contractor in default. If the Contractor does not proceed as directed within 10 days after the notice, the Department will provide written notice to the Contractor to declare the Contractor to be in default of the Contract. If the Contractor provides the Department written notice of voluntary default of the Contract, the Department may waive the 10 -day notice of intent to declare the Contractor in default and immediately provide written notice of default to the Contractor. Calendar day charges will continue until completion of the Contract. A default may result in the application of remedial action by the Department. Reference 43 TAC § 9.24, “Performance Review Committee and Actions.” The Department may suspend work in accordance with Section 10.8.1., “Prosecution of Work,” to investigate apparent fraud or other unfixable conduct before defaulting the Contractor. The Contractor may be subject to sanctions under the TAC. The Department will determine the most expeditious and efficient way to obtain the material and recover damages from the Contractor. The Department will hold all money earned but not disbursed by the date of default. All costs and charges incurred by the Department resulting from the default, including the cost of completing the work under the Contract, costs for other work deemed necessary, and any applicable liquidated damages will be deducted from money due the Contractor for completed work. In case the costs incurred by the Department are less than the amount that would have been payable under the Contract if the work had been completed by the Contractor, the Department will be entitled to retain the difference.

8.7.2 Wrongful Default . If it is determined after the Contractor is declared in default, that the Contractor w as not in

default, the rights and obligations of all parties will be the same as if termination had been issued for the convenience of the public as provided in Section 10.8.8., “Termination of Contract.”

8.8 Termination of Contract . The Department may terminate the Contract in whole or in part whenever:

 the Contractor is prevented from proceeding with the work as a direct result of an executive order of the President of the United States or the Governor of the State,  the Contractor is prevented from proceeding with the work due to a national emergency, or when the work to be performed under the Contract is stopped, directly or indirectly, because of the freezing or diversion of materials, equipment, or labor as the result of an order or a proclamation of the Pr esident of the United States,  the Contractor is prevented from proceeding with the work due to an order of any federal authority,  the Contractor is prevented from proceeding with the work by reason of a preliminary, special, or permanent restraining court order where the issuance of the restraining order is primarily caused by acts or omissions of persons or agencies other than the Contractor, or  the Department determines that termination of the Contract is in the best interest of the State or the public.

8.8.1 Procedures and Submittals. T he Department will provide written notice to the Contractor of termination

specifying the extent of the termination and the effective date. Upon notice, immediately proceed in accordance with the following:  stop work as specified in the notice,  place no further orders for materials,  complete performance of the work not terminated, and  settle all outstanding liabilities and termination settlement proposals resulting from the termination of the Contract. 95 8.8.2. Settlement Provisions. The Engineer will prepare a change order that reduces the affected quantities of work and adds acceptable costs for termination. No claim for loss of anticipated profits will be considered. The Department will pay reasonable and verifiable termination costs including:  all work completed at the unit bid price,  expenses necessary for the preparation of termination settlement proposals and support data, and  other expenses acceptable to the Department.

Article 9 — Measurement and Payment

9.1 Measurement of Quantities. The Engineer or designated representative will measure all completed work orders using United States standard measures, unless otherwise specified.

9.1.1 Haulin g on Routes Accessible to the Traveling Public . For payment purposes on haul routes accessible

to the traveling public:  If the gross vehicle weight is less than the maximum allowed by state law, including applicable yearly weight tolerance permit, the net weight of the load will be determined by deducting the tare weight of the vehicle from the gross weight.  If the gross vehicle weight is more than the maximum allowed by state law, including applicable yearly weight tolerance permit, the net weight of the load will be determined by deducting the tare weight of the vehicle from the maximum gross weight allowed.

9.1.2 Hauling on Routes Not Accessible to the Traveling Public . For payment purposes on haul routes that are

not accessible to the traveling public where advance permission is obtained in writing from the Engineer:  If the gross vehicle weight is less than the maximum allowed by the Engineer, including applicable yearly weight tolerance permit, the net weight of the load will be determined by deducting the tare weight of the vehicle from the gross weight.  If the gross vehicle weight is more than the maximum allowed by the Engineer, the net weight of the load will be determined by deducting the tare weight of the vehicle from the maximum gross weight allowed .

