STONE MATRIX ASPHALT (SMA)
PART 1 GENERAL
1.1SECTION INCLUDES
of aggregate, asphalt binder, hydrated lime, and other additives.
1.2RELATED SECTIONS
1.3REFERENCES
Cores)
Aggregates by Washing
Stone Matrix Asphalt (SMA)
Aggregate by Abrasion and Impact of the Los Angeles Machine
Magnesium Sulfate
Mixtures Using Saturated-Surface Dry Specimens
the Sand Equivalent Test
Mixtures
of Asphalt Mixtures
Drying
Tester
Wheel
Uncompacted Asphalt Mixtures
Aggregate
Thermal Insulation
Stone Matrix Asphalt (SMA)
1.4DEFINITIONS
target on a maximum of two sieves with the following limitations.
No. 8 or any coarser sieve is limited to 3 percent passing per sieve.
No. 50 sieves is 2 percent passing per sieve.
No. 200 sieve is 0.5 percent passing.
Section.
1.5SUBMITTALS
to the UDOT Materials Manual of Instruction 962.
gradation.
minor target change into production.
of any other change.
target changes and mix design volumetric requirements.
data or both are acceptable.
Instruction 962 for a volumetric mix design verification for anything other than approved minor target change.
binder source, or asphalt binder grade.
before placement. Stone Matrix Asphalt (SMA)
1.6ACCEPTANCE
Minimum Sampling and Testing Requirements.
with the following exceptions:
three samples if only three samples can be taken for the production day.
least three random samples cannot be taken. Take one sample for each 500 tons, or portion thereof, from the following day’s production.
day’s production if three random samples cannot be taken.
days when agreed upon in advance by both the Contractor and the Engineer when less than 900 tons are anticipated per production day.
sampling not more than 15 minutes before sampling.
required.
Refer to AASHTO R 67.
pavement for in-place density if the random location for coring falls within 1 ft of the edge of the overall pavement section (outer part of shoulders).
possession of the cores immediately, and begins testing the cores within 24 hours for density acceptance.
Maximum Specific Gravity
Gravity tests for each lot. Stone Matrix Asphalt (SMA)
1) The average thickness is not more than ½ inch greater or ¼ inch less than the total design thickness specified. 2) No individual sublot shows a deficient thickness of more than ⅜ inch.
thickness to remain in place or may order its removal. 1) The Department pays for 50 percent of the mix for material in excess of the +½ inch tolerance when excess thickness is allowed to remain in place. 2) Remove and replace the entire depth of the course if it is necessary to remove portions of the course.
sublots are deficient in thickness. 1) The Department pays for material necessary to reach specified thickness. 2) The Department pays for 50 percent of the mix for additional material over specified thickness necessary to achieve minimum lift thickness. 3) Minimum compacted lift is 3 times the nominal maximum aggregate size.
leveling courses. 1) Check final surfaces in stage construction.
checking thickness regularly with a depth probe during placement and taking corrective action as necessary.
Content, and In-Place Density. The Engineer computes Incentive/Disincentive for each lot.
In-place Density according to Table 1.
computation using Tables 2, 3, and 4.
and asphalt binder content for calculating the gradation/asphalt binder content incentive/disincentive.
does not pay incentives on gradation/asphalt binder content.
Stone Matrix Asphalt (SMA)
incentive for gradation/asphalt binder content.
leveling, and driveways.
500 tons.
to Section 02701.
is less than 60 percent.
percent.
ton, whichever is greater, will be assessed.
such as utility work, traffic signals, detours, lane leveling, and driveways, other hand work, or small projects with plan quantities less than 500 tons.
Incentive/Disincentive.
necessary to determine the material and workmanship meets the project requirements.
maintaining a roller pattern to obtain maximum density without over-stressing the pavement.
