Part 1 — General
1.1 Section Includes
A.Requirements for dust control and pre- wetting.
1.2 RELATED SECTIONS Not Used
1.3 REFERENCES Not Used
1.4 DEFINITIONS Not Used
1.5 SUBMITTALS Not Used
Part 2 — Products
2.1 Water
A.Free of dirt, silt, and other detrimental matter in adequate quantities for dust control and watering requirements.
2.2 Equipment
A.Water distribution system – Self-propelled, pressure distributor with a spray system, equipped with a positive shut -off control.
1.Pressure pump must have the capacity to apply the whole load uniformly.
B.Water truck – 1,000 U.S. gallons minimum capacity, with the capacity clearly and permanently marked on the tank.
1.Engineer may require Contractor to verify capacity.
Part 3 — Execution
3.1 Application
A.Apply water for dust control in quantities and locations as needed to maintain environmental compliance and pre- wet base materials .
1.Dust control may be required at any time.
2.Do not waste water.
Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 205–206 of 1,331.