02216Test-Hole Utility

UT · 2027 Standard Specifications✓ Full text on BuildSpecRev. February 28, 2019Book pages 260–261 Save this section

Ask about Section 02216

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Part 1 — General

1.1 Section Includes

A.Procedure for test-hole operations to identify and locate utilities during construction activities.

1.2 Related Sections

A.Section 01721: Survey

1.3 References

A.CI/ASCE 38-02: Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data

1.4 DEFINITIONS Not Used

1.5 Submittals

A.Provide records to the Engineer within 5 working days of test-hole operations.

Part 2 — PRODUCTS Not Used

Part 3 — Execution

3.1 Preparation

A.Identify locations of possible conflicts including excavation, pipe culvert extensions, catch basins, and other construction elements to test-hole as requested by the Contractor and as determined by the Engineer.
B.Coordinate and cooperate with the utility companies to protect their facilities.
C.Request permission to test-hole from the Engineer at least 24 hours prior to excavation.

3.2 Exploration

A.Use vacuum excavation or other methods that protect the integrity of the utility.
B.Perform test-hole operations to provide Quality Level A per CI/ASCE 38- 02.

3.3 Records

A.Measure and record utility location according to CI/ASCE 38-02.
1.Measure and record horizontal and vertical location in project coordinate system per Standard Specification 01721.
2.Measure and record depth from grade, outside diameter, orientation, material composition, and configuration of non-encased, multi- conduit systems.

3.4 Backfill and Restoration

A.Backfill test-hole excavation according to utility owner’s specifications when outside of roadway prism.
1.Backfill according to the most restrictive of either the Department’s or the utility owner’s specifications if test-hole excavation is within the roadway prism.
2.Backfill within 24 hours or as otherwise determined.
B.Backfill test-hole excavation to the same depths and grades with equivalent or better materials of surrounding pavement or terrain.

Get an email when 02216 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2027 Edition. Pages 260–261 of 1,343. View official source ↗

Ask about this section

Scoped to Utah 2027 Standard Specifications, Section 02216 — Test-Hole Utility. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.