02896Boundary Survey

UT · 2027 Standard Specifications✓ Full text on BuildSpecRev. January 1, 2017Book pages 847–849 Save this section

Ask about Section 02896

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Part 1 — General

1.1 Section Includes

A.Provide boundary survey and plat.
B.Furnish and set right-of-way markers.

1.2 Related Sections

A.Section 03055: Portland Cement Concrete

1.3 References

A.ASTM A 53: Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
B.Utah Code 17-23-17

1.4 DEFINTIONS Not Used

1.5 SUBMITTALS Not Used

Part 2 — Products

2.1 Right-of-Way Markers

A.Pipe – Meet ASTM A 53, Schedule 40, Galvanized. Refer to GW Series Standard Drawings.
B.Cast bronze cap – Free from defects and constructed as shown in GW Series Standard Drawings.

2.2 Concrete

A.Class B concrete according to Section 03055.
B.May substitute higher class of concrete.

Part 3 — Execution

3.1 Right-of-Way Markers

A.Place right-of-way markers according to GW Series Standard Drawings. Stamp onto each right-of-way marker:
1.Right-of-way marker number.
2.Mark exact control point location to within 0.01 ft with center punch or “dimple.”
B.Tightly rivet cap to the pipe.

3.2 Boundary Survey

A.Provide record of survey plat by Utah licensed surveyor.
B.File mylar copy of plat with county surveyor, region, and Department’s Central Right-of-Way office.
C.Accuracy – Third Order and Class I (1/10,000).

3.3 Plat Compliance Requirements

A.Refer to Utah Code 17-23-17.
B.Department Design Process.
C.Show on the survey plat:
1.Survey coordinates accurate to 5 decimal places and elevations accurate to 2 decimal places on all right-of way markers.
2.Right-of-Way markers.
3.Adjacent quarter corners and section corners with bearings and distances along the section line to the control line from each adjacent corner.
4.Original highway control points (right-of-way markers).
5.Local city or county monuments.
6.Control line geometric information with reference ties to section and quarter corners.
7.Tabulate right-of-way markers showing right-of-way marker number, station, offset, elevation, and project coordinates on each record of survey map.
D.Compute and draw plat, stationing, and coordinates to the same units as the project drawings.
E.Deliver the survey plat to Engineer on a CD in MicroStation format.
F.Correction Factor – Show state plane to ground correction factor.
G.Show the latitude and longitude of the control line at the beginning and end of the project.

Get an email when 02896 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2027 Edition. Pages 847–849 of 1,343. View official source ↗

Ask about this section

Scoped to Utah 2027 Standard Specifications, Section 02896 — Boundary Survey. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.