B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Site Construction & Earthwork (02000-02999)

02225Asphalt Surfacing Removal (Structures)

UT · 2027 Standard Specifications✓ Full text on BuildSpecRev. September 12, 2024Book pages 271–272 Save this section

Ask about Section 02225

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Part 1 — General

1.1 Section Includes

A.Removal of existing asphalt surfacing from bridge decks and approach slabs.

1.2 RELATED SECTIONS Not Used

1.3 REFERENCES Not Used

1.4 DEFINITIONS Not Used

1.5 SUBMITTALS Not Used

Part 2 — Products

2.1 Removal Equipment

A.Use equipment capable of removing the full depth of asphalt on the deck and the approach slabs without damaging the underlying concrete surfaces and bridge superstructure.

Part 3 — Execution

3.1 Asphalt Surfacing Removal

A.Verify total asphalt depth before removal at the locations shown.
1.Notify Engineer of any discrepancies between depth measured and the depth shown.
B.Remove asphalt to the top of the concrete surface as shown.
1.Rotomilling as part of the asphalt surfacing removal must meet the following requirements:
a.Verify total asphalt depth in at least three locations along the deck or as shown before rotomilling.
b.At least 1 inch of asphalt must remain above the top of the concrete surface after rotomilling and be removed using other methods.
c.Monitor during rotomilling to ensure concrete is not encountered.
C.Remove existing waterproofing membrane from the deck and concrete approach slabs.
D.Notify Engineer of damage to the deck or approach slab surface that occurs during the removal.
E.Asphalt surfacing material removed becomes the property of the Contractor, unless otherwise specified.

3.2 Protection

A.Prevent material and debris from falling into waterways, pedestrian areas, traffic areas, or onto railroad tracks.

Get an email when 02225 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2027 Edition. Pages 271–272 of 1,343. View official source ↗

Ask about this section

Scoped to Utah 2027 Standard Specifications, Section 02225 — Asphalt Surfacing Removal (Structures). Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.