B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Site Construction & Earthwork (02000-02999)

02376Rolled Erosion Control Products

UT · 2027 Standard Specifications✓ Full text on BuildSpecRev. February 19, 2026Book pages 323–326 Save this section

Ask about Section 02376

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Part 1 — General

1.1 Section Includes

A.Temporary and Permanent Rolled Erosion Control Products (RECP).

1.2 RELATED SECTIONS Not Used

1.3 References

A.ASTM D 4355: Deterioration of Geotextiles by Exposure to Light, Moisture and Heat in a Xenon Arc Type Apparatus
B.ASTM D 6459: Determination of Rolled Erosion Control Product (RECP) Performance in Protecting Hillslopes from Rainfall-Induced Erosion
C.ASTM D 6460: Determination of Rolled Erosion Control Product (RECP) Performance in Protecting Earthen Channels from Stormwater-Induced Erosion
D.ASTM D 6525: Measuring Nominal Thickness of Rolled Erosion Control Products
E.ASTM D 6566: Measuring Mass per Unit Area of Turf Reinforcement Mats
F.ASTM D 6818: Tensile Properties of Rolled Erosion Control Products

1.4 Definitions

A.Rolled Erosion Control Products (RECP) – Degradable or non-degradable prefabricated blankets formed with natural or synthetic materials installed to reduce soil erosion and aid in vegetative establishment.
1.Temporary RECP are composed of degradable natural fibers bound between two degradable natural or synthetic fiber netting to form a continuous matrix designed to provide erosion control protection up to 36 months.
2.Permanent RECP are manufactured with non-degradable synthetic fibers, filaments, nets, wire mesh or other elements into a permanent, three-dimensional matrix, and installed where established vegetation may be insufficient to protect against erosion within high flow channels, ditches or along very steep slopes.

1.5 Submittals

A.Authorized Products List (APL) Compliance Form for information.

1.6 Delivery, Storage, and Handling

A.Deliver products in original ultraviolet (UV) weather-resistant factory labeled packages showing the name of the manufacturer and product description.
1.Protect from damage due to climatic conditions or construction operations.

Part 2 — Products

2.1 Rolled Erosion Control Products (Recp)

A.Meet the requirements in Table 1 for Temporary RECP. Table 1 Requirements for Temporary Rolled Erosion Control Products Test Method Property (ASTM) RECP Type 2 RECP Type 3 RECP Type 4 Typical Functional Longevity 12 months 24 months 36 months Slope Gradient (H:V) ≤ 3:1 ≤ 2:1 ≤ 1:1 Tensile Strength D6818 ≥ 75 lbs/ft ≥ 100 lbs/ft ≥ 125 lbs/ft C Factor D6459 ≤ 0.20 ≤ 0.10 ≤ 0.05 Unvegetated Shear Stress D6460 ≥ 1.75 lbs/ft2 ≥ 2.0 lbs/ft2 ≥ 2.25 lbs/ft2
B.Meet the requirements in Table 2 for Permanent RECP. Table 2 Requirements for Permanent Rolled Erosion Control Products Test Method Property (ASTM) Turf Reinforcement Mat (TRM) Slope Gradient (H:V) ≤ 0.5:1 Vegetated Shear Stress D6460 ≥ 10.0 lbs/ft2 Material Mass per Unit Area D6566 ≥ 8.0 oz/yd2 Tensile Strength D6818 ≥ 175 lbs/ft UV Stability D4355 ≥ 80% Thickness D6525 ≥ 0.25 inch

Part 3 — Execution

3.1 Preparation

A.Complete all required grading, topsoil placement, and seeding in designated areas before installing RECP.
B.Make soil surface stable, firm, free of rocks, roots and other obstructions.
C.Install RECP within 24 hours after seeding.

3.2 Installation

A.Minimize disturbance of the prepared seedbed when installing RECP.
B.Install RECP according to manufacturer’s recommendations including any requirements to anchor RECP into the soil.
C.Unroll RECP parallel to the primary direction of flow and place it in direct contact with the soil.
1.Do not stretch the product or allow it to “tent” or bridge over surface inconsistencies during installation.
D.Within a channel, ditch or swale, install RECP to allow runoff to flow directly to the centerline of ditch, not undermining or bypassing the RECP.
E.Place additional staples in areas such as swales, base of humps, against rock outcrops and as required achieving maximum contact between RECP and the soil.

Get an email when 02376 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2027 Edition. Pages 323–326 of 1,343. View official source ↗

Ask about this section

Scoped to Utah 2027 Standard Specifications, Section 02376 — Rolled Erosion Control Products. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.