Stone Matrix Asphalt (SMA)
Table 1 Incentive/Disincentive for Asphalt Binder Content, and Density PT Based on Min. Four Samples Incentive/Disincentive (Dollars/Ton) >99 2.50 96-99 2.00 92-95 1.25 88-91 0.00 84-87 -0.26 80-83 -0.60 76-79 -0.93 72-75 -1.27 68-71 -1.60 64-67 -1.93 60-63 -2.27 <60 Reject Incentive/Disincentive for Gradation PT Based on Min. Four Samples Incentive/Disincentive (Dollars/Ton) >99 2.50 96-99 2.00 92-95 1.25 88-91 0.00 84-87 -0.26 80-83 -0.60 76-79 -0.93 72-75 -1.27 68-71 -1.60 64-67 -1.93 60-63 -2.27 56-59 -5.00 52-55 -10.00 <52 Reject
Table 2 Production Control for VMA and VCAMIX VMA VCAMIX Action Average Value, x, (%) Job-Mix Design Minimum of three Samples X ≥ 16.5 and X ≤18.5 VCAMIX < VCADRC Continue Paving X < 16.5 or X >18.5 0 < VCAMIX - VCADRC ≤ 0.5% Stop Production until a corrective action plan is approved X < 15.5 or X >19.5 0.5 < VCAMIX - VCADRC Stop Production and resubmit Mix Design
Stone Matrix Asphalt (SMA)
Table 3 Upper and Lower Limit Determination Parameter UL and LL /8” sieve for ½” SMA Target Value ± 5.0% #4 sieve Target Value ± 4.0% # 8 sieve Target Value ± 3.0% # 50 sieve Target Value ± 3.0% # 200 sieve Target Value ± 2.0% Asphalt Binder Content Target Value ± 0.35% Density Lower Limit: Target Value - 2.0% Upper Limit: Target Value + 3.5%
Enter table in the appropriate sample size column and round down to the nearest value.
Stone Matrix Asphalt (SMA)
Table 4 Quality Index Values (QU or QL) for Estimating Percent Within Limits PU or n=3 n=4 n=5 n=6 n=7 n=8 n=10 n=12 n=15 n=20 PL 100 1.16 1.50 1.75 1.91 2.06 2.15 2.29 2.35 2.47 2.56 99 1.16 1.47 1.68 1.79 1.89 1.95 2.04 2.09 2.14 2.19 98 1.15 1.44 1.61 1.70 1.77 1.80 1.86 1.89 1.93 1.97 97 1.15 1.41 1.55 1.62 1.67 1.69 1.74 1.77 1.80 1.82 96 1.15 1.38 1.49 1.55 1.59 1.61 1.64 1.66 1.69 1.70 95 1.14 1.35 1.45 1.49 1.52 1.54 1.56 1.57 1.59 1.61 94 1.13 1.32 1.40 1.44 1.46 1.47 1.49 1.50 1.51 1.53 93 1.12 1.29 1.36 1.38 1.40 1.41 1.43 1.43 1.44 1.46 92 1.11 1.26 1.31 1.33 1.35 1.36 1.37 1.37 1.38 1.39 91 1.10 1.23 1.27 1.29 1.30 1.31 1.32 1.32 1.32 1.33 90 1.09 1.20 1.23 1.24 1.25 1.25 1.26 1.26 1.27 1.27 89 1.08 1.17 1.20 1.21 1.21 1.21 1.21 1.21 1.22 1.22 88 1.07 1.14 1.16 1.17 1.17 1.17 1.17 1.17 1.17 1.17 87 1.06 1.11 1.12. 1.12 1.12 1.13 1.13 1.13 1.13 1.13 86 1.05 1.08 1.08 1.08 1.08 1.08 1.08 1.08 1.08 1.08 85 1.03 1.05 1.05 1.05 1.05 1.04 1.04 1.04 1.04 1.04 84 1.02 1.02 1.02 1.01 1.01 1.01 1.00 1.00 1.00 1.00 83 1.00 0.99 0.98 0.97 0.97 0.96 0.96 0.96 0.96 0.96 82 0.98 0.96 0.95 0.94 0.94 0.93 0.93 0.92 0.92 0.92 81 0.96 0.93 0.92 0.91 0.90 0.90 0.89 0.89 0.89 0.88 80 0.94 0.90 0.88 0.87 0.86 0.86 0.85 0.85 0.85 0.85 79 0.92 0.87 0.85 0.84 0.83 0.83 0.82 0.82 0.82 0.81 78 0.89 0.84 0.82 0.81 0.80 0.79 0.79 0.78 0.78 0.78 77 0.87 0.81 0.79 .0.78 0.77 0.76 0.76 0.75 0.75 0.75 76 0.84 0.78 0.76 0.75 0.74 0.73 0.72 0.72 0.72 0.72 75 0.82 0.75 0.73 0.72 0.71 0.70 0.69 0.69 0.69 0.68 74 0.79 0.72 0.70 0.68 0.67 0.67 