9.2 Scope of Payment . Payment of the Contract unit price is full compensation for providing all approved

materials under the Contract. Until final acceptance in accordance with Section 10.5. 4., “Work Order Final Acceptance,” the Contractor assumes liability for completing all work orders in accordance with material specifications.

9.3 Progress Payments. T he Engineer will prepare a monthly estimate of the quantities of approved materials

received. Payment of the monthly estimate is determined at the Contract item prices less any withholdings or deductions in accordance with the Contract. Progress payments may be withheld for failure to comply with the Contract. It is the Department’s intent to pay a Contractor for work through the last working day of the month; however, the use of early cut -off dates for monthly estimates is a project management practice to manage workload at the Area Office level. Approval for using early cut -off dates is at the District’s discretion. The earliest cut -off date for estimates is the 25 th of the month.

9.4 Payment for Extra Work. Payment for extra work directed, performed, and accepted will be made in

accordance with Section 10.4.3., “Changes in the Work.” Payment for extra work will be established by agreed unit prices. Agreed unit prices are unit prices that include markups and are comparable to recent bid prices for the same materials.

9.5 Demurrage . Demurrage is defined as a delay in delivery of material caused by the Department. Trucks may

be held for up to 2 hr. at the jobsite at no additional expense to the Department. The Contractor ’s driver will report to the Engineer or designated representative at the time of arrival at the final delivery location and 96 obtain a signature documenting the date and time. If not possible to obtain a signature, photographic documentation of the delivery location gate or marked roadway location with time and date stamp could be used. Written documentation of arrival will be used when calculating demurrage charges and included on an invoice submitted to the m anaging office. The demurrage charge will be invoiced in 15- min. increments, rounded down to the nearest whole increment. The Contractor has the option to provide documentation to charge a Demurrage Rate per truck per 15- min. increment. Documentation supporting the demurrage rate per truck will be required. Notify the Engineer or designated representative with any concerns or questions about demurrage charges.

9.6 Return, Cancellation, and Restocking Fee .

The Department may request that the Contractor accept return of merchandise that meets specifications and has already been delivered, or that the Contractor cancel an order prior to delivery. If the Contractor does not agree to the Department’s request, both parties must attempt to resolve the matter. The Contr actor may request a reasonable restocking charge, and the Department may pay a restocking charge (no more than 10% of the cost of the item , unless the Contractor can justify a higher cost for materials that are designed specifically for the work order) if determined that the charge is justifiable. However, the Department will not pay restocking or other fees for cancellations requested prior to shipment by the Contractor unless the material is a product specific design

9.7 Retainage. The Department will not wit hhold retainage on the Contractor.

9.8 Payment Provisions for Suppliers. These requirements apply to all tiers of suppliers. Incorporate the

provisions of this Section into all material purchase agreements. Pay suppliers for work performed within 10 days after receiving payment from the Department . Pay any retainage on a suppl ier’s work within 10 days after satisfactory completion of all the supplier’s work. For the purpose of this Section, satisfactory completion is accomplished when:  the supplier has fulfilled the Contract requirements of both the Department and the subcontr act for the work, including the submittal of all information required by the Contract and the Department, and  the work done by the supplier has been inspected, approved, and paid by the Department. Provide a certification of prompt payment to certify that all suppliers were paid from the previous month’s payments and retainage was released for those whose work is complete. Submit the certification in the manner prescribed by the Department each month and the month following the month when final acceptance occurred.

9.9 Work Order Final Payments. Each work order will be reconciled for final quantities and final payment as

they are completed. 100 Items Earthwork and Landscape This page intentionally left blank

Source: Texas Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges, 2024 Edition. Pages 84108 of 1,034.