B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Site Construction & Earthwork (02000-02999)

02056Embankment, Borrow, And Backfill

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. February 20, 2025Book pages 234–241 Save this section

Ask about Section 02056

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

EMBANKMENT, BORROW, AND BACKFILL

PART 1 GENERAL

1.1SECTION INCLUDES

A.Embankment, backfill, and bridge approach embankments.

1.2RELATED SECTIONS

A.Section 01572: Dust Control and Watering
B.Section 02721: Untreated Base Course (UTBC)
C.Section 03575: Flowable Fill

1.3REFERENCES

A.AASHTO M 145: Classification of Soils and Soil-Aggregate Mixtures for

Highway Construction Purposes

B.AASHTO T 11: Materials Finer than 75 μm (No. 200) Sieve in Mineral

Aggregates by Washing

C.AASHTO T 27: Sieve Analysis of Fine and Coarse Aggregates
D.AASHTO T 99: Moisture-Density Relations of Soils Using a 2.5 kg (5.5-lb)

Rammer and a 305 mm (12 inch) Drop

E.AASHTO T 180: Moisture-Density Relations of Soils Using a 4.54 kg (10-

lb) Rammer and a 457 mm (18 inch) Drop

F.UDOT Materials Manual of Instruction

G UDOT Minimum Sampling and Testing Requirements

1.4DEFINITIONS

A.Borrow material – imported material for use in a constructed fill or backfill.
B.Embankment material – suitable material from project roadway excavation

or other excavation for use in a constructed fill or backfill.

Embankment, Borrow, and Backfill

C.Well-graded material – Material having an even distribution of different

particle sizes. This even distribution of particles of different sizes results in a dense mass upon compaction.

1.5SUBMITTALS

A.Provide the following for information before delivering material to the

project:

1.Supplier and source of materials.
2.Gradation analysis. Refer to AASHTO T 27 and T 11.
3.Soil classification when applicable. Refer to AASHTO M 145.
4.Maximum Dry Density and Optimum Moisture Determination
a.Use AASHTO T 180 Method D for A-1 soils and AASHTO T

99 Method D for all other soils.

B.Requests, for review, to use Untreated Base Course (UTBC) instead of

granular borrow.

C.Engineering proposals for review for alternate materials or trench

configurations for drainage pipe bedding and pipe backfill as outlined in this Section, 2.2 G. Include all of the following:

1.Stamped drawings and specifications signed and sealed by a

Professional Engineer licensed in the state of Utah.

2.Evaluation of site specific conditions and surrounding soils,

including potential for migration of fines.

3.A structural evaluation of the pipe support system for the proposed

pipe that includes the pipe structural capacity and the depth of fill.

4.Complete bedding or backfill source information including

gradation, soil classification, and laboratory testing reports.

D.Proposals, for review, to place an initial layer of granular material as a

working platform.

1.6ACCEPTANCE

A.Acceptance sampling and testing is according to UDOT Minimum

Sampling and Testing Requirements.

B.The Engineer reserves the right to select and test material from any

location at the construction site.

1.The Engineer will establish the limits of nonconforming material

sampled non-randomly.

C.Remove nonconforming material and replace with acceptable material.

Embankment, Borrow, and Backfill

PART 2 PRODUCTS

2.1GENERAL

A.Provide materials free of contamination from chemical or petroleum

products for embankment, borrow, and backfill placements.

1.Materials may include recycled Portland Cement Concrete.
2.Do not include asphalt pavement materials.

2.2MATERIALS

A.Borrow
1.Classifications A-1-a through A-4. Refer to AASHTO M 145.
B.Granular Borrow
1.Classification A-1-a. Refer to AASHTO M 145.
2.Non-plastic.
3.Meet the gradation requirements of Table 1

Table 1 Granular Borrow Gradation Sieve Size Percent Passing 4 inch 100 3 inch 90 - 100 1 inch 60 - 100 1/2 inch 30 - 80 No. 4 25 - 65 No. 10 0 - 50 No. 40 0 - 30 No. 200 0 - 15

4.UTBC meeting the requirements of Section 02721, may be used, at

no additional cost to the Department, upon authorization of the Engineer.