0.66 0.66 0.66 0.65 73 0.77 0.69 0.67 0.65 0.64 0.64 0.62 0.62 0.62 0.62 72 0.74 0.66 0.64 0.62 0.61 0.61 0.60 0.59 0.59 0.59 71 0.71 0.63 0.60 0.59 0.58 0.58 0.57 0.56 0.56 0.56 70 0.68 0.60 0.58 0.56 0.55 0.55 0.54 0.54 0.54 0.53 69 0.65 0.57 0.55 0.54 0.53 0.52 0.51 0.51 0.51 0.50 68 0.62 0.54 0.52 0.51 0.50 0.50 0.48 0.48 0.48 0.48 67 0.59 0.51 0.49 0.48 0.47 0.47 0.46 0.45 0.45 0.45 66 0.56 0.48 0.46 0.45 0.44 0.44 0.43 0.42 0.42 0.42 65 0.53 0.45 0.43 0.42 0.41 0.41 0.40 0.40 0.40 0.39 64 0.49 0.42 0.40 0.39 0.38 0.38 0.37 0.37 0.37 0.37 63 0.46 0.39 0.37 0.36 0.35 0.35 0.35 0.34 0.34 0.34 62 0.43 0.36 0.34 0.33 0.33 0.33 0.32 0.31 0.31 0.31 61 0.39 0.33 0.31 0.30 0.30 0.30 0.29 0.29 0.29 0.28 60 0.36 0.30 0.28 0.27 0.26 0.26 0.25 0.25 0.25 0.25 59 0.32 0.27 0.25 0.25 0.24 0.24 0.24 0.23 0.23 0.23
Stone Matrix Asphalt (SMA)
Table 4 Continued PU/PL n=3 n=4 n=5 n=6 n=7 n=8 n=10 n=12 n=15 n=20 58 0.29 0.24 0.23 0.22 0.21 0.21 0.21 0.21 0.21 0.20 57 0.25 0.21 0.20 0.19 0.19 0.19 0.18 0.18 0.18 0.18 56 0.22 0.18 0.17 0.16 0.16 0.16 0.16 0.16 0.15 0.15 55 0.18 0.15 0.14 0.14 0.13 0.13 0.13 0.13 0.13 0.13 54 0.14 0.12 0.11 0.11 0.11 0.11 0.10 0.10 0.10 0.10 53 0.11 0.09 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 52 0.07 0.06 0.06 0.05 0.05 0.05 0.05 0.05 0.05 0.05 51 0.04 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Stone Matrix Asphalt (SMA)
Table 5 Definitions, Abbreviations, and Formulas for Acceptance Term Explanation Target Value (TV) The target values for gradation and asphalt binder content are given in the CONTRACTOR’s mix design. The target value for density is 94.0 percent of maximum (Rice) density.
Average (AVE) The sum of the lot’s test results for a measured characteristic divided by the number of test results, the arithmetic mean.
Standard Deviation (s) The square root of the value formed by summing the squared difference between the individual test results of a measured characteristic and AVE, divided by the number of test results minus one. This statement does not limit the methods of calculations of s; other methods that obtain the same value may be used.
Upper Limit (UL) The value above the TV of each measured characteristic that defines the upper limit of acceptable production. (Table 3)
Lower Limit (LL) The value below the TV of each measured characteristic that defines the lower limit of acceptable production. (Table 3)
Upper Quality Index (QU) QU = (UL - AVE)/s
Lower Quality Index (QL) QL = (AVE - LL)/s
Percentage of Lot Within UL Determined by entering Table 4 with QU. (PU)
Percentage of Lot Within LL Determined by entering Table 4 with QL. (PL)
Total Percentage of Lot (PL) PT = (PU + PL) - 100 Within UL and LL (PT)
Incentive/Disincentive Determined by entering Table 1 with PT or PL. Values for AVE, s, QU, and QL will be calculated to a minimum two decimal place accuracy that will be carried through all further calculations. Rounding to lower accuracy is not allowed.
