General Requirements & Coatings (Items 100-199)

103Disposal of Wells

TX · 2024 Standard SpecificationsBook pages 111112View official source ↗

Article 1 — Description

Remove and dispose of contaminated and uncontaminated water, petroleum, or sulfur wells. Remove appurtenances, seal and plug wells, and restore the area. Prepare and file required documents with applicable agencies.

Article 2 — Construction

Follow legal responsibilities, construction requirements, and methods in accordance with Article 7.3., “Laws to be Observed,” and Article 7.4., “Permits, Licenses, and Taxes.” Remove all well casing and pump equipment installed in the well to 3 ft. below the finished subgrade or the existing grade, whichever is lower, and within construction limits. Pump equipment includes pump, piping, motor, housing, well structures, foundations, flumes, windmills, casing, and other projecting objects associated with the well. All removed items and appurtenances become the property of the Contractor, excluding existing contaminated soil and liquids, after necessary cleaning and disassembling. Dispose of these items in conformance with applicable laws and regulations. Test, remove, and dispose of hazardous materials in accordance with Article 6.10., “Hazardous Materials.” Plug remaining well casing . Submit a p lugging r eport to the appropriate agency when required by TCEQ, TDLR, or RRC. Furnish a copy to the Engineer. Backfill in accordance with Article 100.3., “Construction,” after removing all appurtenances and plugging the well casing.

2.1 Water Wells. Remove all removable casing from water wells, including dry wells and abandoned wells.

Pressure- grout the well with a mixture of hydraulic cement and water at a rate of not more than 7 gal. of water per sack of cement from the bottom of the well to the natural ground surface or 3 ft. below the finished subgrade, whichever is lower, in conformance with the requirements of TDLR. Obtain written approval from TDLR and the Engineer for alternative procedures. Plug any well located in a cut section up to the proposed earthwork elevation before excavating the cut. Backfill the remainder of the well above the proposed earthwork elevation with earth immediately after plugging a well in a cut section.

2.2 Petroleum and Sulfur Wells . Have a contractor from the RRC -approved list plug the well. Empty the

contents of petroleum or sulfur wells into approved containers in conformance with applicable regulations. Transport and dispose of the filled containers at an approved disposal facility or recycling center in conformance with applicable regulations. Approved plugging methods include protecting water -bearing strata with cement plugs when shown on the plans, or completely cementing the well.

Article 3 — Measurement

This Item will be measured by each properly plugged and disposed well. 102 4. PAYMENT The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price bid for “Disposal of Water Wells” or “Disposal of Petroleum or Sulfur Wells.” This price is full compensation for removing and disposing of appurtenances; plugging; furnishing records; furnishing and placing any material or items; site restoration; and equipment, labor, tools, and incidentals.