C.Granular Backfill Borrow
1.Classification A-1-a. Refer to AASHTO M 145.
2.Well-graded, 2 inch maximum.
D.Free-Draining Granular Backfill
1.Meet the gradation requirements of Table 2:

Embankment, Borrow, and Backfill

Table 2 Free Draining Granular Backfill Gradation Sieve Size Percent Passing 1½ inch 90-100 1 inch 20-55 ¾ inch 0-15 ⅜ inch 0-5

E.Embankment for Bridge
1.Classification A-1. Refer to AASHTO M 145.
2.3 inch maximum.
F.Embankment Material
1.Roadway excavation and other excavation material.
a.Do not include unsuitable materials such as organic, frozen,

or contaminated soils.

b.Do not use rock or broken concrete materials with any

dimension over 1 ft.

2.Borrow may be substituted for embankment material.
G.Drainage Pipe Bedding and Drainage Pipe Backfill
1.Classification A-1. Refer to AASHTO M145.
a.Well-graded material.
b.Maximum aggregate size is 1½ inches for plastic pipe, 2

inches for all other pipes.

2.Flowable fill. Refer to Section 03575.
a.Use only for drainage pipe backfill.
3.Other materials or trench configurations for drainage pipe bedding

and backfill may be used when authorized.

a.Native materials or uniformly graded materials enclosed in

an appropriate drainage geotextile may be proposed.

PART 3 EXECUTION

3.1GENERAL

A.Complete clearing, grubbing, stripping, and stockpiling topsoil, and any

necessary excavation before placing material.

Embankment, Borrow, and Backfill

B.Requirements when placing material during freezing or snowy conditions:
1.Do not place embankment, borrow, or backfill material on frozen or

snow-covered areas.

a.Remove snow and frozen material and furnish specified

materials that can be compacted to the specified density. 1) Measure removed material and provide quantities to the Engineer. 2) The Department does not pay for removed material or material replacement when it would otherwise meet specification requirements if unfrozen.

2.Do not deliver or use frozen material.
C.Use appropriate compaction equipment adjacent to pipes, abutments,

back walls, approach slabs, wing walls, retaining walls, and other structures.

1.Expand the width of the trench to accommodate necessary

compaction equipment.

2.Compact by hand areas where compaction equipment cannot

compact the soil.

D.Compaction Requirements
1.Borrow, Drainage Pipe Bedding, Embankment Material,

Embankment for Bridge, Granular Backfill Borrow and Granular Borrow

a.Compact each lift to a minimum average of 96 percent of

maximum laboratory density with no single determination lower than 92 percent. 1) Use AASHTO T 180 Method D for A-1 soils and AASHTO T 99 Method D for all other soils to establish maximum laboratory density. 2) Maintain appropriate moisture for compaction during processing. Refer to Section 01572.

2.Drainage Pipe Backfill
a.Compact each lift to a minimum average of 92 percent

maximum laboratory density with no single determination less than 90 percent. 1) Use AASHTO T 180 Method D for A-1 soils. 2) Maintain appropriate moisture for compaction during processing. Refer to Section 01572.

b.Meet the pavement section material density requirement for

pipes that encroach into the pavement section or use flowable fill.

Embankment, Borrow, and Backfill

3.Material with more than 30 percent retained on the ¾ inch sieve
a.Compact each lift to 100 percent of the developed field

density. 1) The Department develops a field density compaction curve according to UDOT Materials Manual of Instruction Section 989.

4.Free-Draining Granular Backfill
a.Compact each lift to 100 percent of the developed field

density. 1) The Department develops a field density compaction curve according to UDOT Materials Manual of Instruction Section 989.