1.7LABORATORY CORRELATION
project quality control testing using UDOT LQP qualified lab.
tests related to volumetric properties and the following background testing:
Stone Matrix Asphalt (SMA)
1) Maximum Theoretical Specific Gravity of Mix (Gmm), AASHTO T 209 2) Bulk Specific Gravity of Mix (Gmb), AASHTO T 166 3) Bulk Specific Gravity of Coarse Aggregates (Gsb), AASHTO T 85
meeting α = 0.05, for a minimum of two consecutive production days (UDOT Materials Manual of Instruction, Part 8, Appendix C).
received before disclosure of the QA testing results. This applies to paired t-test and all subsequent QA/QC testing data.
paired t-testing calculations and any corrections made to account for failed comparisons.
resolution.
1.8DISPUTE RESOLUTION
acceptance tests.
PART 2 PRODUCTS
2.1ASPHALT BINDER
509: Asphalt Binder
C Use the minimum asphalt binder content specified in Table 10 unless called out differently in 02742S for the project.
2.2AGGREGATE
stone, gravel, or slag.
Stone Matrix Asphalt (SMA)
Table 6 Test Method Test No. Specification One Fractured Face AASHTO T 335 100% min.
Two Fractured Face AASHTO T 335 90% min.
Fine Aggregate AASHTO T 304 45 min. Angularity
Flakiness Index UDOT MOI (Based on 3/8 inch and 25% max. above)
L.A. Wear AASHTO T 96 28% max.
Sand Equivalent AASHTO T 176 (Pre-wet method) 60 min.
Plasticity Index AASHTO T 89 and T 90 0 max. (Does not apply to Mineral Filler)
Unit Weight AASHTO T 19 75 lb/cu. ft. min.
Polishing* AASHTO T 278 and T 279 31 min.
Soundness (sodium AASHTO T 104 10% max. loss with five cycles sulfate)
Clay Lumps and AASHTO T 112 2% max Friable Particles
Natural Fines N/A 0 max.
* The Department has the right to waive this requirement if the aggregates have proven acceptable through successful past performance as determined by the Engineer.
Stone Matrix Asphalt (SMA)
Table 7 Control Sieve ½ inch 3 /8 inch Size
¾ inch 100 100 ½ inch 90 - 100 100 /8 inch 45 - 78 90 - 100 No. 4 20 - 28 26 - 50 No. 8 16 - 24 20 - 28 No. 16 13 - 21 13 - 21 No. 30 12 - 18 12 - 18 No. 50 12 - 15 12 - 15 No. 200 8 - 10 8 - 10
2.3ADDITIVES / STABILIZERS
treated with a cationic sizing agent to enhance disbursement of the fiber as well as increase adhesion of the fiber surface with the asphalt binder and control drain-down. Meet AASHTO M 325.
of the total mix.
Passing No. 60 sieve 90 – 100 percent Passing No. 230 sieve 65 – 100 percent
weight of total mix.
Stone Matrix Asphalt (SMA)
maximum passing the No. 100 sieve 70 percent (± 10 percent).
No. 20 sieve 85 percent (± 10 percent) No. 40 sieve 65 percent (±10 percent) No. 140 sieve 30 percent ± 0 percent)
Consists of finely divided mineral matter such as rock dust, slag dust, hydrated lime, hydraulic cement, fly ash, or other suitable mineral matter. Free flowing and free of lumps.
Table 8 Sieve Size Percent Passing No. 30 100 No. 50 95 – 100 No. 200 55 – 100 No. 450 40 max.
hydraulic cement)
2.4JOB-MIX DESIGN
Instruction 962.
paving.
Table 9 Mix Design Compaction Parameters Design Gyrations % of Gmm* 100 96.5 * Gmm: Maximum theoretical specific gravity of mix.