E.Place an initial layer of granular material to act as a working platform over

soft, wet ground when authorized by the Engineer.

1.Density requirements do not apply to the working platform except

as specified in this Section, Paragraph 3.2 B.

2.Meet density requirements for embankment, borrow, or backfill

placed above the working platform.

3.Do not place initial layer of embankment, borrow, or backfill until the

Engineer inspects and verifies the working platform or foundation.

3.2EMBANKMENT MATERIAL AND BORROW PLACEMENT

A.Place embankment material or borrow or both in the embankment section

with the highest quality material in the top portion of the embankment section.

B.Scarify and compact the top eight inches of the working platform or

foundation to at least 90 percent of maximum laboratory density when the embankment height is 6 ft or less.

C.Break and scarify all underlying concrete pavement surfaces so that

pieces do not exceed 1 ft2 before placing material over an existing concrete pavement surface that is outside the limits of removal or excavation shown.

1.Remove other pavement surfaces that are not portland cement

concrete.

D.Maintain Drainage
1.Grade and maintain the roadway to provide adequate drainage.
2.Maintain drainage pipes and drainage ditches or provide temporary

facilities when interrupting items such as irrigation systems, sewers, and under-drains.

Embankment, Borrow, and Backfill

E.Spread material uniformly in layers not exceeding 1 ft (uncompacted

depth) and compact to the density requirements.

1.Reduce the lift thickness or modify operations if tests show

unsatisfactory density.

2.Distribute larger particles so space exists for placing and

compacting remaining material.

3.Do not place rocks or broken concrete larger than 4 inches within 1

ft of the subgrade surface.

F.Finish subgrade surface within ±0.2 ft of line and grade.
G.Do not use compacting equipment that causes shear failure in the

constructed fill or backfill.

3.3GRANULAR BORROW, GRANULAR BACKFILL BORROW, AND BACKFILL

PLACEMENT

A.Compact material in maximum 6 inch layers (uncompacted depth) to the

density requirement.

B.Finish surface within ± 0.1 ft of line and grade.
C.Backfill catch basins, cleanout boxes, manholes, drainage boxes, and

diversion boxes with Granular Backfill Borrow unless otherwise specified or shown.

3.4DRAINAGE PIPE FOUNDATION, BEDDING, AND BACKFILL PLACEMENT

A.Place in 6 inch layers (uncompacted depth) and compact to the density

requirement.

B.Place uniform layers of drainage pipe backfill on both sides of the pipe and

compact to the density requirement before placing successive lifts.

C.Fully compact the haunch areas.

3.5EMBANKMENT FOR BRIDGE PLACEMENT

A.Construct bridge approach embankments from the existing ground up with

the specified material to the limits defined in this Section and according to GW Series Standard Drawings.

1.Approach Embankments
a.Place embankment for bridge beneath the bridge except

riprap or other described materials used for MSE walls.

Embankment, Borrow, and Backfill

b.Place embankment for bridge to extend at least 150 ft from

the centerline of the bridge abutment as measured along the approach roadway alignment and on the inside of abutments.

c.Use the described material throughout the length of the walls

where retaining walls are located beyond this delineation.

2.Intersecting Roadway Embankments
a.Place embankment for bridge along the intersecting roadway

alignment(s) at least 150 ft from the abutment centerline station as measured along the approach and intersecting alignments.

B.Spread embankment for bridge uniformly in layers not exceeding 1 ft

(uncompacted depth) and compact to the specified density requirements before placing the next layer.

1.Reduce the lift thickness if tests show unsatisfactory density.
C.Finish surface within ±0.2 ft of line and grade.

3.6FREE-DRAINING GRANULAR BACKFILL PLACEMENT

A.Compact material in 1 ft maximum layers.
B.Finish surface within ±0.2 ft of line and grade.

END OF SECTION

Embankment, Borrow, and Backfill

Get an email when 02056 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 234–241 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02056 — Embankment, Borrow, And Backfill. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.