Stone Matrix Asphalt (SMA)
Table 10 Minimum Asphalt Binder Content Combined Aggregate Bulk Specific Gravity Minimum Asphalt Including Lime Binder Content %* Gsb 2.375 - 2.424 6.8 2.425 - 2.474 6.7 2.475 - 2.524 6.6 2.525 - 2.574 6.5 2.575 - 2.624 6.3 2.625 - 2.674 6.2 2.675 - 2.724 6.1 > 2.724 6.0 * Percent of total mix.
Table 11 Mix Design Requirements SMA design mixing and compaction Provided by the Engineer temperatures Voids in Mineral Aggregate (VMA) 17.0% min. AASHTO R 46, using Gsb. Equation based on percent of total mix. Voids In Course Aggregate (Stone Matrix VCAMIX < VCADRC Asphalt Mix Design) Hamburg Wheel Tracker < 10.00 mm at 20,000 Cycles. Draindown (AASHTO T 305) 0.30 max.
Instruction 962.
2.5CONTRACTOR INITIATED CHANGES IN STONE MATRIX ASPHALT MIX
DESIGN
incorporating changes into production.
Stone Matrix Asphalt (SMA)
target changes and mix design volumetric requirements. Department acceptance or Contractor QC testing data is acceptable.
gyratory specimens run at the new target gradation, asphalt binder content, or both.
for field verification.
provides written concurrence of the verified field volumetric mix design if the field volumetric mix design meets the volumetric requirements.
qualified by UDOT Central Materials if the field volumetric mix verification does not meet the volumetric requirements.
project without penalty to the Contractor.
target change.
verifications at no cost to the Contractor.
laboratory or field verification required including all laboratory or field volumetric mix design verifications required due to contractor initiated target changes.
aggregate source, asphalt binder source, or grade.
verified by the Resident Engineer in consultation with the Region Materials Engineer.
PART 3 EXECUTION
3.1SMA
percent by weight.
Stone Matrix Asphalt (SMA)
aggregate.
certified supplier to cover the costs of inspection.
Management Plan 514 Hot-Mix Asphalt.
percent of the particles retained on the No. 4 sieve.
not properly coated.
defined on Volumetric Mix Design Verification Letter.
3.2SMA PLANT
a daily basis.
to the mix design.
the tank at any time.
tanks.
aggregate feed or weigh system to maintain correct proportions and uniform distribution for all rates of production and batch sizes.
controls.
into the mixer. (8 to 12 seconds)
Stone Matrix Asphalt (SMA)
the plant.
aggregate feed or weigh system to maintain correct proportions and uniform distribution for all rates of production and batch sizes.
controls.
the mixer.
the plant.
3.3CEASE PRODUCTION
the following criteria:
percent.
continues indicating the changes in production procedures that will be implemented to correct the deficiencies.
directive.
continues.
3.4SURFACE PREPARATION
gutter, and other components affected by the paving operations.
from the prepared surface before placing the mix.
Refer to Section 02748.
Stone Matrix Asphalt (SMA)
3.5SURFACE PLACEMENT
to be paved when full-width or echelon paving is impractical and more than one pass is required.
center of the lane at the direction of the Engineer, but never in a wheel path.
specification if the lift is 2 or more inches thick.
and uniform longitudinal lines and neat vertical edges.
steady paver speed is maintained.
the uncompacted end or edge of freshly placed mix until the mat temperature drops to a point where damage or differential compaction will not occur.
(horizontal to vertical).
portion of the pass that contains the tapered end.
compacted mix.
an MTV that internally performs additional mixing of the SMA mix and then deposits material into the paver at a uniform temperature and consistency.
an MTV is impractical, placements such as utility work, traffic signals, detours, lane leveling, and driveways, side street tie-ins, other hand work, or small projects with plan quantities less than 500 tons.
3.6COMPACTION
structures.
Stone Matrix Asphalt (SMA)
the lay-down machine and assuring proper mix design placement temperatures.
3.7LIMITATIONS
the Engineer for all equipment and hand tools used to mix, haul, and place the SMA.
or when roadway surface is icy or wet.
the shade and the roadway surface temperature are above 50 degrees F.
these dates and temperature.
limits.
END OF SECTION
Stone Matrix Asphalt (SMA)
Get an email when 02744 changes
Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.